

Chunhua Wu
Marketing and Behavioural Science, UBC Sauder School of Business, University of British Columbia.
Prepared for the Robert H. Lee Graduate School opening week session on artificial intelligence in the classroom, 3 September 2026. Figures verified to 2 September 2026.
How this book was made. The research was gathered by fourteen artificial intelligence research agents working in parallel, one per dimension, each producing a written brief, a machine-readable dataset and a folder of downloaded primary documents. Roughly five hundred searches were run and 884 files totalling 716 megabytes were saved. The charts are generated directly from the datasets. The framing, the ordering, the judgement calls and any errors are the author's. Appendix A sets out the method and its limits in full.
On accuracy. Where sources disagree, the disagreement is reported rather than resolved. Where a figure could not be verified it is marked as contested. Before quoting any number from this book in your own work, open its source. Appendix G lists all 534 of them.
Rights. Third-party material is reproduced with attribution under fair dealing for the purpose of education and research. This document is prepared for course use and is not for redistribution or commercial publication. Source documents remain the property of their publishers.
Developed with the assistance of Anthropic's Claude. Typeset from Markdown and JSON by
research/book/build_book.py.
This book began as a classroom exercise. On 3 September 2026 the incoming Full-time MBA, Master of Management and Master of Business Analytics cohorts at the UBC Sauder School of Business were given twenty-five minutes, a team of four and any artificial intelligence tool they liked, and asked one open question: the wave of artificial intelligence data centres is coming to Canada, so what should it mean for Canada, and for whom?
It seemed only fair to do the exercise myself. This book is the result. Fourteen research agents worked in parallel, one per dimension of the question, each producing a written brief, a machine-readable dataset and a folder of downloaded primary documents. Between them they ran roughly five hundred searches, saved 884 files and 716 megabytes of source material, and recorded every figure with a link. What you are reading is those fourteen briefs, edited into a single argument, with the charts and the connective tissue added.
I want to be exact about what that means, because the method is part of the subject. The research was gathered by machines. The framing, the ordering, the judgement calls and the errors are mine. Where two sources disagreed, the disagreement is reported rather than resolved. Where a number could not be verified, it is marked as contested rather than quietly dropped. Two of the scores that appear in the companion software are explicitly labelled as my judgement rather than published data, and the reasoning is shown beside them. Readers who want to check anything will find the full source for every figure in Appendix G.
The subject deserves that care, because it is moving quickly and it is being argued about badly. In the fifteen months to August 2026 the Alberta Electric System Operator's data-centre connection queue was reported at 16.2, 19.6 and 20.7 gigawatts by three different counters on three different dates. All three numbers are true of the moment they describe. Quoted without a date, any of them is misleading. Much of the public conversation about data centres in Canada consists of numbers quoted without their dates.
There is a second reason for care. A great deal of what has been announced will not be built. Roughly twenty-one gigawatts of Canadian capacity has been announced or proposed; about two point three gigawatts is actually under construction. The federal government's own documents say most of the proposed pipeline is not expected to proceed. An argument built on the announcement number and an argument built on the construction number are arguments about different countries.
The book is organised in three parts. Part I sets the global picture and the physics, because you cannot argue about megawatts without knowing what one is. Part II is Canada on the ground: the projects, the rules and the ledger of costs and benefits. Part III is the strategic frame: the border, the inheritance and the money. The appendices hold the inventory, the timelines, a glossary and every source.
My own conclusion, which readers are free to reject, appears at the end of the executive summary. The students were not asked to reach it. They were asked to reach one they could defend.
Chunhua Wu
Marketing and Behavioural Science, UBC Sauder School of Business
Vancouver, September 2026
Artificial intelligence has to live somewhere. That somewhere is a building full of processors that consumes electricity, water, capital and land, and it has to be built in a specific place, under a specific government, on a specific grid. The question of where those buildings go is now one of the larger industrial questions in the world, and Canada is unusually well placed to answer it and unusually unprepared to.
World data-centre electricity consumption was about 415 terawatt hours in 2024 and 485 in 2025, and the International Energy Agency's base case puts it near 945 by 2030. The growth alone is roughly another Japan. Forecasts keep being revised upward: BloombergNEF's estimate of American data-centre demand in 2035 went from 78 gigawatts in April 2025 to 106 in December to 194 in July 2026. The four largest hyperscale operators plan about 725 billion United States dollars of capital spending in 2026, up from 410 billion in 2025, and almost a third of it is now debt funded, against nine per cent two years earlier.
The constraint has moved. It is no longer processors. It is electricity, and the iron that delivers it. A power transformer takes about 160 weeks. A large gas turbine takes about five years. Average grid connection in the Americas takes five years. Capacity that exists is essentially full: North American vacancy has sat near one per cent for three years, and ninety-five per cent of the sixty-six gigawatts under construction is already leased.
Canada's advantage is specific and measurable. Six of the seven cheapest large-power cities in North America are Canadian: Winnipeg at 5.09 cents per kilowatt hour, Montreal at 5.52, Vancouver at 6.72, against Toronto at 12.66 and New York at 22.88. Seventy-eight per cent of Canadian generation is non-emitting. The prairie cities sit at or below fifteen degrees for nine months of the year, which is free cooling. The country is politically stable and legally predictable, and it is not the United States, which since 2025 has become a commercial argument in itself.
There is almost no spare room. Every large province is now rationing rather than recruiting. British Columbia caps new data-centre load at 400 megawatts over two years and 145 megawatts per project, written into regulation, against about 800 megawatts requested. Quebec requires a ministerial decision for any load above five megawatts and has asked its regulator to charge data centres about 13 cents per kilowatt hour, roughly double the general large-power rate. Ontario makes data centres pay the full cost of their grid impact and screens every connection at the minister's desk. Alberta received requests near twenty thousand megawatts against a record provincial peak of 12,785 and allocated 1,200 megawatts of firm capacity in total, all of which went to two projects.
The consequence is the central fact of this book. The only route to gigawatt scale in Canada this decade is to build your own power station, and the only province that will let you is the one whose grid runs at about 490 grams of carbon dioxide per kilowatt hour. Meta's campus in Sturgeon County, Alberta, is the template: thirteen billion dollars, one gigawatt, groundbreaking in July 2026, with its own 932 megawatt gas plant. Canada's cleanest power and Canada's only buildable gigawatt sit in different provinces. A one gigawatt campus on the Alberta grid emits about 3.9 megatonnes of carbon dioxide a year. The same machine in Quebec emits about 0.01. That is a factor of nearly three hundred, decided entirely by which province signs the contract.
The investment is real and large: Meta's project alone is about 17.6 billion Canadian dollars including its power plant, with roughly 250 million a year in provincial revenue and 40 million in municipal tax by government estimate, and a 60 million dollar community package. The employment case is much weaker: about thirty permanent jobs per hundred megawatts, against construction crews ten to a hundred times larger that then leave. Electricity costs can be shifted onto other customers, as they were in one American capacity auction to the tune of 6.5 billion dollars. This asymmetry, large capital and tax against small permanent employment, is why the argument is so often about whether the community got a fair price rather than about technology.
Communities have begun to answer. Rocky View County refused a campus and later imposed a moratorium. Mississauga and Oakville paused approvals. The Alberta Utilities Commission refused a 1.4 gigawatt gas plant at Olds. Manitoba's premier dropped a proposal after a petition gathered more than thirteen thousand signatures. There were coordinated demonstrations in fourteen cities in June 2026. Social licence is no longer a communications problem; in several provinces it is the binding constraint.
The first is the bubble. Bain estimates that artificial intelligence needs about two trillion dollars of annual revenue by 2030 to fund the compute being built, and will fall roughly 800 billion short. A widely cited study from MIT found that ninety-five per cent of enterprise pilots produced no measurable profit. The International Energy Agency notes that only about a fifth of American grid connection requests ever materialise. A province that builds transmission for a load that never arrives has made an expensive mistake, which is precisely why Ontario and Alberta now make the developer carry that risk.
The second is repricing. Canada's advantage is the price of firm clean power, and Canada is in the process of raising it. If Quebec's proposed 13 cent rate takes effect, the country's cheapest clean electricity becomes roughly as expensive as Ontario's, and much of the arithmetic in Chapter 8 changes. Any recommendation that rests on 5.5 cents should say what happens at 13.
Canada is not choosing whether artificial intelligence happens. It is choosing what to charge, in money and in conditions, for firm clean power delivered soon. That is the only thing the build-out needs which it cannot easily get elsewhere, and it is a genuinely scarce asset that Canada has been in the habit of selling cheaply.
The provinces that are rationing are not being obstructive. They are discovering that they own something valuable and are working out the price. The open question is whether they charge for it in dollars, which is easy, or in conditions such as clean supply, community benefit, Indigenous equity, demand flexibility and domestic compute access, which is harder and worth more.
Four answers are defensible on this evidence, and they disagree about weights rather than facts. Alberta is the only province that can deliver scale this decade, and the price is carbon and contested local consent. Quebec has the cleanest and cheapest firm power and is rationing it, so it suits a hundred-megawatt project and not a gigawatt one. Ontario has the largest system, a nuclear build-out and the customers, and it charges full freight and takes three to five years. And not building at all is defensible too: leasing capacity rather than owning it may be the right call if the revenue does not arrive.
For a student, an investor or a minister, the useful discipline is the same. Name the number your case depends on. Say which date and which counter it came from. Then say what would have to be true for you to change your mind.
Each of the eight chapters follows the same shape, so the book can be read straight through or opened at any point.
The research in this book was gathered by artificial intelligence and has been checked, but not exhaustively. Several claims were found to be unverifiable during preparation and are marked as such. Before you put any figure from this book into your own work with your name on it, open the source.
What is being built, and why the numbers are so large. A data centre is a building full of servers; AI has filled it with racks of accelerators such as Nvidia graphics processing units (GPUs) that draw far more power per rack. A terawatt-hour (TWh) measures energy used over time: one TWh is one billion kilowatt-hours, and 415 TWh, the IEA's estimate of data-centre electricity in 2024, is roughly 1.5% of everything the world consumed that year. A gigawatt (GW) measures power drawn at an instant: 1 GW is 1,000 megawatts (MW), about the output of a large nuclear reactor, and a 100 MW data centre running all year uses roughly the electricity of 100,000 households (IEA 2025). Capacity figures from real-estate firms are usually expressed in MW of "critical IT load", the power available to servers; total power drawn is higher by the facility's power usage effectiveness (PUE), the ratio of total energy to server energy, typically 1.1 to 1.5.
Demand. The IEA's April 2025 Energy and AI report set the reference numbers: 415 TWh in 2024, rising about 15% a year to 945 TWh in 2030 and 1,200 TWh in 2035 in its Base Case, with 2035 scenarios spanning 700 to 1,720 TWh. Its April 2026 update reported 485 TWh in 2025, a 17% rise, with AI-focused facilities up 50%, and left the 2030 figure at about 950 TWh. The United States dominates (45% of 2024 consumption, 180 TWh), followed by China (25%) and Europe (15%). US-specific work by Lawrence Berkeley National Laboratory (LBNL) shows the acceleration: the December 2024 report had 176 TWh in 2023 (4.4% of US electricity) and 325 to 580 TWh by 2028; the 2025 Update, published in 2026, has 192 TWh in 2024 and a 649 TWh Reference Case for 2030 (11.8%), with data centres supplying a third of all US load growth this decade. The important nuance is between energy and peak power: utilities plan for peak demand, and the aggregate five-year peak forecast filed by US utilities has risen six-fold since 2022 to 166 GW, about 90 GW of it data centres (Grid Strategies, November 2025).
Capacity and markets. Real-estate data describe what has actually been built. JLL counts about 103 GW of data-centre capacity worldwide at the start of 2026 and expects 200 GW by 2030, with the Americas holding half and the US about 90% of the Americas. Cushman & Wakefield's 2026 comparison shows the pipeline's scale: 43.4 GW operating in the Americas, 25.3 GW under construction and 191.3 GW planned. The market has no slack. "Vacancy" is the share of built capacity available to lease; "absorption" is the amount newly leased; "pre-leasing" means signing tenants before a building is finished. North American vacancy has been about 1% for three years, H1 2026 absorption doubled to 25 GW, and 95% of the 66 GW under construction is already committed, so tenants signing today are getting 2028 deliveries (JLL Midyear 2026); Northern Virginia, the world's largest market, had 0.3% vacancy in Q1 2026 (CBRE). Hyperscalers, the largest cloud and internet companies, now run 1,360 large data centres and hold 48% of all capacity, heading to 67% by 2031 (Synergy Research). Outside North America the story is one of clusters and constraints: Johor in Malaysia and Mumbai in India are growing fastest; Ireland, where data centres take 22% of electricity, only ended a four-year connection moratorium in December 2025 by requiring new sites to bring their own generation and 80% renewables; Amsterdam allows no new data centres; the Gulf is building the 5 GW UAE-US AI campus with a 1 GW Stargate cluster.
Money. Four companies, Amazon, Alphabet, Microsoft and Meta, spent about USD 410 billion of capital expenditure (capex, spending on long-lived assets) in 2025 and guide to about USD 725 billion in 2026; with Oracle the IEA counts more than USD 400 billion in 2025 and a 75% rise. Nvidia's data-centre revenue was USD 193.7 billion in its fiscal 2026 and USD 89.0 billion in the quarter to July 2026. The money is increasingly borrowed: FactSet finds debt funded 32% of hyperscaler capex in the last twelve months versus 9% in fiscal 2024, and JLL counts USD 250 billion of AI-related bonds in the first half of 2026. Flagship projects show the gap between announcement and operation: OpenAI's Stargate has more than 9 GW planned by 2029 but only 0.3 GW operating in April 2026.
The shortages. Chips were the first bottleneck and are still tight at the memory layer: high-bandwidth memory (HBM), the stacked memory bonded to each AI accelerator, is sold out at Micron and SK hynix through 2026, and the IEA expects the shortage to last through at least end-2027, capping AI-server additions at roughly 25 GW a year. Power has become the binding constraint, captured in the industry phrase "time to power". An interconnection queue is the waiting list on which a utility or grid operator studies requests to connect large new loads or generators; in PJM, the grid covering 13 US states around Northern Virginia, AI projects entering service in 2025 waited more than seven years from request to operation, and Cushman & Wakefield puts average connection times at 5.0 years in the Americas. Behind the queue sit physical shortages: GE Vernova's gas-turbine backlog and reservations reached 116 GW with new orders delivering in 2031; large power transformers take more than 160 weeks and cost 77% more than in 2019; more than 60% of operators report difficulty hiring, and electricians are the tightest trade. Water and permitting add local friction: US data centres consumed 66 billion litres of water directly in 2023 and about 800 billion litres indirectly through the power they used, and LBNL expects hyperscale sites alone to use 60 to 124 billion litres in 2028; a JLL survey found only 14% of Americans support a data centre near them.
The demand gap. Put the two halves together and a gap appears. Demand-side models (McKinsey 219 GW of capacity demand by 2030; Bain 200 GW of incremental AI compute by 2030; Epoch AI's finding that frontier training compute grows four to five times a year) exceed what the supply side can plausibly deliver (JLL's 200 GW of total capacity by 2030 in its base case, HBM at 25 GW a year, turbines booked to 2031). Bain frames the gap financially: USD 2 trillion of annual AI revenue would be needed by 2030 to fund the build, and it expects an USD 800 billion shortfall. BloombergNEF sees a 19 GW US power shortfall even at record connection rates. For a country with spare clean electricity and land, the implication is that power delivered within two to three years is now worth more than cheap power delivered in seven.
Where Canada fits. Canada ranks fifth in the world by number of data centres (337) but is small by capacity: about 1.4 GW live against 40.6 GW in the US. The pipeline is disproportionate: DC Byte counts 10.3 GW across all stages, and federal documents list 20 to 22 GW of proposed projects, more than 18 GW of them in Alberta, against a government estimate that the country needs 5.5 GW of AI compute by 2030 and a warning that most proposals will not proceed. The advantage is cheap, clean power in the hydro provinces: Montreal's large-power rate of 5.55 cents per kWh compares with 12.01 in Houston and 18.07 in New York, and Vancouver (7.91) and Toronto (8.88) also undercut most US hubs, though Calgary and Edmonton were above 23 cents in the 2023 comparison. The constraint is allocation and time to power. Alberta received more than 20 GW of connection requests, more than its peak demand, and capped interim connections at 1,200 MW to 2028, pushing developers toward "bring your own generation". BC Hydro is releasing just 400 MW over two years. Quebec, where data-centre load is expected to rise from 200 MW to more than 1,000 MW by 2035, proposes to charge data centres 13 cents per kWh, about double its industrial rate, from late 2026. Canada's opportunity is therefore less about total scale than about whether it can convert a small number of large, well-sited, quickly powered projects while the global gap is widest.
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Data-centre electricity consumption | 415 | TWh | 2024 | Global | IEA, Energy and AI (Apr 2025) |
| Data-centre electricity consumption (+17% y/y) | 485 | TWh | 2025 | Global | IEA, Key Questions on Energy and AI (Apr 2026) |
| Data-centre consumption, Base Case | 945 (about 950 in 2026 update) | TWh | 2030 | Global | IEA (Apr 2025) |
| Data-centre consumption, 2035 cases | 700 (Headwinds), 1,200 (Base), 1,720 (Lift-Off) | TWh | 2035 | Global | IEA (Apr 2025) |
| Regional shares of data-centre electricity | US 45, China 25, Europe 15 | % | 2024 | Global | IEA (Apr 2025) |
| Global electricity demand growth, 2026-2030 average | 3.6 | % per year | 2030 | Global | IEA, Electricity 2026 |
| Share of US data-centre connection requests that materialise | about 20 | % | 2026 | United States | IEA, Electricity 2026 |
| US data-centre electricity use | 176 (4.4% of US) | TWh | 2023 | United States | US DOE / LBNL (Dec 2024) |
| US data-centre electricity use, 2028 range | 325-580 (6.7-12.0% of US) | TWh | 2028 | United States | US DOE / LBNL (Dec 2024) |
| US data-centre electricity use, 2025 Update | 192 (4.7%) in 2024; 649 (11.8%) Reference Case, range 521-843 | TWh | 2030 | United States | LBNL 2025 Update (2026) |
| Data-centre share of US electricity | 9-17 (4-5 today) | % | 2030 | United States | EPRI Powering Intelligence 2026 |
| Utility five-year peak load growth forecast | 166 (about 90 from data centres) | GW | 2030 | United States | Grid Strategies (Nov 2025) |
| Ten-year summer / winter peak growth | 224 / 246 | GW | 2035 | US and Canada (NERC) | NERC 2025 LTRA via Utility Dive (Jan 2026) |
| BNEF US data-centre demand, by edition | 78 (Apr 2025), 106 (Dec 2025), 194 (Jul 2026) | GW | 2035 | United States | BNEF via Tom's Hardware/Yahoo (Jul 2026) |
| US data-centre power demand (AI share) | 33 (12%) in 2024; 176 (70%) in 2035 | GW | 2035 | United States | Deloitte (Jun 2025) |
| Ireland data-centre share of metered electricity | 22 | % | 2024 | Ireland | IEA, Electricity 2026 |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Global data-centre power demand | 55 (2023), 84 (2027), 122 (2030) | GW | 2030 | Global | Goldman Sachs via APPA (Feb 2025) |
| Global capacity demand (AI portion) | 82 (44) in 2025; 219 (156) in 2030 | GW | 2030 | Global | McKinsey via The Data Score (Feb 2026) |
| Global capacity, all segments | 103 today; 200 by 2030 | GW | 2030 | Global | JLL 2026 Global Data Center Outlook |
| Americas capacity: operating / under construction / pipeline | 43.4 / 25.3 / 191.3 | GW | 2026 | Americas | Cushman & Wakefield (May 2026) |
| EMEA capacity: operating / under construction / planned | 11.4 / 2.7 / 12.1 | GW | 2026 | EMEA | Cushman & Wakefield (May 2026) |
| APAC capacity | 32 (2025) to 57 (2030) | GW | 2030 | Asia-Pacific | JLL (Jan 2026) |
| Hyperscale data centres in operation (pipeline) | 1,360 (about 800) | facilities | 2025 | Global | Synergy Research (Apr 2026) |
| Hyperscale share of capacity (2031) | 48 (67) | % | 2025 | Global | Synergy Research (Apr 2026) |
| North America absorption H1 2026 / under construction / pre-committed | 25 / 66 / 95 | GW, GW, % | 2026 | North America | JLL Midyear 2026 (Aug 2026) |
| US primary markets: inventory, vacancy, absorption | 9,432 MW, 1.4%, 2,497.6 MW | MW, %, MW | 2025 | US eight primary markets | CBRE H2 2025 (Feb 2026) |
| Northern Virginia inventory / vacancy | 4,182 / 0.3 | MW / % | Q1 2026 | Northern Virginia | CBRE Global Data Center Trends 2026 (Jun 2026) |
| Vacancy Europe / Asia-Pacific | 7.3 / 7 | % | Q1 2026 | Europe, APAC | CBRE (Jun 2026) |
| Malaysia capacity (Johor pipeline) | 2,055 by end-2026 (Johor 2,700 in pipeline) | MW | 2026 | Malaysia | The Edge Malaysia / JLL (Apr 2026) |
| India capacity | 1.7-2.0 (2026); about 6 (2029) | GW | 2029 | India | Business Today / Vestian (Apr 2026) |
| Stargate UAE cluster (first phase) | 1 GW (200 MW due Q3 2026) inside a 5 GW campus | GW | 2026 | UAE | The National (Dec 2025) |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Combined capex, Microsoft + Alphabet + Amazon + Meta | 226 (2024), 410 (2025), about 725 (2026 guidance) | USD billion | 2026 | Global | Yahoo Finance (Jun 2026) |
| 2026 guidance by company | Amazon 200; Alphabet 180-190; Meta 125-145; Oracle about 50 | USD billion | 2026 | Global | FactSet (Jul 2026), Futurum (Feb 2026) |
| Microsoft capex incl. finance leases, fiscal 2026 | 115.9 | USD billion | FY to Jun 2026 | Global | Microsoft (Jul 2026) |
| Five-hyperscaler capex, calendar 2026 incl. leases and prepayments | about 800 | USD billion | 2026 | Global | FactSet (Jul 2026) |
| Debt-funded share of hyperscaler capex | 32 (9 in FY2024) | % | 2026 | Global | FactSet (Jul 2026) |
| Nvidia Data Center revenue | 193.7 (fiscal 2026); 89.0 (Q2 fiscal 2027, +117%) | USD billion | 2026 | Global | Nvidia (Aug 2026) |
| Stargate: planned by 2029 / operating | more than 9 / 0.3 | GW | 2026 | United States | Epoch AI (Apr 2026) |
| Nvidia-OpenAI letter of intent | 10 GW, up to USD 100 billion | GW | 2025 | Global | NBC News (Oct 2025) |
| xAI Colossus (Memphis) | about 1.5 operating, 2 target | GW | 2026 | United States | Introl (Jan 2026) |
| Meta Hyperion (Louisiana) | 1.5 by end-2027, scaling to 5 | GW | 2027 | United States | Data Center Frontier (Aug 2025) |
| AI revenue needed / shortfall in 2030 | 2,000 / 800 | USD billion | 2030 | Global | Bain (Sep 2025) |
| GenAI pilots with no measurable P&L impact | 95 | % | 2025 | Global | MIT NANDA (Aug 2025) |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| GE Vernova gas-turbine backlog plus slot reservations | 83 (end-2025), 100 (Q1 2026), 116 (Q2 2026); deliveries booked to 2031 | GW | 2026 | Global | Utility Dive (Jul 2026) |
| Gas-turbine orders growth | 70 | % | 2025 | Global | IEA (Apr 2026) |
| Power-transformer lead time | 50 (2021), 120 (2024), 150 (2025), 160+ (2026) | weeks | 2026 | United States | Data Center Knowledge (May 2026) |
| Power-transformer price increase since 2019 | 77 | % | 2025 | United States | POWER Magazine (Jan 2026) |
| Average grid connection time | 4.4 global; 5.0 Americas; 5.2 EMEA; 2.7 APAC | years | 2026 | Global | Cushman & Wakefield (May 2026) |
| PJM: time to operation for AI projects entering service in 2025 | more than 7 (3+ to agreement, 4+ after) | years | 2025 | PJM | Data Center Knowledge (May 2026) |
| PJM large-load adjustment requests | 54 (95 requests) | GW | 2025 | PJM | Data Center Knowledge (May 2026) |
| PJM capacity-market cost | 2.2 (2023) to 16.1 (2025) | USD billion | 2025 | PJM | Canary Media (Nov 2025) |
| HBM supply limit on AI servers | about 25 per year through 2027 | GW | 2027 | Global | IEA (Apr 2026) |
| HBM market share (SK hynix / Micron / Samsung) | 62 / 21 / 17 | % | Q2 2025 | Global | Barrack AI compilation (Mar 2026) |
| Data-centre providers reporting hiring difficulty | more than 60 | % | 2026 | United States | BRG ThinkSet (2026) |
| US data-centre direct water consumption | 21.2 (2014); 66 (2023); hyperscale sites alone 60-124 expected (2028); indirect via electricity about 800 (2023) | billion litres | 2028 | United States | LBNL (Dec 2024) |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Live data-centre IT capacity, Canada vs US | 1.4 (Sep 2025) vs 40.6 (early 2026) | GW | 2025 | Canada, US | BLG (Jul 2026) |
| Canada total pipeline (all stages) | 10.3 (more than 75% early stage or committed) | GW | Q2 2025 | Canada | DC Byte (Sep 2025) |
| Share of Canadian IT load in Toronto, Montreal and Alberta | 93 | % | 2025 | Canada | DC Byte (Sep 2025) |
| AI data-centre capacity operating / proposed (Alberta share) | 337 MW / 20-22.1 GW (Alberta more than 18 GW) | MW, GW | 2026 | Canada | Canadian Press via Daily Commercial News (Jul 2026) |
| Federal estimate of AI compute needed by 2030 | 5.5 | GW | 2030 | Canada | Canadian Press (Jul 2026) |
| Data centres by count (rank) | 337 (5th; US 5,427) | facilities | Nov 2025 | Canada | Cargoson / Cloudscene (Jan 2026) |
| Toronto / Montreal rank in Cushman & Wakefield Americas lists | 8th primary / 5th secondary | rank | 2026 | Canada | Cushman & Wakefield (May 2026) |
| Alberta connection requests vs interim cap | more than 20,000 vs 1,200 (to 2028) | MW | 2025 | Alberta | AESO (Sep 2025) |
| BC Hydro capacity for data centres (two years from Feb 2026) | 400 (145 per project cap) | MW | 2026 | British Columbia | BLG (Jul 2026) |
| Quebec data-centre load today / 2035 | 200 / more than 1,000 | MW | 2035 | Quebec | Hydro-Quebec (Feb 2026) |
| Proposed Quebec data-centre rate (5 MW+) vs Rate L energy charge | 13 vs 3.821 plus CAD 15.027 per kW | CAD cents per kWh | 2026 | Quebec | Hydro-Quebec (Feb 2026), Rates 2026 |
| Large-power price, selected cities (5,000 kW, 3,060,000 kWh per month) | Montreal 5.55; Winnipeg 5.90; Vancouver 7.91; Chicago 8.67; Toronto 8.88; Seattle 11.98; Houston 12.01; New York 18.07; Calgary 23.77; Boston 26.32 | CAD cents per kWh | Apr 2023 | North America | Hydro-Quebec comparison |
| Federal Sovereign AI Compute Strategy | 2 (700 million challenge fund, 1 billion public compute, 300 million access fund) | CAD billion | 2024-2029 | Canada | ISED (page updated Jun 2026) |
Here is the shape of the thing, in plain English.
For the first twenty years of this century, computing got enormously more useful without getting much hungrier. That is the fact almost everyone leaves out. Between 2010 and 2018 the world's data centres ran roughly six times as much computing work while their electricity bill rose about 6 per cent, from 194 to 205 terawatt-hours. Storage capacity went up twenty-five-fold over the same period. Internet traffic went up more than tenfold. Electricity went sideways. As a share of world electricity, data centres moved from about 1 per cent in 2005 to about 1.5 per cent in 2024. That is nineteen years for half a percentage point.
This did not happen by luck, and it did not happen because chips got better, though they did. It happened for a mostly boring reason: the work moved buildings. In 2014 more than sixty per cent of American server energy sat in company-owned rooms and closets where the average server ran at about ten per cent utilisation and the building wasted about as much electricity on cooling as it delivered to the computers. By 2023, nearly ninety per cent of that work had moved into hyperscale and colocation facilities where servers run at forty-five per cent utilisation and the best buildings waste ten per cent instead of one hundred per cent. Virtualisation, which lets one machine carry many workloads, meant that servicing more demand needed fewer physical boxes: American server shipment growth fell from fifteen per cent a year in the early 2000s to three per cent after 2010, even as the internet exploded.
Lawrence Berkeley National Laboratory put a price on all of this. It ran the counterfactual: freeze American efficiency practice at 2010 levels and let only the chips improve. On that path, 2020 consumption would have been 170 per cent higher, and the industry's efficiency work saved about 620 terawatt-hours over the decade. That is roughly Canada's entire annual electricity generation, saved by engineering that got no press at all.
Now the second half of the story. Every one of those offsets is either exhausted or exhausting.
The building migration is nearly complete: with enterprise rooms down to single-digit percentages of server energy, there is almost nothing left to move. Power usage effectiveness, the cooling-overhead ratio, has fallen from 2.0 in 2007 to about 1.45 across the American fleet, and at facilities built for AI it is already 1.145 and forecast to reach only 1.136 by 2030. A building at 1.1 has ten per cent of overhead left to remove, ever. Koomey's law, the fifty-year trend of computations per kilowatt-hour doubling every eighteen months, slowed to a doubling every 2.6 years after 2000, when the physics of shrinking transistors changed.
And into that exhausted set of levers walked a workload with the opposite characteristics. An NVIDIA P100 accelerator drew 300 watts in 2016. The B300 and AMD's MI355X draw 1,400 watts in 2025. The power density of AI servers rose elevenfold between 2020 and 2025 and is expected to rise fourfold again by 2027, at which point a single rack the size of a large refrigerator could peak at the electricity demand of sixty-five households. The chips got more numerous, each one got heavier, and the building could not get any more efficient. Three multiplicative terms, all pointing the same way, at the same time.
So the curve bent. Global data-centre electricity grew about twelve per cent a year from 2017, then seventeen per cent in 2025 alone. In the United States it grew fourteen per cent in 2024 with twenty-two and twenty-nine per cent forecast for 2025 and 2026. Accelerated servers were fifteen per cent of global data-centre electricity in 2024; by 2030 AI-focused facilities are forecast to be about half the total.
Three things a business audience should take from this rather than the headline.
First, the numbers are softer than they look. Every historical global figure in this brief is a model output, not a meter reading. The IEA says so explicitly. When an independent review graded over a hundred studies, the estimates for 2020, a year that has already finished, spanned two hundred to twelve hundred terawatt-hours, a factor of six. Projections for 2030 diverge by nearly forty times. And there is a pattern: studies with weak methods produced systematically bigger numbers, averaging 1,013 terawatt-hours for 2023 against 335 from the strong ones. Peer review did not filter this; five of the nine peer-reviewed global estimates since 2014 were graded low or low-medium.
Second, the famous per-query numbers are the weakest part of the field, and the failure is instructive. The figure most people have heard, that a ChatGPT query uses about ten times a Google search, decomposes into three separate errors. The "Google search uses 0.3 watt-hours" anchor comes from a Google blog post of January 2009 which has never been updated. The "ten times" came from an Alphabet chairman talking to Reuters about DOLLARS, not electricity. And the resulting 2.9 watt-hours was published with the words "at most," a hedge that vanished when a consultancy repeated it. When researchers sampled a hundred news articles about AI energy, seventy-five per cent gave a figure with no uncertainty or source and five per cent urged caution. Meanwhile the three organisations that actually did the work by different methods, Google with production telemetry, Microsoft with a peer-reviewed bottom-up model, and Epoch with an independent one, landed at 0.24, 0.31 and 0.30 watt-hours. The convergence is the news; nobody reported it. The honest caveat is that Google's own paper computes 0.24 and 0.10 watt-hours for the same prompts on the same day, purely by changing where the boundary sits, and that a reasoning query measures thirteen times a short one.
Third, cryptocurrency is the control case, and it teaches in both directions. Bitcoin grew from thirteen terawatt-hours in 2017 to about 189 in 2025, which is more than the entire global electric vehicle fleet used in 2024. It is driven by coin price, not by anyone's demand for a service. Then on 15 September 2022 Ethereum changed a consensus rule and removed roughly twenty-one terawatt-hours a year, about two thirds of Ireland's whole annual generation, in a single day. Digital electricity demand is not a law of nature; it is a set of choices. But the disanalogy is just as important. Proof-of-work mining was wasteful by design, which is exactly why it could be deleted without losing anything. AI compute does work that customers are paying for, so there is no equivalent switch to flip, and anyone who suggests otherwise is selling something.
Where does that leave a decision-maker? With a load that is real, growing fast, geographically concentrated, and roughly a sixth AI today heading toward roughly a half by 2030. Also with a load that is smaller than air conditioning's growth, smaller than the world's televisions, and roughly one and a half per cent of world electricity. Both of those sentences are true, and anyone using only one of them is arguing rather than informing.
Read the boundary column before the number column. Four questions decide whether two rows can share an axis: does it count storage and network equipment or only servers; does it count facility infrastructure such as cooling; does it count cryptocurrency mining; does it count telecom networks and end-user devices. A fifth question applies only to crypto, and it bites hard: is this a calendar-year total or an annualised instantaneous rate.
| Year | TWh | Source (year published) | Boundary | Kind |
|---|---|---|---|---|
| 2000 | 58 | Koomey (2007) | Servers plus cooling and auxiliary only. No storage, no network. | estimate |
| 2000 | 70.8 | Koomey (2011), from Koomey (2008) | Servers, storage, communications, infrastructure at PUE 2.0 | estimate |
| 2005 | 123 | Koomey (2007) | As above, servers only | estimate |
| 2005 | 152.5 | Koomey (2011) | Full boundary | estimate |
| 2007 | 216 | Van Heddeghem et al. (2014) | Full, plus a 1.25 uplift for orphaned servers, PUE 1.95 | estimate |
| 2010 | 194 | Masanet et al., Science (2020) | Full, region-specific PUE, closets to hyperscale | estimate |
| 2010 | 203.4 to 271.8 (midpoint 237.6) | Koomey (2011) | Full, PUE 1.83 to 1.92 | estimate |
| 2012 | 268 (text rounds to 270) | Van Heddeghem et al. (2014) | Full, PUE 1.83 | estimate |
| 2014 | 194 | IEA (2017) | Global expansion of the LBNL United States model | estimate |
| 2015 | 245 | Malmodin and Lunden (2018) | Data centres PLUS enterprise networks, crypto excluded | estimate |
| 2015 | 397 | Andrae and Edler (2015), "expected" | Extrapolation from data-centre internet traffic. Graded LOW quality. | estimate |
| 2017 | 704 | Belkhir and Elmeligi (2018) | Extrapolation at 12 per cent a year from a 2008 figure. Graded LOW. | estimate |
| 2018 | 205 | Masanet et al., Science (2020) | Full boundary. About 1 per cent of world electricity. | estimate |
| 2018 | 200 | IEA (2019 to 2023 series) | Full boundary | estimate |
| 2020 | 223 | Malmodin et al. (2024) | Data centres including support activities, crypto excluded | estimate |
| 2020 | 345 to 1,200 | Andrae and Edler (2015) forecasts | Forecast made in 2015. It did not happen. | forecast |
| 2022 | 350 | IEA (2024) | Excludes crypto. 460 TWh including crypto. | estimate |
| 2022 | 375 | SemiAnalysis (2024) | Bottom-up from 3,000 sites. Graded HIGH but with high assumed utilisation. | estimate |
| 2023 | 300 to 380 | Kamiya and Coroama, IEA 4E EDNA (2025) | Excludes crypto. Triangulated three ways. | estimate |
| 2023 | 360 | IEA, Energy and AI (2025) | Excludes crypto, networks and devices | estimate |
| 2024 | 415 | IEA (2025) | Same. About 1.5 per cent of world electricity. | estimate |
| 2025 | 485 | IEA (2026) | Same | estimate |
| 2030 | 950 (range 670 to 1,260) | IEA (2026) Base Case, four cases | Same | forecast |
| 2035 | 1,200 (range 700 to 1,720) | IEA (2025), four cases | Same | forecast |
Three warnings on that table. First, Koomey's 2010 midpoint of 237.6 TWh and Masanet's 194 TWh are different models, not a revision of one another, and the 44 TWh gap for the same year is the honest measure of how much model choice matters. Second, the 220 TWh often attributed to Malmodin and Lunden for 2015 is a third party's back-out; the paper's own table says 245 TWh for data centres plus enterprise networks. Third, the 2030 rows are scenarios, and the IEA 4E review advises against projections reaching more than five years ahead.
The Energy Act of 2020 requires the United States Department of Energy to publish this, which is why it exists.
| Year | TWh | Share of United States electricity | Source | Kind |
|---|---|---|---|---|
| 2000 | 28.2 | 0.82 per cent | Koomey (2011) | estimate |
| 2005 | 45 (servers only) / 56.0 (full) | 1.2 / 1.53 per cent | Koomey (2007) / Koomey (2011) | estimate |
| 2006 | 61 | 1.5 per cent | EPA Report to Congress (2007) | estimate |
| 2008 | 69 | 1.8 per cent | Masanet et al. (2011) | estimate |
| 2010 | 76.4 (range 67.1 to 85.6) | about 2 per cent | Koomey (2011) | estimate |
| 2014 | 70 / 60 | 1.8 per cent | LBNL 2016 report / LBNL 2024 report, revised | estimate |
| 2016 | 60 | not stated | LBNL 2024 report | estimate |
| 2018 | 76 | 1.9 per cent | LBNL 2024 report | estimate |
| 2020 | 73 (a 2016 forecast) | not stated | LBNL 2016 report "current trends" | forecast |
| 2023 | 176 | 4.4 per cent | LBNL 2024 report | estimate |
| 2024 | 192 | 4.7 per cent | LBNL 2025 Update | estimate |
| 2024 | 180 | about 4 per cent | IEA (2025) | estimate |
| 2028 | 464 (Reference) / 325 to 580 | not stated / 6.7 to 12.0 per cent | LBNL 2025 Update / LBNL 2024 report | forecast |
| 2030 | 649 (range 521 to 843) | 11.8 per cent (9.5 to 15.3) | LBNL 2025 Update | forecast |
Note two disagreements that are worth showing students. The same laboratory put 2014 at 70 TWh in 2016 and at about 60 TWh in 2024, a 17 per cent revision from updated shipment data. And the IEA and LBNL differ by 12 TWh for the United States in 2024, the same country in the same year.
Mainframes and early servers, 1946 to 1999. No credible global electricity series exists. What is documented is efficiency: computations per kilowatt-hour doubled about every 1.57 years from ENIAC in 1946 to 2009, measured across 76 machines with an R-squared of 0.983 (Koomey, Berard, Sanchez and Wong, 2009 and 2011). ENIAC managed 437 computations per kilowatt-hour on 150,000 watts. The whole modern debate rests on a series that only begins in 2000.
The dot-com build-out and the internet-electricity myth, 2000 to 2005. World consumption roughly doubled, from 70.8 to 152.5 TWh, about 16.6 per cent a year. Almost all of it came from the sheer number of cheap volume servers, which went from 19.7 to 50.5 TWh worldwide; power per box barely moved. United States server shipments grew 15 per cent a year, nearly doubling the installed base. Why the curve bent upward: the internet was being built, and each new service needed its own physical machine. This is also the era of the field's biggest public error, covered in its own section below.
Rapid growth meets the financial crisis, 2005 to 2010. World consumption rose about 56 per cent rather than doubling, to a midpoint of 237.6 TWh, about 9.3 per cent a year. The United States rose about 36 per cent. Why the curve bent downward: the 2008 to 2009 recession cut server purchases hard, server virtualisation arrived and let one physical box carry many workloads, and cost pressure made operators care about efficiency for the first time. American server shipment growth fell from 15 per cent a year to 5 per cent. The IEA dates the decoupling of data-centre electricity from digital service demand to 2007 and 2008.
The efficiency plateau, 2010 to 2018. From 194 to 205 TWh, about 0.7 per cent a year, while compute instances grew about 550 per cent, storage capacity 25-fold and internet traffic more than tenfold. Why the curve went flat: four offsets, quantified in the next section. This is the central fact of this dimension and the thing most commentary still gets wrong in both directions.
The cryptocurrency surge, 2017 onward. Bitcoin went from about 13 TWh in 2017 to about 96 TWh in 2022 and about 189 TWh in 2025, roughly 49 per cent a year over the first five years. Why the curve bent: nothing to do with demand for a service. Mining hardware is added whenever the coin price exceeds the electricity cost of running it. It appeared outside every official data-centre statistic and remains outside them.
The Merge, 15 September 2022. Ethereum switched from proof of work to proof of stake and removed roughly 21 TWh a year of demand in one day, about two thirds of Ireland's entire annual generation. Why the curve bent: a rule change. This is the counter-example that stops anyone treating digital demand as a law of nature, and the disanalogy matters as much as the analogy, because proof of work was wasteful by design while AI compute does work people are paying for.
The artificial intelligence inflection, 2022 to 2026. From 350 TWh in 2022 to 485 TWh in 2025, about 11.5 per cent a year, accelerating to 17 per cent in 2025 alone, with AI-focused facilities up 50 per cent in that year. In the United States: 14 per cent in 2024, a forecast 22 per cent in 2025 and 29 per cent in 2026. Why the curve bent: the offsets ran out at the same moment the demand arrived. That is the whole story, and it is the next section.
The projected decade, 2026 to 2030. The IEA Base Case doubles global consumption to 950 TWh, about 14.4 per cent a year, with AI-focused facilities more than tripling to about 465 TWh. Accelerated server electricity grows 30 per cent a year against 9 per cent for conventional servers. Treat every number after 2026 as a scenario.
1. Migration out of enterprise rooms. In 2014 more than 60 per cent of American server energy sat in internal company data centres. By 2023 that was nearly 10 per cent, with hyperscale and colocation facilities taking almost 80 per cent, and by 2028 internal facilities fall below 2 per cent (LBNL, 2024). This mattered because of utilisation: LBNL modelled internal data centres at 10 per cent average server utilisation against 45 per cent for hyperscale. Moving a workload from a 10 per cent box to a 45 per cent box removes roughly four servers.
2. Virtualisation and utilisation. Virtualisation, which lets one physical server carry many independent workloads, arrived between 2005 and 2010 and is the main reason American server shipment growth fell from 15 per cent a year to 5 per cent and then to 3 per cent after 2010 (LBNL, 2016).
3. Falling power usage effectiveness. At the time of the 2007 EPA Report to Congress the average was 2.0, meaning every kilowatt-hour reaching the servers needed another for cooling and power conversion. Some sites measured above 3.0. By 2014 the American fleet average was 1.6, by 2024 it was 1.45, and by 2030 it is forecast at 1.36. The gains came almost entirely from the shift to big buildings, not from improving small ones: LBNL's 2014 modelling put hyperscale at 1.2 and a server room at 2.5, and the best hyperscale operators were already recording 1.1 or less by 2016.
4. Chip efficiency, Koomey's law. Computations per kilowatt-hour doubled about every 1.57 years from 1946 to 2009. Energy per compute instance fell about 20 per cent a year through the 2010 to 2018 plateau (Masanet et al., 2020).
The counterfactual that prices all four. LBNL froze American industry efficiency at 2010 levels (server utilisation 14 per cent, idle draw 59 per cent of maximum, 11.3 watts per hard disk drive, weighted average PUE 1.89) while letting chip performance keep improving. Result: 2014 consumption would have been 60 per cent higher and 2020 consumption 170 per cent higher, a saving of about 620 TWh over the decade (LBNL, 2016). That is roughly Canada's entire annual generation, saved by engineering that nobody wrote about.
Koomey's law slowed first. After about 2000 the doubling time for peak-output computations per kilowatt-hour stretched from roughly 1.5 years to about 2.6 years, as Dennard scaling ended (Koomey and Naffziger, 2016). Note also the metric's own caveat: Koomey's law measures peak output, and servers in typical business applications run near full load only 5 to 15 per cent of the time.
The migration lever is spent. With internal data centres already down to a few per cent of American server energy, there is almost nothing left to move.
The PUE lever is spent. American facilities serving AI equipment were at 1.145 in 2024 and are forecast to reach 1.136 in 2030. That is a 0.8 per cent improvement over six years. A hyperscaler at 1.1 has at most 10 per cent of overhead left to remove, ever.
Accelerator power went vertical. NVIDIA's Tesla P100 drew 300 watts in 2016 and its V100 the same in 2017. The A100 reached 400 watts in 2020, the H100 700 watts in 2022, the B200 1,200 watts in 2024, and the B300 and AMD's MI355X 1,400 watts in 2025. That is a 4.7-fold rise in nine years, at the same time as the number of chips was rising and PUE had stopped falling. Three multiplicative terms, all pointing the same way.
Density followed. AI server power density rose elevenfold between 2020 and 2025 and is set to rise a further fourfold by 2027, when a single rack the physical size of a large refrigerator could peak at the demand of 65 households (IEA, 2026). At server level, average annual power draw of an eight-GPU server passes 4 kilowatts by 2026 (LBNL, 2025 Update).
And idle power turned out to matter more than anyone assumed. LBNL cut its assumed AI inference utilisation from 40 per cent to about 20 per cent by 2030, because inference is user-facing and must be sized for peak demand, so it idles between peaks. Industry experts told LBNL idle draw could reach 50 per cent of rated power in latency-sensitive facilities against the 20 per cent LBNL assumes. That single assumption moves the 2030 American forecast by more than 20 per cent, from 649 to 782 TWh.
No published source gives a clean four-way split of traditional, cloud, crypto and AI in terawatt-hours across a run of years. The IEA says why: there is no comprehensive data on workload shares, colocation and cloud operators often cannot see what runs in their own halls, and definitions of AI differ. What follows is assembled from published totals and published AI shares, with every derivation labelled. It should be charted with the caveat on the face of the chart.
| Year | Total data centres (TWh) | AI (TWh) | Non-AI data centres (TWh) | Crypto, separate band (TWh) |
|---|---|---|---|---|
| 2020 | not verified | not verified | not verified | 71 (Bitcoin only; about 78 including Ethereum) |
| 2022 | 350 | not verified | not verified | 96 |
| 2023 | 360 | 30 (range 10 to 50) | 330 | 121 |
| 2024 | 415 | 62 (derived: 15 per cent of 415) | 353 | 159 |
| 2025 | 485 | not published as a level | not derivable | 189 |
| 2030 | 950 | 465 (IEA facility basis) or 200 to 400 (EDNA hardware basis) | 485 | not forecast here |
Sources: IEA Energy and AI (2025) and Key Questions (2026) for totals and the 15 per cent accelerated-server share; Kamiya and Coroama, IEA 4E EDNA (2025) for the AI ranges; Cambridge Bitcoin Electricity Consumption Index v1.8.0 for crypto calendar-year totals. Crypto sits OUTSIDE the IEA and LBNL data-centre totals, so it is a band on top, never inside.
The 2030 row deserves a moment. The IEA's 465 TWh counts AI-FOCUSED FACILITIES, including their cooling and their conventional servers. EDNA's 200 to 400 TWh counts AI HARDWARE. Both are defensible; they are answering different questions, and the gap between them is roughly the non-AI equipment sitting inside AI buildings.
| Year | Measure | Value | Source |
|---|---|---|---|
| 2023 | AI share of global data-centre electricity | 10 per cent (range 5 to 15) | IEA 4E EDNA (2025) |
| 2024 | Accelerated servers, share of total data-centre electricity | 15 per cent | IEA (2025) |
| 2024 | Accelerated servers, share of server electricity | 24 per cent | IEA (2025) |
| 2030 | AI share of global data-centre electricity | 35 to 50 per cent | IEA 4E EDNA (2025) |
| 2030 | AI-focused facilities, share of the 950 TWh total | about 49 per cent | derived from IEA (2026) |
| 2030 | AI servers, share of total United States data-centre electricity | 55 per cent | LBNL 2025 Update |
| 2030 | AI servers, share of United States SERVER electricity | 84 per cent | LBNL 2025 Update |
| Year | Training | Inference | Source |
|---|---|---|---|
| 2023 | about 40 per cent | nearly 60 per cent | LBNL 2024 report, United States |
| 2028 | 50 to 53 per cent | 47 to 50 per cent | LBNL 2024 report forecast, United States |
| 2024 | about 35 per cent | about 65 per cent | LBNL 2025 Update, on Omdia data, United States |
| 2030 | about 20 per cent | about 80 per cent | LBNL 2025 Update forecast, United States |
Eighteen months apart, the same laboratory forecast training rising to about 52 per cent by 2028 and then falling to about 20 per cent by 2030. This is not a data correction. It is a change of view about where AI activity and spending go, and the newer report follows industry feedback that inference now dominates both. Chart both lines and let students argue about which is right. Use the newer one and say so.
The perspective number: every large AI model ever trained accounts for about 1.7 TWh cumulatively across 283 models. Against 485 TWh of data-centre electricity a year, all frontier training in history is about 0.35 per cent of a single year.
Two different bases. Do not mix them.
| Basis | Year | Enterprise or internal | Hyperscale plus colocation | Source |
|---|---|---|---|---|
| Share of United States SERVER ENERGY | 2014 | over 60 per cent | not split in the text | LBNL 2024 report |
| Share of United States SERVER ENERGY | 2023 | nearly 10 per cent | almost 80 per cent | LBNL 2024 report |
| Share of United States SERVER ENERGY | 2028 | below 2 per cent | over 90 per cent | LBNL 2024 report |
| Share of GLOBAL INSTALLED CAPACITY | 2025 | not published | hyperscale 48 per cent | Synergy Research (April 2026) |
| Share of GLOBAL INSTALLED CAPACITY | 2031 | not published | hyperscale 67 per cent | Synergy Research (April 2026) |
The only published terawatt-hour split by data-centre type that could be verified is the World Bank and ITU's 2022 figure: colocation 110 TWh, cloud 53 TWh, content 32 TWh, totalling 195 TWh. It EXCLUDES enterprise data centres entirely, which is why it sits well below the IEA's 350 TWh for the same year. The roughly 155 TWh gap is a rough measure of the enterprise and unreported remainder.
| Measure | 2018 | 2024 | 2030 |
|---|---|---|---|
| United States installed servers, total (millions) | 16.3 | 30.9 | 48.6 (Reference Case) |
| of which accelerated (millions) | almost none | 4.2 | 19.0, about 40 per cent |
| United States AI server electricity (TWh) | not published | 50 to 75 | about 357 (derived: 55 per cent of 649) |
| United States infrastructure share of data-centre electricity | 36 per cent | 31 per cent | falling |
| United States networking share | 3.4 per cent | 4.5 per cent | roughly constant |
Globally, accelerated server electricity grows 30 per cent a year to 2030 against 9 per cent for conventional servers. Accelerated servers deliver almost half the net increase in total data-centre electricity, and about 70 per cent of the increase in server electricity alone (IEA, 2025).
Not verified, and not manufactured. No credible published breakdown of data-centre electricity by customer industry (finance, telecoms, healthcare, government, retail, media and streaming) could be found. This cut is genuinely absent, for a structural reason the IEA states plainly: colocation and cloud operators often have limited visibility over the workloads running in their own facilities, so nobody holds the data. Vendor reports on IT SPENDING by industry vertical exist, but spending is not electricity, and converting one to the other would be invention. Any chart a student meets showing data-centre electricity by end-use industry should be treated as unsourced until proven otherwise.
| Comparison | TWh | Year | Source |
|---|---|---|---|
| World electricity generation | 31,734 | 2025 | Ember (2026 release) |
| ALL data centres worldwide | 485 | 2025 | IEA (2026) |
| ALL data centres worldwide, 2030 Base Case | 950 | 2030 | IEA (2026) |
| Japan, total generation | 1,030 | 2025 | Ember (2026) |
| Canada, total generation | 652 | 2025 | Ember (2026) |
| Germany, total generation | 500 | 2025 | Ember (2026) |
| United Kingdom, total generation | 292 | 2025 | Ember (2026) |
| Netherlands, total generation | 135 | 2025 | Ember (2026) |
| Ireland, total generation | 31 | 2025 | Ember (2026) |
So: global data centres in 2025 used about 74 per cent of everything Canada generates, about 97 per cent of Germany's output, and about 3.6 times the Netherlands'. The 2030 Base Case is about 1.5 times Canada's entire system and about 92 per cent of Japan's. Ireland already gives about 22 per cent of its metered electricity to data centres.
| Comparison | TWh | Year | Source |
|---|---|---|---|
| Global electric vehicle fleet, charging | 180 | 2024 | IEA Global EV Outlook (2025) |
| Global electric vehicle fleet, 2030 Stated Policies | 780 | 2030 | IEA Global EV Outlook (2025) |
| Bitcoin mining | 189 | 2025 | Cambridge CBECI v1.8.0 |
| All cryptocurrencies | 125 | 2023 | IEA (2025) |
| Telecommunication networks | 280 | 2023 | IEA (2025) |
| End-user devices (computers, phones, connected devices) | 440 | 2023 | IEA (2025) |
| Televisions, peripherals and cable networks | 500 | 2023 | IEA (2025) |
| Entire information and communication technology sector | over 1,000 | 2023 | IEA (2025) |
| Growth in space cooling electricity, 2014 to 2024 | +700 | 2024 | IEA (2025) |
| Growth in data-centre electricity, 2014 to 2024 | +250 | 2024 | IEA (2025) |
Three of these are worth saying out loud in a classroom. Data centres in 2024 used more than twice the electricity of every electric vehicle on earth. In 2023 end-user devices used MORE electricity than all the world's data centres, and televisions used more still. And over the decade in which data centres added 250 TWh, air conditioning added 700 TWh, which got a fraction of the coverage.
On heavy industry and aviation, honesty is required. Global steel and cement electricity in terawatt-hours could not be verified from a primary source, and cement is dominated by thermal fuel rather than electricity, so an electricity-only comparison would mislead. The defensible statement is the IEA's own: by 2030 the United States is set to consume more electricity for data centres than for the production of aluminium, steel, cement, chemicals and all other energy-intensive goods combined. Aviation runs on jet fuel, so there is no honest terawatt-hour comparison at all; on carbon, data-centre electricity emitted about 180 million tonnes of CO2 in 2024, but the corresponding aviation figure was not verified here and is therefore not given.
| Item | Energy | Boundary | Source | Verdict |
|---|---|---|---|---|
| Median Gemini text prompt | 0.24 Wh | Full facility: accelerator, host processor and memory, idle reserve, overhead | Google (August 2025) | SOLID |
| The SAME prompts | 0.10 Wh | Accelerator silicon only, best tenth of sites | Google (August 2025) | SOLID |
| Median text prompt | 0.31 Wh (IQR 0.16 to 0.60) | Full facility, bottom-up | Oviedo et al., Joule (2026) | SOLID, peer reviewed |
| Typical ChatGPT query | 0.3 Wh | Modelled, GPT-4o assumed | Epoch AI (February 2025) | SOLID as a model |
| Average ChatGPT query | 0.34 Wh | Unstated | Sam Altman (June 2025) | WEAK |
| Reasoning query | 3.91 Wh (IQR 2.15 to 7.05) | Full facility | Oviedo et al., Joule (2026) | SOLID |
| Agentic query with reasoning | about 50 Wh | GPU only, indicative | IEA (2026), their figure 2.1 | ORDER OF MAGNITUDE ONLY |
| Six-second AI video | 115 Wh | GPU only, lab | IEA (2025) | SOLID but not comparable |
| "A ChatGPT request" | 2.9 Wh | Derived, not measured | de Vries (2023) via EPRI (2024) | DISPUTED, do not use |
| A Google web search | 0.3 Wh | Per search including index building | Google blog, 12 January 2009 | OBSOLETE |
| Charging a smartphone | 15 Wh | IEA (2025) | SOLID | |
| Charging a laptop | 60 Wh | IEA (2025) | SOLID | |
| An hour of television | 100 Wh | at about 100 watts | Google (2025) | SOLID |
| Boiling one litre of water | about 110 Wh | derived physics; Murray et al., Applied Energy (2016) | SOLID as physics | |
| Driving an electric car one kilometre | 186 Wh | 2024 Tesla Model 3 Performance AWD, EPA combined | fueleconomy.gov | SOLID for that model |
Useful ratios on Google's measured figure: one kettle boil is about 458 prompts, one kilometre of electric driving about 775 prompts, one phone charge about 62 prompts, and one prompt is about nine seconds of television.
Training energy, for completeness: GPT-3 took 1,287 megawatt-hours and 552.1 tonnes of CO2e (Patterson et al., 2021). The IEA estimates GPT-4 at 42.4 gigawatt-hours on a full-facility basis for training compute of 2.2e25 calculations. Llama 3.1 405B took 30.84 million GPU-hours and 8,930 tonnes of CO2e location-based, or zero market-based because Meta matches its electricity with renewables; note that the widely quoted 11,390 tonnes is the whole model family, not the 405B alone, and Meta publishes no megawatt-hour figure at all.
This section matters more here than in any other dimension of the pack.
The whole historical series is modelled, not measured. The IEA states plainly that all historical data on global data-centre consumption are estimates. Very few governments require reporting, and operators do not disclose data-centre electricity specifically.
The 2020 estimates span a factor of six. From about 200 terawatt-hours to 1,200. For 2030 the spread is nearly forty times. Studies graded low quality averaged 1,013 terawatt-hours for 2023; high-quality studies averaged 335 (IEA 4E EDNA, 2025).
Koomey's 2010 figure and Masanet's 2010 figure differ by 44 TWh (237.6 against 194) for the same year. They are different models, not a revision. Never treat one as superseding the other without saying so.
LBNL revised its own 2014 estimate down by about 17 per cent between its 2016 and 2024 reports, from 70 to about 60 TWh.
The IEA and LBNL disagree about the United States in 2024 by 12 TWh, 180 against 192.
LBNL contradicts itself on training against inference. The 2024 report forecast training rising to 50 to 53 per cent of AI server energy by 2028. The 2025 Update forecasts training falling to about 20 per cent by 2030. Both are current publications from the same laboratory.
The AI share depends entirely on what "AI" means. Accelerated-server electricity in 2024 was about 62 TWh. AI-focused FACILITIES in 2030 are 465 TWh on the IEA's basis and 200 to 400 TWh on EDNA's. These are different boundaries answering different questions.
Per-query energy figures span a factor of 400, from 0.10 to about 40 watt-hours, and almost none of that is disagreement about physics. The drivers are: where the boundary sits (Google gets 0.10 or 0.24 for the same prompts), whether idle reserve capacity is counted, whether requests are batched (academic benchmarks often are not, and batching roughly halves per-task energy), how long the answer is, whether a reasoning model is thinking, whether a median or a mean is reported, and the fact that no closed model discloses its size, hardware or location.
The 2.9 watt-hour figure is disputed and should not be used as current. Its chain is documented in full in the data file and the manifest.
The "500 millilitres per conversation" water claim is a misquotation. The paper says 500 millilitres per ten to fifty medium-length responses, which is roughly 10 to 28 millilitres each, for GPT-3 in specific American data centres. The paper's own headline total moved 54 per cent between its versions. Water figures are the least comparable numbers in the field: Google's measured 0.26 millilitres is about 173 times below Mistral's audited 45 millilitres, mainly because of boundary.
The Llama 3.1 emissions figure is routinely misattributed. 11,390 tonnes is the whole model family; the 405B model alone is 8,930 tonnes location-based and zero market-based. Meta publishes no energy figure, so any megawatt-hour number for Llama is somebody's arithmetic, and the two published attempts differ by a factor of two.
Cryptocurrency has two separate traps. First, the headline Cambridge number is an ANNUALISED INSTANTANEOUS RATE, not a calendar-year total: on 2 September 2026 the live rate was 150.9 terawatt-hours a year while the 2025 calendar total was 188.6. Second, Cambridge serves five model vintages simultaneously, and 2021 Bitcoin is 89.0 terawatt-hours on the current model against 104.0 on the old one, a 17 per cent difference from methodology alone. Digiconomist reads about 35 per cent higher than Cambridge and has been frozen at an unchanged value for 259 days; its Ethereum index reads exactly zero from 6 May 2026 and should not be cited live.
The four published Merge reduction percentages are not variants of one number. 99.84 per cent is de Vries's most conservative bound; 99.95 per cent is an Ethereum Foundation forecast made sixteen months BEFORE the Merge; 99.988 per cent is the Crypto Carbon Ratings Institute's measurement; 99.99 per cent is Cambridge's day-of-Merge figure. Name the owner when you quote one.
The IEA has no crypto figure after 2023. Its only published number is about 125 terawatt-hours for 2023. Also, on the same page, DATA CENTRES grew by over 90 terawatt-hours between 2020 and 2023 while CRYPTOCURRENCY grew by over 50; the two are frequently swapped.
Could not be verified at all: any breakdown of data-centre electricity by end-use industry; global steel and cement electricity in terawatt-hours; a global level (as opposed to growth) for residential air conditioning electricity; global aviation for a carbon comparison; the energy of an LED bulb-hour or a laundry load from a primary source. None of these were invented.
Could not be obtained: the Masanet et al. Science paper itself, the Koomey et al. IEEE Annals paper itself, and the Malmodin et al. Telecommunications Policy paper itself are all paywalled. Their headline figures here come from freely available companion documents by the same authors and from the IEA 4E review's reading, both of which are in the downloads folder. Two citation corrections came out of this: Malmodin et al. 2024 is in Telecommunications Policy, not the Journal of Industrial Ecology, and the "1.57 years" of Koomey's law is verified in the 2009 companion report rather than in the 2011 article text.
The claim that Canada should attract a large share of the world's new AI data centres rests on three adjectives: cheap power, clean power, lots of it. Each one is testable. Two of the three hold up. The third does not, and the way the first two interact with the third is the actual strategic problem.
Start with size, because it disciplines everything else. Canada generated 652 terawatt hours of electricity in 2025 from about 156 gigawatts of installed capacity. That makes it the seventh largest producer in the world and the tenth largest by capacity, with 2.06 per cent of global generation. Statistics Canada and Ember, working independently, agree on the capacity figure to within one per cent, which is reassuring. But the ranking flatters. Canada is roughly the same size as South Korea and smaller than Russia, Japan and India. China generates sixteen times more.
The number that should reframe the whole conversation is the rate of addition. In 2025, China added 315 gigawatts of solar capacity and 119 gigawatts of wind. That single year of Chinese additions is 2.8 times the entire Canadian generating fleet, built from scratch, in twelve months. In the same year Canada added about 1.1 gigawatts of non-emitting capacity: 0.1 gigawatts of solar and 0.3 of wind. Canada's whole national build rate is a rounding error against the pace of its largest competitor. Any strategy that assumes Canada can out-build anyone is not a strategy.
Now price, which is where the real advantage lives and where the debate is most often misled. There are at least four different numbers that people call "the electricity price" and they differ by a factor of five. A residential customer in Montreal pays 8.29 Canadian cents per kilowatt hour. A small business pays 12.08. A medium industrial customer at 500 kilowatts pays 14.70. A 5,000 kilowatt industrial customer pays 5.83, and a 50,000 kilowatt customer pays 5.52. The large-power price is one third of the medium-power price in the same city, in the same month, from the same utility. Comparing a residential number in one country with an industrial number in another produces conclusions that are wrong by hundreds of per cent, and this happens constantly in press coverage of data centres.
Done properly, Canada's advantage is real. Statistics Canada reports an implied industrial price for mining and manufacturing of 6.72 Canadian cents per kilowatt hour in 2024, which is 4.91 United States cents. The United States Energy Information Administration reports 8.13 United States cents for the same year on the same conceptual basis, revenue divided by volume for the industrial class. Canadian industry pays about sixty per cent of what American industry pays. Hydro-Quebec's annual city comparison, the only source that puts twenty-two North American utilities on a single customer profile and a single exchange rate, gives the same answer at the level that matters for a data centre: at a 50,000 kilowatt profile, Montreal is 5.52 Canadian cents, Winnipeg 5.09 and Vancouver 6.72, against Toronto 12.66, Houston 12.90, New York 22.88 and Boston 24.58.
But Canada is not the world's cheapest. Eurostat's band IF and band IG series, which cover exactly the consumption levels a data centre reaches, put Finland at 4.16 euro cents per kilowatt hour and Norway at 4.68 in the second half of 2025, excluding taxes. Converted at the 2025 average rate those are 4.70 and 5.28 United States cents. Norway's band IG price, for consumers above 150 gigawatt hours a year, is 4.08 euro cents, or 4.61 United States cents, the cheapest large-industrial power in Europe. France sits at 6.86 United States cents on that basis. So the honest ranking puts Norway and Finland ahead of Canada's national average, with Quebec alone beating them.
Europe's price story since 2020 is worth understanding because it is what created the current competitive map. The European Union's band IF industrial price roughly tripled between the first half of 2020 and the second half of 2022, from 5.30 to 18.92 euro cents. It has since fallen back to 10.95, but that is still double the pre-crisis level and it is not falling much further. Germany is stuck at 12.83 against 4.34 in 2020, a 196 per cent rise, which is why Berlin has legislated a subsidised industrial price of 50 euros per megawatt hour retroactive to January 2026. Italy has done something similar at 65 euros. The International Energy Agency's assessment is blunt: European prices for energy-intensive industry are more than double United States prices and more than fifty per cent above China and India, and the European Central Bank estimates that a permanent ten per cent price rise costs two per cent of employment in those industries. This is why Europe's AI gigafactory programme, for all its 20 billion euros, faces a structural cost disadvantage that money does not fix.
Ireland is the cautionary tale inside that story. It is the European data-centre capital and it now has the most expensive large-industrial electricity in the European Union: 16.80 euro cents at band IF and 15.62 at band IG. Data centres take about twenty-two per cent of Ireland's metered electricity. Concentrating a lot of inflexible load on a small system does not lower prices; it raises them and then triggers connection moratoria. Singapore reached the same place by a different route: about 1.46 gigawatts live, only about 20 megawatts under construction, and 5.5 per cent non-emitting generation.
On cleanliness, Canada is genuinely strong but the usual framing overstates it. Ember, the only source that applies one method to every country, puts Canada at 77.0 per cent non-emitting generation in 2025, fifth in the world among large producers behind Norway, Sweden, France and Brazil. Its carbon intensity figure for Canada is 190.7 grams of carbon dioxide per kilowatt hour, which is higher than the 100 to 120 grams often quoted, because Ember uses lifecycle emission factors and assigns non-zero emissions to hydro, wind, solar and nuclear. Environment and Climate Change Canada, counting only what comes out of stacks, reports about 86 grams for 2024. Both numbers are defensible; mixing them is not. What matters commercially is that Canada is three to seven times cleaner than every large market it competes with for AI load, and that the provincial range runs from 1.7 grams in Quebec to 730 in Saskatchewan.
The set of jurisdictions that are simultaneously cheap and clean at scale is therefore very short: Norway, Sweden, Finland, France, and four Canadian provinces. Everywhere else forces a trade. Texas is cheap and dirty. Malaysia is cheap and among the dirtiest destinations at 603 grams. The Gulf is the cheapest gas in the world and the dirtiest grid, at 692 grams in Saudi Arabia. Denmark and Ireland are clean and expensive. That short list is Canada's actual competitive set, and it is small enough that Canada's position in it is a genuine asset.
Which brings the argument to its uncomfortable end. The North American Electric Reliability Corporation assesses Canadian and American systems on the same reserve-margin basis. Alberta has an anticipated reserve margin of 36.2 per cent against a reference level of 11.8, and holds above 33 per cent through 2030-31. Saskatchewan and British Columbia are similarly comfortable. Quebec is not: its margin falls from 15.6 per cent to 11.5 by 2030-31 against a 12.2 per cent reference, with an explicit warning of winter shortfalls. Manitoba falls to 1.2 per cent. The Maritimes are already below target.
So the province with abundant spare capacity is Alberta, where industrial power costs 10.01 Canadian cents, the highest in the country, and the grid runs at 335 to 540 grams, comparable to Germany. The provinces where the pitch of cheap, clean power is true have no room. That is the real Canadian constraint, and it is not solved by attracting more announcements. It is solved by building generation and transmission in Quebec, British Columbia and Manitoba, or by accepting that Canadian AI capacity will largely be gas-fired Alberta capacity with a carbon story to manage. Given that Canada added 1.1 gigawatts of non-emitting capacity last year and the pipeline is 20 gigawatts, the arithmetic does not currently work.
All Ember figures are from the 2026 release of the Yearly Electricity Data file, downloaded 2 September 2026 and stored in this pack. Ember's capacity total is clean plus fossil capacity; it is not a nameplate registry and should be treated as within a few per cent.
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Total generation | 31,734 | TWh | 2025 | World | Ember Yearly Electricity Data (2026) |
| Total installed capacity | 10,195 | GW | 2025 | World | Ember (2026) |
| Total generation | 10,578 | TWh | 2025 | China | Ember (2026) |
| Total installed capacity | 3,726 | GW | 2025 | China | Ember (2026) |
| Total generation / capacity | 4,520 / 1,333 | TWh / GW | 2025 | United States | Ember (2026) |
| Total generation / capacity | 2,792 / 1,200 | TWh / GW | 2025 | European Union (27) | Ember (2026) |
| Total generation / capacity | 2,082 / 556 | TWh / GW | 2025 | India | Ember (2026) |
| Total generation / capacity | 1,193 / 238 | TWh / GW | 2025 | Russia | Ember (2026) |
| Total generation / capacity | 1,030 / 323 | TWh / GW | 2025 | Japan | Ember (2026) |
| Total generation / capacity | 751 / 261 | TWh / GW | 2025 | Brazil | Ember (2026) |
| Total generation / capacity | 652 / 156 | TWh / GW | 2025 | Canada | Ember (2026) |
| Total installed capacity, cross-check | 156.4 | GW | 2024 | Canada | Statistics Canada Table 25-10-0022 |
| Total generation / capacity | 625 / 159 | TWh / GW | 2025 | South Korea | Ember (2026) |
| Total generation / capacity | 570 / 168 | TWh / GW | 2025 | France | Ember (2026) |
| Total generation / capacity | 500 / 268 | TWh / GW | 2025 | Germany | Ember (2026) |
| Total generation / capacity | 455 / 104 | TWh / GW | 2024 | Saudi Arabia | Ember (2026) |
| Total generation / capacity | 292 / 111 | TWh / GW | 2025 | United Kingdom | Ember (2026) |
| Total generation / capacity | 287 / 116 | TWh / GW | 2025 | Australia | Ember (2026) |
| Total generation / capacity | 201 / 42 | TWh / GW | 2025 | Malaysia | Ember (2026) |
| Total generation / capacity | 177 / 54 | TWh / GW | 2024 | United Arab Emirates | Ember (2026) |
| Total generation / capacity | 170 / 55 | TWh / GW | 2025 | Sweden | Ember (2026) |
| Total generation / capacity | 161 / 41 | TWh / GW | 2025 | Norway | Ember (2026) |
| Total generation / capacity | 135 / 59 | TWh / GW | 2025 | Netherlands | Ember (2026) |
| Total generation / capacity | 82 / 26 | TWh / GW | 2025 | Finland | Ember (2026) |
| Total generation / capacity | 60 / 14 | TWh / GW | 2025 | Singapore | Ember (2026) |
| Total generation / capacity | 35 / 17 | TWh / GW | 2025 | Denmark | Ember (2026) |
| Total generation / capacity | 31 / 15 | TWh / GW | 2025 | Ireland | Ember (2026) |
| Total generation / capacity | 19 / 2.2 | TWh / GW | 2024 | Iceland | Ember (2026) |
| Canada rank by generation | 7th of 195 | rank | 2025 | Canada in world | Ember (2026) |
| Canada rank by capacity | 10th | rank | 2025 | Canada in world | Ember (2026) |
| Canada share of world generation | 2.06 | % | 2025 | Canada in world | Ember (2026) |
| Canada share of world capacity | 1.53 | % | 2025 | Canada in world | Ember (2026) |
Net capacity additions, the pace test:
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Solar capacity added | 315.1 | GW | 2025 | China | Ember (2026) |
| Wind capacity added | 119.4 | GW | 2025 | China | Ember (2026) |
| All non-emitting capacity added | 441.1 | GW | 2025 | China | Ember (2026) |
| Fossil capacity added | 92.3 | GW | 2025 | China | Ember (2026) |
| Solar capacity added | 511.1 | GW | 2025 | World | Ember (2026) |
| All renewable capacity added, IEA basis | 800 | GW | 2025 | World | IEA, Electricity 2026 |
| Battery storage capacity added | about 110 (up about 40%) | GW | 2025 | World | IEA, Electricity 2026 |
| Solar / non-emitting capacity added | 34.0 / 40.1 | GW | 2025 | United States | Ember (2026) |
| Solar / non-emitting capacity added | 37.0 / 45.6 | GW | 2025 | India | Ember (2026) |
| Solar / non-emitting capacity added | 56.3 / 68.1 | GW | 2025 | European Union | Ember (2026) |
| Solar / wind / all non-emitting added | 0.1 / 0.3 / 1.1 | GW | 2025 | Canada | Ember (2026) |
| World electricity demand growth | about 3 | % | 2025 | World | IEA, Electricity 2026 |
| Forecast demand growth, annual average | 3.6 | % per year | 2026-2030 | World | IEA, Electricity 2026 |
Non-emitting share is Ember's "clean" category: hydro, nuclear, wind, solar, bioenergy and other renewables. Carbon intensity is Ember's published figure, which is a LIFECYCLE number (see "Contested or uncertain figures").
| Country or region | Non-emitting share, % | CO2 intensity, gCO2/kWh (Ember, lifecycle) | Year | Source |
|---|---|---|---|---|
| Iceland | 100.0 | 27.8 | 2024 | Ember (2026) |
| Norway | 99.0 | 28.1 | 2025 | Ember (2026) |
| Sweden | 98.8 | 35.4 | 2025 | Ember (2026) |
| Finland | 96.3 | 57.5 | 2025 | Ember (2026) |
| France | 94.8 | 41.5 | 2025 | Ember (2026) |
| Denmark | 94.2 | 99.6 | 2025 | Ember (2026) |
| Brazil | 88.7 | 110.0 | 2025 | Ember (2026) |
| Canada | 77.0 | 190.7 | 2025 | Ember (2026) |
| European Union (27) | 71.2 | 209.2 | 2025 | Ember (2026) |
| United Kingdom | 64.4 | 217.4 | 2025 | Ember (2026) |
| Germany | 59.1 | 329.6 | 2025 | Ember (2026) |
| Netherlands | 54.2 | 253.6 | 2025 | Ember (2026) |
| Ireland | 48.2 | 255.9 | 2025 | Ember (2026) |
| United States | 43.0 | 384.4 | 2025 | Ember (2026) |
| China | 41.6 | 526.2 | 2025 | Ember (2026) |
| South Korea | 40.0 | 417.1 | 2025 | Ember (2026) |
| Australia | 38.7 | 524.6 | 2025 | Ember (2026) |
| Russia | 35.7 | 449.9 | 2025 | Ember (2026) |
| Japan | 32.7 | 477.4 | 2025 | Ember (2026) |
| United Arab Emirates | 31.7 | 467.5 | 2024 | Ember (2026) |
| India | 26.7 | 670.5 | 2025 | Ember (2026) |
| Malaysia | 20.6 | 603.2 | 2025 | Ember (2026) |
| Singapore | 5.5 | 497.1 | 2025 | Ember (2026) |
| Saudi Arabia | 2.2 | 692.0 | 2024 | Ember (2026) |
| World | 42.6 | 458.5 | 2025 | Ember (2026) |
Canada on the Canadian method, and the provincial spread that the national number hides:
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| National electricity emissions intensity, operational basis | about 86 | gCO2e/kWh | 2024 | Canada | Canadian Climate Institute, 440 Megatonnes, on ECCC NIR 2026 |
| Same measure in 2008, for context | about 195 | gCO2e/kWh | 2008 | Canada | 440 Megatonnes |
| Grid consumption intensity, Quebec / Manitoba / British Columbia / Ontario | 1.7 / 2.0 / 15 / 30 | gCO2e/kWh | 2023-2024 | Canadian provinces | Environment and Climate Change Canada, 2025, via dimension 05 of this research pack |
| Grid consumption intensity, Alberta / Saskatchewan | 540 / 730 | gCO2e/kWh | 2023-2024 | Canadian provinces | Environment and Climate Change Canada, 2025, as above |
| Alberta emissions intensity, alternative provincial series | 335 (629 in 2019) | gCO2e/kWh | 2024 | Alberta | Government of Alberta |
| Renewable share of generation | 63.9 | % | 2024 | Canada | Statistics Canada |
| Hydro share of generation | 52.8 | % | 2025 | Canada | Ember (2026) |
| Nuclear share of generation | 13.1 | % | 2025 | Canada | Ember (2026) |
| Gas plus other fossil share of generation | 19.0 | % | 2025 | Canada | Ember (2026) |
| Coal share of generation | 4.0 | % | 2025 | Canada | Ember (2026) |
Which countries are both cheap and clean. Naming them explicitly, using large-industrial price below about 8 United States cents per kWh and non-emitting share above 75 per cent:
Everywhere else fails one test. Texas is cheap (6.65 United States cents) and dirty. Malaysia is cheap and very dirty (603 gCO2/kWh). Denmark and Ireland are clean-ish and expensive. Germany is neither. Singapore is dirty (497 gCO2/kWh from 5.5 per cent non-emitting) and constrained. The Gulf states are the cheapest gas power in the world and among the dirtiest grids anywhere, at 692 gCO2/kWh in Saudi Arabia.
Every row states the basis. Residential prices appear only in the clearly labelled block at the end and are not comparable to anything above it. Conversions use the Bank of Canada 2025 annual averages of 1.3978 Canadian dollars per United States dollar and 1.5782 Canadian dollars per euro, implying 1.1291 United States dollars per euro, except where the source uses its own rate.
C1. Eurostat, industrial band IF (70,000 to 149,999 MWh a year, roughly an 8 to 17 MW continuous load), second half of 2025, EXCLUDING taxes and levies.
| Country | EUR/kWh | US cents/kWh | Year | Region | Source |
|---|---|---|---|---|---|
| Finland | 0.0416 | 4.70 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Norway | 0.0468 | 5.28 | 2025 H2 | EEA | Eurostat nrg_pc_205 |
| France | 0.0681 | 7.69 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Sweden | 0.0728 | 8.22 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Spain | 0.0914 | 10.32 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Poland | 0.0915 | 10.33 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| European Union (27) average | 0.1095 | 12.36 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Netherlands | 0.1168 | 13.19 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Denmark | 0.1192 | 13.46 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Germany | 0.1283 | 14.49 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Italy | 0.1341 | 15.14 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Ireland | 0.1680 | 18.97 | 2025 H2 | EU | Eurostat nrg_pc_205 |
| Czechia | 0.1747 | 19.73 | 2025 H2 | EU | Eurostat nrg_pc_205 |
C2. Eurostat band IG (150,000 MWh a year and over, roughly 17 MW and up, the right band for a real data centre), second half of 2025, EXCLUDING taxes.
| Country | EUR/kWh | US cents/kWh | Year | Source |
|---|---|---|---|---|
| Norway | 0.0408 | 4.61 | 2025 H2 | Eurostat nrg_pc_205 |
| France | 0.0608 | 6.86 | 2025 H2 | Eurostat nrg_pc_205 |
| Sweden | 0.0639 | 7.21 | 2025 H2 | Eurostat nrg_pc_205 |
| Belgium | 0.0857 | 9.68 | 2025 H2 | Eurostat nrg_pc_205 |
| Netherlands | 0.0919 | 10.38 | 2025 H2 | Eurostat nrg_pc_205 |
| European Union (27) average | 0.0998 | 11.27 | 2025 H2 | Eurostat nrg_pc_205 |
| Germany | 0.1190 | 13.44 | 2025 H2 | Eurostat nrg_pc_205 |
| Ireland | 0.1562 | 17.64 | 2025 H2 | Eurostat nrg_pc_205 |
C3. North America and the rest of the world, industrial or large-power basis.
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Industrial average retail price, all sectors basis | 8.62 | US cents/kWh | 2025 | United States | EIA Electric Power Monthly Table 5.3 |
| Industrial average retail price | 8.13 | US cents/kWh | 2024 | United States | EIA Table 5.3 |
| Industrial price, Texas | 6.65 | US cents/kWh | Jan-Jun 2026 | Texas | EIA Table 5.6.B |
| Industrial price, Virginia | 10.08 (from 9.18) | US cents/kWh | Jan-Jun 2026 | Virginia | EIA Table 5.6.B |
| Industrial price, Ohio / Pennsylvania | 10.21 / 10.91 (from 8.00 / 8.87) | US cents/kWh | Jan-Jun 2026 | PJM states | EIA Table 5.6.B |
| Cheapest US industrial states | New Mexico 5.41, Oklahoma 6.44, Arkansas 6.63, Texas 6.65 | US cents/kWh | Jan-Jun 2026 | United States | EIA Table 5.6.B |
| Industrial price (mining and manufacturing), implied average revenue | 6.72 CAD = 4.91 US | cents/kWh | 2024 | Canada | Statistics Canada Table 25-10-0021 |
| Same, by province | NL 3.49, QC 4.92, MB 6.09, BC 6.66, ON 6.79, SK 8.82, AB 10.01 | CAD cents/kWh | 2024 | Canadian provinces | Statistics Canada Table 25-10-0021 |
| Large power, 50,000 kW, 30.6 GWh/month, excl. taxes | Winnipeg 5.09, Montreal 5.52, Vancouver 6.72, Calgary 7.99, Toronto 12.66 | CAD cents/kWh | 1 Apr 2025 | Canadian cities | Hydro-Quebec 2025 comparison |
| Same, US cities | Detroit 6.43, Chicago 6.45, Seattle 8.48, Houston 8.99, New York 15.95, Boston 17.13 | US cents/kWh | 1 Apr 2025 | US cities | Hydro-Quebec 2025 comparison |
| Large power, 5,000 kW, 3.06 GWh/month, excl. taxes | Montreal 5.83, Winnipeg 6.00, Calgary 8.02, Vancouver 8.42, Toronto 12.80, Houston 14.35, Boston 28.19 | CAD cents/kWh | 1 Apr 2025 | 22 cities | Hydro-Quebec 2025 comparison |
| Hydro-Quebec Rate L, large-power industrial tariff | 3.821 cents/kWh plus $15.027 per kW per month, 5,000 kW minimum | CAD | effective 1 Apr 2026 | Quebec | Hydro-Quebec 2026 Electricity Rates |
| Hydro-Quebec Rate CB, cryptographic use (blockchain), medium power | 6.292 cents/kWh plus $18.242 per kW per month | CAD | effective 1 Apr 2026 | Quebec | Hydro-Quebec 2026 Electricity Rates |
| Industrial tariff, 36-city average, supply at 35 kV and above | 0.620 CNY = about 8.7 US cents | per kWh | Jul 2026 | China | NDRC price monitoring via CEIC |
| Industrial price, indicative | about 17.5 JPY = about 11.7 US cents | per kWh | Oct 2025 | Japan | Intratec / GlobalPetrolPrices compilation |
| Large-industry rate after a 10.2 per cent increase | about 182.7 KRW = about 13.2 US cents | per kWh | 2025 | South Korea | Energynews on KEPCO |
| EU price for energy-intensive industry versus peers | more than 2x the United States, more than 50% above China and India, about 1.6x its own 2019 level | ratio | 2025 | EU | IEA, Electricity 2026 |
| Average wholesale price (not retail) | EU about 95, Germany about 100, United Kingdom just under 115, United States about 48, Nordics about 40 | USD/MWh | 2025 (US and Nordics H1 2025) | various | IEA, Electricity 2026 |
C4. The 2020 to 2026 price trend, Eurostat band IF, EUR/kWh excluding taxes. This is the European price spike and where it has settled.
Source for the whole table: Eurostat nrg_pc_205, extracted 2 September 2026, dataset last updated 11 August 2026.
North America over the same period, for contrast: the United States industrial price rose from 6.67 cents in 2020 to 8.62 in 2025 and 8.89 year to date through June 2026, a 33 per cent rise (EIA Table 5.3). Montreal's large-power rate rose from 5.24 Canadian cents in 2021 to 5.83 in 2025, an 11 per cent rise (Hydro-Quebec). Alberta spiked to 23.77 Canadian cents in 2023 and fell back to 8.02 by 2025.
C5. Residential prices, kept separate on purpose. These are a different and much higher number and must not be compared with anything above.
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Residential average retail price | 17.30 (2025), 18.16 year to date | US cents/kWh | 2025-2026 | United States | EIA Table 5.3 |
| Residential implied average revenue | 11.70 CAD = 8.54 US | cents/kWh | 2024 | Canada | Statistics Canada Table 25-10-0021 |
| Residential, 1,000 kWh a month, excl. taxes | Montreal 8.29, Winnipeg 10.53, Vancouver 12.60, Toronto 15.57, Calgary 22.90, Houston 26.07, Boston 47.87, New York 52.48, San Francisco 59.94 | CAD cents/kWh | 1 Apr 2025 | 22 cities | Hydro-Quebec 2025 comparison |
| Non-household price, Eurostat medium band IC (500 to 1,999 MWh), incl. non-recoverable taxes | EU average 0.1837; Ireland 0.2552; Germany 0.2264 | EUR/kWh | 2025 H2 | EU | Eurostat news release, 8 May 2026 |
The last row is the number most often quoted as "European industrial electricity prices." It is 68 per cent higher than the band IF figure for the same countries in the same half-year, because it covers small businesses and includes taxes. Using it to describe a data centre's cost is wrong by more than half.
C6. Data-centre specific tariffs and large-load rules. The important trend is that regulators everywhere are creating a separate price and a separate queue for data centres, which means the general industrial tariffs above are increasingly the wrong number for a new AI facility.
| Jurisdiction | Rule or rate | Value | Date | Status | Source |
|---|---|---|---|---|---|
| Quebec | Proposed data-centre rate, roughly double the large-power rate | about 13 CAD cents/kWh | February 2026 | Proposed, from late 2026 | Hydro-Quebec, via dimension 03 of this pack |
| Quebec | Rate L, the existing large-power industrial tariff | 3.821 CAD cents/kWh plus $15.027 per kW per month | effective 1 Apr 2026 | In force | Hydro-Quebec 2026 Electricity Rates |
| Quebec | Rate CB, cryptographic use applied to blockchains, the existing precedent for load-specific pricing of computing | 6.292 CAD cents/kWh plus $18.242 per kW per month (medium power) | effective 1 Apr 2026 | In force | Hydro-Quebec 2026 Electricity Rates |
| Ontario | Data Centre Playbook: facilities above 1 MW charged more than industrial programs; the minister states data centres pay 100 per cent of costs | not a published rate | posted August 2026, comments to 12 September 2026 | Draft | Ontario ERO 026-0853, via dimension 04 of this pack |
| Alberta | AESO interim large-load connection limit to 2028, against more than 20 GW of requests | 1,200 MW | 4 June 2025, fully allocated by October 2025 to Meta's GLDC Load (970 MW) and Keephills Phase I (230 MW) | In force | AESO |
| British Columbia | BC Hydro capacity released to data centres over two years | about 400 MW | 2025-2026 | In force | BC Hydro, via dimension 03 of this pack |
| Virginia | Dominion Energy proposes a separate GS-5 rate class for large load: 14-year contract terms, 85 per cent minimum charges, USD 1.5 million per MW collateral | contract terms, not a per-kWh rate | filed 3 September 2025 | Proposed | Virginia Mercury |
| PJM (United States mid-Atlantic) | Data-centre share of the capacity auction cost | USD 6.5bn of a USD 16.4bn auction (40 per cent); USD 29.4bn (46 per cent) across four auctions | December 2025 auction | Settled | Monitoring Analytics via Utility Dive, 2026, per dimension 05 of this pack |
| Ireland | The EirGrid Dublin moratorium on new grid connections for data centres was ENDED, replaced by a bring-your-own-power model | n/a | 12 December 2025 | In force | Energy Connects |
| Singapore | The 2019 moratorium was lifted in 2022 and replaced by a capacity allocation regime; the effect is visible in the numbers | about 1.46 GW live but only about 20 MW under construction against a 980 MW pipeline; 2 per cent vacancy | 2026 | In force | BMI via TechNode |
| Denmark | Grid-driven pause on new data-centre connections | 398 MW installed, 208 MW under construction | 2026 | In force | CNBC |
| Canadian municipalities | Local moratoria: Rocky View County (Alberta), Oakville (first Ontario municipality, one year), Mississauga pause | n/a | July to August 2026 | In force | Canadian Press, CBC, City of Mississauga, per dimension 03 of this pack |
Texas and ERCOT belong in this table and are not fully covered here. ERCOT's industrial price of 6.65 United States cents makes it the cheapest large United States market, its anticipated reserve margin of 28 to 30 per cent gives it the most headroom of any large North American system, and Texas passed large-load legislation in 2025 imposing curtailment obligations on data centres. The specific thresholds and curtailment terms of that legislation could not be verified from a primary source within this dimension and should be checked against the Public Utility Commission of Texas and ERCOT protocols before being quoted.
Read the metric column before quoting anything. The four main research houses measure four different things and their global totals differ by nearly a factor of two.
| Country or region | Value | Metric | Year | Source |
|---|---|---|---|---|
| World | 103 GW today, 200 GW by 2030 | Installed capacity | 2026 | JLL 2026 Global Data Center Outlook |
| World | 122.2 GW | Installed IT power capacity | Q1 2025 | Synergy Research via Data Center Knowledge |
| World | 67.7 GW, up 36% in two years | Facility power draw | 2026 | IDCA 2026 Data Center Report |
| United States | 29.2 GW, about 43% of global, about 6% of US electricity | Power consumption | 2026 | IDCA 2026 |
| United States | about 50 GW | Operating IT load | end-2025 | Global Data Center Hub, FERC-derived |
| Americas | 43.4 operational, 25.3 under construction, 191.3 pipeline (GW) | Operational capacity | 2026 | Cushman & Wakefield |
| China | 32 GW end-2025, about 40 GW end-2026 | Installed capacity | 2026 | Rystad Energy |
| EMEA | 11.4 operational, 2.7 under construction, 12.1 planned (GW) | Operational capacity | 2026 | Cushman & Wakefield |
| FLAP-D (Frankfurt, London, Amsterdam, Paris, Dublin) | 3.8 GW live, up from 1.8 GW in 2019 | Live capacity | H1 2026 | JLL EMEA |
| Ireland (Dublin) | 11.4 MW added; data centres take about 22% of national metered electricity | New supply; share | H1 2026; 2024 | JLL EMEA; IEA Electricity 2026 |
| Denmark (Nordics) | about 398 MW installed, 208 MW under construction | Installed capacity | 2026 | CNBC |
| India | about 1,530 MW operational IT stock, 3.1 GW pipeline | Operational IT stock | 2025-26 | CBRE India |
| Japan | about 3.8 GW; Tokyo alone above 1,000 MW at 6% vacancy | Installed IT load | 2026 | Mordor Intelligence (vendor); CBRE |
| Malaysia (Johor) | 1,110 MW operational, 602 MW under construction, 2,486 MW planned | Operational IT | H1 2026 | Fitch via TechNode |
| Singapore | about 1.46 GW live, only about 20 MW under construction, 2% vacancy | Live capacity | 2026 | BMI via TechNode |
| United Arab Emirates | more than 400 MW operational colocation, largest in the Gulf | Operational colocation | 2026 | Data Center World Middle East |
| Saudi Arabia | 467 MW operational against a 1.5 GW 2030 target | Operational capacity | Q1 2026 | Semafor |
| Australia | about 1.39 GW (derived) | Operating capacity | 2025 | Climate Council, derived |
| Brazil (Sao Paulo) | 536.7 MW inventory, 9.6% vacancy | Wholesale inventory | Q1 2026 | CBRE |
| Canada | about 1.4 GW live; 10.3 GW pipeline all stages; 20 to 22 GW proposed | Live and pipeline | 2025-26 | DC Byte; Canadian Press, Jul 2026 |
The four questions, answered as rankings.
Is Canada cheap? Yes, and it is one of the cheapest in the developed world, but it is not the cheapest and the advantage is concentrated in four provinces.
On the most defensible like-for-like comparison, Statistics Canada's implied industrial price against the EIA's, Canada was at 4.91 United States cents per kWh in 2024 against the United States at 8.13. Canada was 40 per cent cheaper. On the Hydro-Quebec comparison of posted large-power tariffs, Montreal at the 50,000 kW profile was 3.85 United States cents against Houston at 8.99, Toronto at 8.82, New York at 15.95 and Boston at 17.13. But on the Eurostat band IF and IG measures for large industrial consumers in Europe, Finland at 4.70 and Norway at 4.61 to 5.28 United States cents undercut Canada's national average. Ranking the large-industrial prices in this brief from cheapest to most expensive: Norway (4.61 band IG), Finland (4.70), Canada national average (4.91), Norway band IF (5.28), Texas (6.65), France (6.86 band IG), Sweden (7.21 band IG), United States average (8.62), China (about 8.7), Japan (about 11.7), European Union band IF average (12.36), South Korea (about 13.2), Germany (14.49), Ireland (18.97). Canada is third. Quebec alone, at 3.59 United States cents, would be first.
Two honest caveats. Alberta, the province with by far the largest data-centre pipeline, is Canada's most expensive at 7.31 United States cents industrial, above the Nordics and above Texas. And Quebec has proposed a data-centre specific rate of about 13 Canadian cents per kWh from late 2026, roughly double its industrial rate, which would erase most of Montreal's headline advantage for new AI load.
Is Canada clean? Yes, and it is a genuine top-five country, but not top-three and not uniform.
Canada is fifth in the world on non-emitting share among countries generating more than 100 TWh, at 77.0 per cent in 2025, behind Norway (99.0), Sweden (98.8), France (94.8) and Brazil (88.7). On Ember's lifecycle carbon intensity it ranks twelfth of the 48 countries generating more than 50 TWh, at 190.7 grams, behind Norway (28), Sweden (35), Switzerland (39), France (42), Finland (58), Belgium (109), Brazil (110), Austria (117), Portugal (128), Spain (154) and Colombia (187). On Canada's own operational method the number is about 86 grams, which would place it much higher. The provincial spread from 1.7 grams in Quebec to 730 in Saskatchewan is a factor of more than 400 and makes the national figure meaningless for siting.
Canada is unambiguously cleaner than every large competitor it actually competes with: the United States at 384 grams, China at 526, Japan at 477, Korea at 417, Malaysia at 603, Singapore at 497 and Saudi Arabia at 692. Against the Nordics and France, Canada loses.
Is Canada big? No.
Canada is seventh in the world by generation with 2.06 per cent of the world total, and tenth by capacity with 1.53 per cent. It is smaller than Russia, Japan and India and about the same size as South Korea, a country with 40 per cent more people on a quarter of the land. China generates 16 times as much electricity as Canada. The United States generates seven times as much. The more telling comparison is the rate of change: China added 434 GW of solar and wind capacity in 2025, 2.8 times Canada's entire fleet, while Canada added 1.1 GW of non-emitting capacity, or one four-hundredth of China's addition. Canada is not big and it is not adding capacity quickly.
Does Canada have spare room? Yes in Alberta, British Columbia and Saskatchewan. No in Quebec, Manitoba and the Maritimes.
NERC's 2025 Long-Term Reliability Assessment, which covers Canadian and United States areas on the same basis, gives Alberta an anticipated reserve margin of 36.2 per cent in 2026-27 falling only to 33.0 per cent in 2030-31, against a reference margin level of 11.8 to 17.6 per cent. Saskatchewan runs at 25.9 to 35.0 per cent against 15.0. British Columbia is 19.1 to 24.2 per cent against 11.6 to 12.1. Those three have real headroom.
Quebec does not. Its anticipated margin falls from 15.6 per cent in 2026-27 to 11.5 per cent in 2030-31 against a reference level of 12.2 per cent, and NERC's own summary states that "demand growth projections are outpacing planned resource additions, leading to projected resource shortfalls in the winter season." Manitoba collapses to 1.2 per cent by 2030-31 against a 12.0 per cent target. The Maritimes sit below their 20 per cent target in the first two years. Ontario is adequate but thin, at 18.7 per cent in 2029 against a 15.8 per cent reference.
For context, the United States comparators are worse in the two biggest markets: MISO falls to 4.3 per cent by 2030 against an 8.5 per cent reference, and PJM to 13.9 per cent against a reference rising to 26.3 per cent. ERCOT and California have large margins. So Canada's spare-room position is better than PJM's and MISO's, and worse than ERCOT's and California's, and inside Canada the headroom sits in exactly the province where the power is dirtiest and dearest.
The uncomfortable synthesis: Canada's competitive advantage is real but it is a Quebec, Manitoba, British Columbia and Newfoundland advantage, and those systems are either short of reserve margin or committed. The province with room to grow is the one where the pitch of cheap, clean power does not hold.
Carbon intensity for Canada: 190.7 or 86 grams? Ember reports 190.7 grams of CO2 per kilowatt hour for 2025 on a lifecycle basis; Environment and Climate Change Canada reports about 86 grams of CO2 equivalent for 2024 on an operational basis. Reverse-engineering Ember's own data file confirms it assigns 23.8 grams to hydro, 47.6 to solar, 11.7 to wind and 5.3 to nuclear, and uses a gas factor of 593 grams globally and 722 for Canada, well above direct combustion. Use Ember for country comparisons and ECCC for Canada alone. Never put them in the same column.
Price comparisons are sensitive to four things at once: taxes, exchange rate, consumption band and year. Eurostat band IC (500 to 1,999 MWh, including non-recoverable taxes) gives an EU average of 18.37 euro cents. Band IF for the same half-year excluding taxes gives 10.95, and band IG gives 9.98. That is a 45 per cent range on the same continent in the same six months, driven entirely by definition. Add exchange rate volatility (the Canadian dollar moved 5.4 per cent against the United States dollar in the year to April 2025 by Hydro-Quebec's own reckoning; the euro moved further) and the year of the data, and a careless comparison can be wrong by a factor of two in either direction. Every price in this brief carries its band, its tax treatment, its year and its conversion rate.
The IEA's "United States" industrial price is Texas. The IEA's chart of estimated final electricity prices for large industrial customers in energy-intensive industries uses Texas as its United States reference point and Eurostat's above-150 GWh band for Europe. Texas was 6.65 United States cents year to date through June 2026, 23 per cent below the national industrial average of 8.89 and 64 per cent below New England's 18.31. The IEA's headline that European prices are "more than double" United States prices is true against Texas and would be a smaller multiple against the United States average.
Ember's installed-capacity totals are constructed, not registry data. Ember's total is the sum of its clean and fossil capacity series. It agrees with Statistics Canada for Canada to within one per cent (156.0 against 156.4 gigawatts) which is reassuring, but it should not be treated as a definitive nameplate figure for every country, and 2025 capacity data are available for only about 90 countries against 195 for generation.
Data-centre capacity by country is the weakest data in this brief. Synergy, JLL, Cushman and Wakefield and IDCA report global totals of 122.2, 103, 43.4 (Americas only) and 67.7 gigawatts respectively, on four different definitions. A figure of about 5.5 gigawatts for Germany and about 2.0 for the United Kingdom circulates in aggregated coverage but could not be verified and is inconsistent with JLL's 3.8 gigawatt total for all five FLAP-D markets combined. No credible free national total exists for Korea, and Canada's roughly 1.4 gigawatts comes from DC Byte via a single law-firm summary. The United States ranges from 17.2 to 50 gigawatts depending on whose definition is used.
Statistics Canada's implied industrial price is average revenue, not a tariff. It is value of sales divided by quantity sold for the mining and manufacturing class. It blends contract and posted rates, includes some self-generation arrangements differently by province, and is not a price a new customer could sign. It is nevertheless the only official, consistent, province-by-province Canadian series, and its EIA counterpart is constructed the same way, which is why the two are compared here.
Quebec's proposed 13 cent data-centre rate is a proposal. It has been reported and is discussed in the companion dimensions of this pack, but its final level, scope and approval status are not settled. If approved at that level it would put Montreal's data-centre price above Toronto's current large-power rate and roughly at the level of the European Union band IF average, which would materially change the Canadian case.
Japan, Korea and China industrial prices in this brief are indicative, not official tariffs. The Japanese figure of about 17.5 yen per kilowatt hour and the Korean figure of about 182.7 won come from press and price-aggregator sources, not METI or KEPCO tariff sheets. The Chinese 36-city average of 0.62 yuan is an official NDRC monitoring series but covers supply at 35 kilovolts and above generally, not a data-centre tariff, and Chinese provincial rates vary from about 0.49 to 0.68 yuan. Treat all three as within roughly 20 per cent.
Sovereign programme money is not comparable across countries. Stargate's 500 billion United States dollars is a private consortium pledge. France's 109 billion euros is pledged foreign and private investment. The European Union's 200 billion euros is a mobilisation ambition. India's 1.2 billion United States dollars is an appropriated budget that is being under-spent. The United Kingdom's 2 billion pounds is appropriated. Adding these together produces a meaningless number.
Reserve margins are forecasts made by system operators with incentives. NERC's Anticipated Reserve Margin counts Tier 1 resources only and reflects each operator's own demand forecast. Since data-centre load forecasts are themselves contested (the IEA finds only about 20 per cent of United States connection requests materialise), the margins for areas with large speculative queues, notably Alberta, may be more comfortable than they look, or less, depending on which load actually shows up.
Prepared 2 September 2026 for the RHL Opening Week 2026 session "The opportunity of AI growth in Canada." Every figure carries the year of its source and, for prices, the customer class, the tax treatment and the exchange rate used. Where a price is residential it says so.
Start with the unit. A data centre is sized in megawatts because everything inside it, from the graphics processing units (GPUs) to the pumps and fans, turns electricity into heat, continuously. A conventional cloud facility considered by the International Energy Agency (IEA) is about 25 MW; a hyperscale site is 100 MW; the largest campuses under construction are around 2,000 MW and the largest planned about 5,000 MW. One MW running all year is 8,760 MWh, which is the electricity of roughly 750 average Canadian homes, or 450 Quebec homes that heat with electricity, or 1,160 Ontario homes that mostly heat with gas (NRCan, 2022 data). That is why a single 1 GW campus, at a 90% load factor, would use about 7.9 TWh a year, 1.3% of everything Canada generated in 2024 and about 9% of Alberta's 2025 output.
The AI difference is density and duty cycle. Traditional data centres serve web traffic, cluster near users to keep latency low, and run at moderate utilization. AI training clusters pack tens of thousands of GPUs into tightly coupled racks and run flat out for weeks; the IEA notes that training "is less latency-sensitive than traditional data centre workloads," which is why training sites can sit far from cities, next to power. Inference, the serving of trained models, is more mixed: a chatbot query tolerates tens of milliseconds and can be served from a distant region, while autonomous driving or trading cannot. In practice, the industry is separating remote, power-led training campuses from smaller, metro-located inference and colocation capacity, with edge computing on devices at the extreme.
Density drives cooling. For fifteen years a rack drew 4 to 10 kW and air cooling was enough. Uptime Institute's 2025 survey finds the typical rack still at about 9 kW and more than 80% of operators with nothing above 30 kW. An Nvidia GB200 NVL72 rack draws around 120 kW, and hyperscale halls now support over 135 kW per rack. Air cannot move that heat, so liquid is piped directly to the chips and rejected outdoors through dry coolers, cooling towers or evaporative systems. The choice sets the water bill: closed-loop designs use almost nothing (Meta's Alberta campus is designed to consume no water in normal operation), while evaporative cooling can consume 1.9 to 2.5 litres per kWh of IT load. Lawrence Berkeley National Laboratory (LBNL) puts the US average at 0.36 L/kWh in 2023, rising as liquid-cooled AI grows. A 100 MW IT load at 85% utilization therefore uses anywhere from near zero to about 1.4 billion litres a year depending on design, a fact that matters in Alberta's dry south and much less in Quebec or coastal BC.
Efficiency is summarized by power usage effectiveness (PUE), total facility energy divided by IT energy. The industry average of 1.54 has not moved in six years, but the frontier has: Google reports 1.09, hyperscale facilities average 1.14 worldwide, and new high-latitude builds routinely reach 1.3 or better. Cold climates help because economizers can use outside air or cold water for most of the year; Calgary has ten months with mean temperatures at or below 15 degrees C, Winnipeg, Edmonton and Quebec City nine, Montreal, Toronto and Vancouver eight. The gain is real but bounded: moving from PUE 1.5 to 1.2 cuts overhead by 30 percentage points of IT load, whereas the IT load itself is fixed by the chips. Climate improves the operating bill; it does not shrink the megawatts the utility must deliver.
Those megawatts are the hard part. Transformers, switchgear and substations are the bottleneck of the decade: Wood Mackenzie's mid-2025 survey shows power transformers averaging 128 weeks and generator step-up units 144 weeks, with prices up 77% since 2019. Grid connection queues run one to three years in the US on average, up to seven in Northern Virginia, up to ten in the Netherlands, and Dublin has paused new connections until 2030 (IEA). The IEA's 2026 update states plainly that grid waits of five to ten years and turbine deliveries of about five years are now the pacing items. Developers respond with behind-the-meter gas plants, batteries and long-dated nuclear deals, but each has its own queue: GE Vernova ended 2025 with an 80 GW turbine backlog and expects to be sold out through 2030; reliable onsite gas must be overbuilt by 30 to 70%; the first Canadian small modular reactor at Darlington costs $7.7 billion for 300 MW and arrives in 2030. Capital intensity follows: about US$11 million per MW to build the shell and power systems, up to US$25 million per MW more for AI compute, and in Canadian terms C$30 to 40 million per MW fully loaded.
Against that backdrop Canada's resource position is strong on paper. The grid is 78% non-emitting, hydro alone supplies 55% of generation, and the country exported 36 TWh to the United States in 2024. Industrial power in Winnipeg (5.09 cents per kWh) and Montreal (5.52) is the cheapest of 22 North American cities benchmarked by Hydro-Quebec, roughly a quarter of Boston or San Francisco and less than half of Toronto or Seattle. Canada has gas (17.9 Bcf/d, the Montney alone 8.1 Bcf/d), water, land, a critical minerals strategy covering copper and rare earths, a trans-Pacific fibre landing at Port Alberni and Vancouver (Topaz, 240 Tbps), and a construction workforce of 1.6 million.
The catch is that surplus has become scarce almost everywhere at once. Quebec, long the continent's exporter, was a net importer in 2023 after drought, exported only 5.9 TWh to the US in 2024, and plans 60 TWh and 8,000 to 9,000 MW of new supply by 2035 at a cost of $155 to 185 billion; it now requires ministerial authorization for any load above 5 MW and proposes a data centre rate of 13 cents per kWh, about double today's large-power rate. British Columbia imported 14.5 TWh from the US in 2024, has just absorbed Site C's 1,100 MW, and is offering a total of 400 MW to AI and data centres over two years through a competitive call that was roughly twice oversubscribed. Manitoba's hydro is spoken for by export contracts and needs new capacity by 2029; it screens every request above 5 MW and has already rejected one 100 MW proposal. Ontario plans for demand to grow 65% to 250 TWh by 2050, with data centres 13% of new demand by 2035, and is betting on refurbished and new nuclear while legislating priority for data centres that bring jobs and domestic hosting. New Brunswick faces a capacity shortfall by 2028 before any data centre connects; Nova Scotia still burns coal and says supply comes first.
Alberta is where the numbers are largest and the fuel is different. Its deregulated market delivered the lowest pool price in eight years in 2025 ($43.68/MWh) and has a supply cushion, but 20.7 GW of data centre requests against a 12.8 GW peak cannot be served by the grid; only 1,200 MW was allocated for 2027/28, and the 2026 Data Centre Regulation now gives priority to "tethered" projects that bring their own generation. Meta's Sturgeon County campus is the template: 1 GW growing to 1.8 GW, a dedicated 932 MW combined-cycle gas plant, closed-loop cooling with no water draw, and a 2030 in-service date for the power plant. The province can host gigawatts, but on gas, which is what the Canada Energy Regulator's scenarios, Ottawa's emissions rules and the tech companies' own clean-energy commitments will all have to reconcile.
For managers the arithmetic is simple. Every 100 MW of AI capacity needs a 110 to 150 MW grid connection, a substation whose transformers take two to three years, water or dry-cooling choices that fix the local footprint, and either a utility with firm surplus or a power plant of its own. Canada has the cheapest clean electrons in North America in Manitoba and Quebec, the largest gas-backed pipeline of projects in Alberta, the deepest nuclear build-out in Ontario, and almost no uncommitted capacity anywhere before 2028 to 2030. The opportunity is real; the constraint is time, iron and firm megawatts, and the provinces that move fastest on new supply and connection rules will capture it.
| Metric | Value | Unit | Year | Region | Source (URL) |
|---|---|---|---|---|---|
| Global data centre electricity consumption | 415 (2024); 485 (2025); 950 (2030 projection) | TWh | 2024-2030 | World | IEA Key Questions on Energy and AI (https://iea.blob.core.windows.net/assets/3179f7f8-01f6-4dd6-bffa-c9f7b73f1dc9/KeyQuestionsonEnergyandAI.pdf) |
| Growth in data centre electricity demand | 17 | % year on year | 2025 | World | IEA news, 16 April 2026 (https://www.iea.org/news/data-centre-electricity-use-surged-in-2025-even-with-tightening-bottlenecks-driving-a-scramble-for-solutions) |
| Installed data centre capacity, world / North America | 97 / 43 (2024); 226 / 102 (2030 Base Case) | GW | 2024, 2030 | World, North America | IEA Energy and AI, Table A.2 (https://iea.blob.core.windows.net/assets/de9dea13-b07d-42c5-a398-d1b3ae17d866/EnergyandAI.pdf) |
| US data centre electricity use | 176 (4.4% of US); 325 to 580 (2028) | TWh | 2023, 2028 | United States | LBNL 2024 report (https://eta-publications.lbl.gov/sites/default/files/2024-12/lbnl-2024-united-states-data-center-energy-usage-report_1.pdf) |
| Share of electricity used by servers / cooling | 60 / 7 to over 30 | % | 2025 | World | IEA Energy and AI (same URL) |
| Average PUE, industry survey | 1.54 (all); 1.44 (20 MW+); 1.48 (built since 2020) | ratio | 2025 | World | Uptime Institute survey 2025 (https://datacenter.uptimeinstitute.com/rs/711-RIA-145/images/2025.Annual.Survey.Report.pdf) |
| PUE by type, world average | 1.14 hyperscale; 1.53 colocation; 1.92 enterprise; 1.41 total | ratio | 2024 | World | IEA Energy and AI, Table A.1 |
| PUE, North America | 1.32 (2024); 1.24 (2030) | ratio | 2024, 2030 | North America | IEA Energy and AI, Table A.3 |
| Best-in-class fleet PUE | 1.09 | ratio | 2025 | Google fleet | Google (https://datacenters.google/efficiency/) |
| US average PUE | 1.4 (2023); 1.15 to 1.35 (2028) | ratio | 2023, 2028 | United States | LBNL 2024 |
| Site WUE, US average | 0.36 (2023); 0.45 to 0.48 (2028) | L per IT kWh | 2023, 2028 | United States | LBNL 2024 |
| WUE, industry average / evaporative maximum | 1.9 / about 2.5 | L per kWh | 2025 | US | EESI (https://www.eesi.org/articles/view/data-centers-and-water-consumption) |
| US data centre direct water use | 66 (2023); hyperscale alone 60 to 124 (2028) | billion litres | 2023, 2028 | United States | LBNL 2024 |
| Typical rack density (modal average) | 9 (8.3 in 2024); over 80% of sites have no rack above 30 kW | kW per rack | 2025 | World | Uptime 2025 |
| GB200 NVL72 rack power | about 120 (132 observed at full load in third-party deployments) | kW per rack | 2025 | Product | Nvidia blog (https://blogs.nvidia.com/blog/blackwell-platform-water-efficiency-liquid-cooling-data-centers-ai-factories) |
| Power transformer / GSU / switchgear lead time | 128 / 144 / 44 | weeks | Q2 2025 | North America | POWER citing Wood Mackenzie (https://www.powermag.com/transformers-in-2026-shortage-scramble-or-self-inflicted-crisis/) |
| Grid connection queue | US 1 to 3; N. Virginia up to 7; Netherlands up to 10; Dublin paused to 2030 | years | 2025 | Selected | IEA Energy and AI, Table 2.4 |
| Gas turbine delivery / backlog | about 5 years; GE Vernova 80 GW backlog into 2029 | years, GW | 2025 | World | IEA 2026; Utility Dive (https://www.utilitydive.com/news/ge-vernova-gas-turbine-investor/807662/) |
| Onsite gas overbuild needed for reliability | 30 to 70 | % above load | 2026 | World | IEA Key Questions 2026 |
| Construction cost, global | US$10.7 million (2025); US$11.3 million (2026); US$7.7 million (2020) | per MW | 2020-2026 | World | JLL (https://www.jll.com/en-us/insights/global-data-center-outlook) |
| Construction cost, Canada | C$7 to 12 million shell and core; about C$20 million AI-optimized; C$30 to 40 million fully loaded | per MW | 2026 | Canada | Encor Advisors (https://encoradvisors.com/data-center-cost/) |
| Darlington SMR cost | $20.9 billion for 4 x 300 MW; first unit $7.7 billion; 14.9 cents per kWh projected | C$ | 2025 | Ontario | World Nuclear News (https://world-nuclear-news.org/articles/what-is-the-budget-for-canadas-first-smr-project) |
| Average Canadian household electricity | 11,650 (Canada); 19,600 (Quebec); 7,560 (Ontario); 10,190 (BC); 7,320 (Alberta) | kWh per year | 2022 | Canada | NRCan NEUD (https://oee.nrcan.gc.ca/corporate/statistics/neud/dpa/showTable.cfm?type=CP§or=res&juris=ca&year=2022&rn=1&page=0) |
| Homes served by 1 MW at 100% load | about 750 (Canada average); 450 (Quebec); 1,160 (Ontario) | homes | 2022 basis | Canada | Analyst calculation from NEUD, 8,760 MWh per MW-year |
| Site C output versus homes | 5,100 GWh for about 500,000 homes (10,200 kWh each) | GWh, homes | 2025 | BC | BC Hydro (https://www.bchydro.com/news/press_centre/news_releases/2025/site-c-full-operation.html) |
| Metric | Value | Unit | Year | Source (URL) |
|---|---|---|---|---|
| Total generation | 622.2 | TWh | 2024 | Statistics Canada, The Daily 22 Oct 2025 (https://www150.statcan.gc.ca/n1/daily-quotidien/251022/dq251022c-eng.htm) |
| Hydro share / renewables share | 55.2 / 63.9 | % | 2024 | Same |
| Non-emitting share (hydro, nuclear, wind, solar, tidal) | 77.9 (2024); 77.0 (2025) | % | 2024, 2025 | Analyst calculation from StatCan Table 25-10-0015-01 (https://www150.statcan.gc.ca/t1/tbl1/en/tv.action?pid=2510001501) |
| Nuclear generation | 80.7 | TWh | 2024 | StatCan Daily |
| Exports to US / imports from US | 36.1 / 23.5 | TWh | 2024 | StatCan Daily |
| Largest exporters to US | Ontario 12.8; BC 6.3; Manitoba 6.0 | TWh | 2024 | StatCan Daily |
| Largest importer from US | BC 14.5 | TWh | 2024 | StatCan Daily |
| Sales to end users / residential sales | 503.3 / 179.6 | TWh | 2024 | StatCan Table 25-10-0021-01 (https://www150.statcan.gc.ca/t1/tbl1/en/tv.action?pid=2510002101) |
| Installed capacity, all Canada | about 160 | GW | 2023 | CER Energy Future 2026 (https://www.cer-rec.gc.ca/en/data-analysis/canada-energy-future/2026/results/) |
| Demand growth to 2050 | +30 (Lower) to +120 (Net-zero); about +50 (Current Measures) | % vs 2023 | 2050 | CER Energy Future 2026 |
| Data centre demand by 2050 | 1.5 to 12 GW; about 100 TWh (a quarter of growth) in Higher scenario | GW, TWh | 2050 | CER via Canadian Press (https://www.pentictonherald.ca/news/national_news/article_2d1def2f-1143-598d-8076-90a558ba8a52.html); CER results page |
| Provincial system outlooks, aggregate demand | 604 (2025) to 982 (2050), +62% | TWh | 2025-2050 | Transition Accelerator, Nov 2025 (https://transitionaccelerator.ca/wp-content/uploads/2025/11/Forecasting-Canadas-Electricity-Future-Report-Final-November-2025.pdf) |
| Natural gas production, Canada / Montney | 17.9 (2023) / 8.1 (2022, 47% of Canada) | Bcf/d | 2022-2023 | CER Canada profile; CER Energy Future 2023 (https://www.cer-rec.gc.ca/en/data-analysis/canada-energy-future/2023/canada-energy-futures-2023.pdf) |
Non-emitting share here counts hydro, nuclear, wind, solar and tidal only; biomass is excluded. The StatCan monthly table totals 609.5 TWh for 2024 against 622.2 TWh in the annual survey; shares are internally consistent within each table.
| City | Cents per kWh (C$) | Index (Montreal = 100) |
|---|---|---|
| Winnipeg, MB | 5.09 | 92 |
| Montreal, QC | 5.52 | 100 |
| Vancouver, BC | 6.72 | 122 |
| St. John's, NL | 7.66 | 139 |
| Calgary, AB | 7.99 | 145 |
| Edmonton, AB | 8.05 | 146 |
| Regina, SK | 8.05 | 146 |
| Miami, FL | 8.68 | 157 |
| Detroit, MI | 9.22 | 167 |
| Chicago, IL | 9.25 | 168 |
| Nashville, TN | 10.04 | 182 |
| Moncton, NB | 10.63 | 193 |
| Charlottetown, PE | 11.27 | 204 |
| Seattle, WA | 12.16 | 220 |
| Ottawa, ON | 12.31 | 223 |
| Portland, OR | 12.35 | 224 |
| Toronto, ON | 12.66 | 229 |
| Houston, TX | 12.90 | 234 |
| Halifax, NS | 13.43 | 243 |
| New York, NY | 22.88 | 414 |
| San Francisco, CA | 23.88 | 432 |
| Boston, MA | 24.58 | 445 |
| Average of 22 cities | 11.61 |
For a 5,000 kW customer at 85% load factor the same ranking holds: Montreal 5.83, Winnipeg 6.00, Calgary 8.02, Vancouver 8.42, Regina 9.57, Edmonton 10.17, Ottawa 12.75, Toronto 12.80, Halifax 13.43 cents per kWh. Alberta's 2025 average pool price of $43.68/MWh (4.37 cents) is energy only; the Hydro-Quebec figures for Calgary and Edmonton are estimated all-in bills.
| City | Annual mean, deg C | Coldest month | Warmest month | Months with mean at or below 15 deg C (illustrative economizer proxy) |
|---|---|---|---|---|
| Winnipeg | 2.9 | Jan -16.3 | Jul 19.5 | 9 |
| Edmonton | 4.2 | Jan -10.3 | Jul 18.1 | 9 |
| Calgary | 4.5 | Jan -7.6 | Jul 16.9 | 10 |
| Quebec City | 4.7 | Jan -11.9 | Jul 19.5 | 9 |
| Montreal | 7.0 | Jan -9.2 | Jul 21.7 | 8 |
| Toronto | 9.7 | Jan -3.5 | Jul 22.5 | 8 |
| Vancouver | 10.5 | Dec 3.9 | Jul and Aug 18.2 | 8 |
The 15 degree threshold is an analyst simplification for comparing cities; actual economizer hours depend on humidity, design supply temperature and cooling architecture. A Montreal operator claims outside-air economization up to 80% of the year (Vantage Data Centers).
| Metric | 2024 | 2025 |
|---|---|---|
| Average pool price ($/MWh) | 62.78 | 43.68 (median $23; 10-year inflation-adjusted average $78) |
| Average Alberta Internal Load (MW) | 10,112 | 10,316 |
| Winter peak (MW) | 12,241 | 12,785 (record, December 2025) |
| Installed capacity (MW) | 23,122 | 23,242 (gas 14,182; wind 5,684; solar 1,850) |
| Average supply cushion (MW) | 1,794 | 1,960 |
| Gas-fired share of generation | 76.8%; wind, solar and hydro 21.0% |
Start with one chip and one number. An accelerator is a specialised processor that does the arithmetic behind AI. The best known is NVIDIA's H100 graphics processing unit (GPU), and NVIDIA's own specification says its maximum thermal design power, the heat its cooling system must be built to remove, is up to 700 watts. That single figure is the seed from which every other number in this brief grows. A domestic kettle is about 1,500 watts, so two H100s running flat out are roughly one kettle, permanently on, for five years.
The escalation is the story, not the level. In 2016 NVIDIA's flagship data centre chip, the Tesla P100, drew 300 watts. The A100 in 2020 drew 400. The H100 in 2022 drew 700. In 2025 AMD published a maximum total board power of 1,400 watts for its Instinct MI355X, and NVIDIA's Blackwell Ultra is reported at the same figure. AMD is the cleanest illustration because it publishes one comparable number per part in a datasheet: 750 watts for the MI300X in 2023, 1,000 for the MI350X and 1,400 for the MI355X in 2025. That is a near doubling in two years, and it happened because performance per chip rose faster than efficiency per watt. Chips did become more efficient; they just got bigger faster.
Above roughly forty kilowatts a rack, air stops working. A rack is a standard cabinet about the size of a fridge. For twenty years the typical rack drew under ten kilowatts and was cooled by blowing cold air through it. Uptime Institute's July 2025 survey found more than 80% of operators still have no rack above thirty kilowatts and only 22% use direct liquid cooling. Meanwhile NVIDIA's GB200 NVL72, which packs 72 Blackwell GPUs and 36 Grace central processing units into one cabinet, draws about 120 kilowatts, and NVIDIA's own reference architecture states its successor, the GB300 NVL72, requires up to 142 kilowatts, fed by eight power shelves of 33 kilowatts each. Air physically cannot move that much heat. So the industry has moved to direct-to-chip liquid cooling, in which water or a coolant runs through a metal cold plate bolted onto the chip, capturing roughly 80% of the heat in a closed loop. Immersion cooling, in which whole servers sit in a bath of non-conductive fluid, handles even higher densities but is still rare. The practical threshold where liquid becomes mandatory is somewhere between thirty and fifty kilowatts a rack, and NVIDIA and AMD have settled the question for their customers by shipping their top parts as liquid-only. NVIDIA now says today's racks exceed 200 kilowatts and projects one-megawatt racks in 2027.
From one chip to one building. The manager's question is how many accelerators fit in a given amount of power. Build it in three steps. First, chip to server: NVIDIA's own DGX H200 puts eight 700-watt GPUs in a chassis rated at 10.2 kilowatts, a multiplier of about 1.8 once the host processors, memory, storage, fans and power supply losses are counted. In a rack-scale system that overhead is already inside the published rack figure, so 120 kilowatts divided by 72 GPUs is about 1,670 watts per GPU. Second, add the network switches and storage that sit outside the compute rack, roughly 8 to 10% more. Third, multiply by power usage effectiveness (PUE), the ratio of total building power to information technology (IT) power, which is about 1.15 for a new cold-climate liquid-cooled hall and 1.30 for a merely competent one. The answer is that one accelerator needs roughly 1.5 to 2.5 kilowatts of facility power, and a modern AI data centre holds roughly 400 to 500 accelerators per megawatt, about half a million per gigawatt.
Two real installations confirm it. xAI's Colossus in Memphis ran 100,000 NVIDIA Hopper GPUs, a figure NVIDIA itself published in October 2024, against 150 megawatts of grid supply approved by the local utility and the Tennessee Valley Authority. That is 1.5 kilowatts per GPU, within 10% of the bottom-up estimate. TELUS announced in May 2026 that its British Columbia cluster will hold over 60,000 NVIDIA GPUs against more than 150 megawatts by 2032: exactly 400 accelerators per megawatt, which is what the arithmetic gives for a Blackwell Ultra or Rubin class part. Larry Ellison's claim of more than 450,000 GB200 GPUs at Stargate Abilene against a 1.2 gigawatt grid interconnect implies 2.67 kilowatts per GPU, at the high end of the same band. The rule holds across three companies, two countries and three chip generations, which is the best evidence that it is not a coincidence.
What that costs. At Epoch AI's transparent estimate of US$25,000 per H100 and US$37,000 to US$43,000 per Blackwell part, a 100 megawatt campus contains roughly 43,000 to 48,000 Blackwell GPUs, which is about 725 GB200 NVL72 racks. At HSBC's estimated US$3 million per rack, that is about US$2.2 billion of silicon and racks before a single wall is built. Two independent checks agree: JLL puts AI technology fit-out at up to US$25 million per megawatt, that is US$2.5 billion for 100 megawatts, and Jensen Huang's stated US$50 to 60 billion per gigawatt with about US$35 billion of NVIDIA content implies US$3.5 billion of NVIDIA content per 100 megawatts. Against that, the electricity is almost cheap: C$43 million a year at Manitoba or Quebec industrial rates. The capital is the constraint, and the capital sits in a five-year asset.
Which is why depreciation is the real argument. Two haircuts sit under every headline GPU count. The first is operational. Meta's own Llama 3 paper reports model FLOPs utilisation, the share of a cluster's theoretical arithmetic actually used, of 38% to 43% on up to 16,000 H100s, with effective training time above 90%. So the compute actually delivered is roughly 35 to 39% of the nameplate number in the press release. The same paper records 466 job interruptions in 54 days, with about 78% traced to hardware and 220 of them to failed GPUs or failed high-bandwidth memory: a failure roughly every three hours. The second haircut is financial. In the same twelve months, Amazon shortened the assumed useful life of a subset of its servers from six years to five, explicitly citing the pace of AI, which added about US$1.4 billion of depreciation and cut fiscal 2025 net income by about US$1.0 billion. Meta went the other way, lengthening most servers to 5.5 years, which reduced depreciation by about US$2.92 billion and lifted net income by about US$2.59 billion. Alphabet uses six years, Microsoft two to six, CoreWeave six. Michael Burry's November 2025 argument was that the real economic life is two to three years and that the industry is therefore understating depreciation by roughly US$176 billion between 2026 and 2028. The counter-argument is that older accelerators cascade to cheaper work rather than becoming scrap, and that A100s from 2020 still rent. Both sides are arguing about the same unknown, which is how fast a 700-watt chip becomes uneconomic when a 1,400-watt chip delivers five times the work. For anyone financing a Canadian data centre, this single assumption swings the return more than the electricity price does.
The units, one last time. A megawatt is a rate; a megawatt-hour is an amount. A gigawatt data centre in Canada would consume 7.88 terawatt-hours a year at a 90% load factor, which is 1.26% of the 625.2 terawatt-hours Canada generated in 2025 and about 1.4% of the 71 gigawatts the entire country produces on average. It would hold roughly half a million accelerators, about six thousand liquid-cooled racks, and about US$20 billion of silicon. It would cost between C$434 million and C$1.02 billion a year to power depending on where in Canada it sits. Those five numbers, held together, are enough to interrogate almost any claim made about this industry.
Everything in this brief reduces to one distinction. Power is a rate: how fast energy is being used, measured in watts. Energy is an amount: how much was used, measured in watt-hours. A grid operator sizes wires, transformers and generators against the rate. A finance team pays for the amount. Confusing the two is the most common error in public discussion of data centres.
| Unit | Symbol | What it is | Roughly equal to |
|---|---|---|---|
| Watt | W | One joule per second | An LED bulb, 8 to 10 W |
| Kilowatt | kW | 1,000 W | A hair dryer, or a home fast charger at 7 kW |
| Megawatt | MW | 1,000 kW, one million W | About 750 average Canadian homes at their annual average draw |
| Gigawatt | GW | 1,000 MW, one billion W | One Darlington CANDU unit is about 0.9 GW |
| Terawatt | TW | 1,000 GW, one trillion W | Canada's whole electricity system averages 0.071 TW, that is 71 GW |
Nameplate, or capacity, is the maximum rate the equipment is designed to draw or produce. It is what the utility must be able to deliver at any instant.
| Unit | Symbol | What it is |
|---|---|---|
| Watt-hour | Wh | One watt sustained for one hour |
| Kilowatt-hour | kWh | The unit on the electricity bill, and the unit in which power is priced |
| Megawatt-hour | MWh | 1,000 kWh |
| Gigawatt-hour | GWh | 1,000 MWh |
| Terawatt-hour | TWh | 1,000 GWh, one billion kWh; the unit of national statistics |
The bridge between rate and amount is time, and it is exact:
Data centres run close to baseload, near their maximum almost all the time, unlike a factory with shifts. At a 90% load factor, a realistic planning figure for an AI campus, one MW delivers 7.884 GWh a year rather than 8.76.
All rows assume a 90% load factor. Homes use the Natural Resources Canada figure of about 11,650 kWh per Canadian household per year. The Canadian share uses Statistics Canada's 625.2 TWh of total generation in 2025. Costs are Canadian cents per kilowatt-hour at the two ends of the Canadian industrial range: 5.5 cents, roughly Winnipeg (5.09) or Montreal (5.52) for a 50 MW customer, and 13 cents, roughly Toronto (12.66) or Halifax (13.43), from Hydro-Quebec's price comparison at rates in effect 1 April 2025.
| Facility size | Energy per year | Average Canadian homes | Share of Canada's 2025 generation | Bill at 5.5c/kWh | Bill at 13c/kWh |
|---|---|---|---|---|---|
| 1 MW | 7.88 GWh (0.0079 TWh) | 677 | 0.001% | C$0.43 million | C$1.02 million |
| 10 MW | 78.8 GWh (0.079 TWh) | 6,767 | 0.013% | C$4.3 million | C$10.2 million |
| 100 MW | 788 GWh (0.79 TWh) | 67,674 | 0.126% | C$43.4 million | C$102.5 million |
| 1 GW | 7,884 GWh (7.88 TWh) | 676,738 | 1.26% | C$434 million | C$1.02 billion |
Three things fall straight out of that table. First, the electricity bill for a gigawatt campus is roughly half a billion Canadian dollars a year at cheap Canadian industrial rates and about a billion at expensive ones, so a 7.5 cent spread is worth about C$590 million a year. That is why siting is a board-level decision. Second, one gigawatt campus is 1.26% of everything Canada generates, and Canada's whole system averages only 71 GW, so the 20.7 GW of Alberta data centre applications reported in September 2025 is not a rounding error. Third, at a 100% load factor the homes figure is 752 per MW, so the common shorthand "a megawatt powers 750 homes" is right for a facility running flat out and about 10% too high at a realistic load factor.
A grid operator cares about the rate because a power system must match supply and demand instant by instant, and because building the rate is slow and lumpy. A finance team cares about the amount because the amount is what appears in the cash flow statement. The bridge between them is the load factor, and for AI the load factor is high, which is good for a utility's revenue per dollar of asset and bad for its ability to say yes.
Thermal design power (TDP) is the maximum sustained heat, and therefore power, the cooling solution must remove for that part alone. It excludes the host processor, storage, the network card and everything in the building. AMD publishes the equivalent as total board power (TBP).
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| NVIDIA Tesla P100 (SXM2) max power | 300 | W | 2016 | Global | NVIDIA P100 datasheet |
| NVIDIA Tesla V100 (SXM2) TDP | 300 | W | 2017 | Global | NVIDIA Volta architecture whitepaper |
| NVIDIA A100 PCIe / SXM max TDP | 300 / 400 | W | 2020 | Global | NVIDIA A100 datasheet |
| NVIDIA H100 SXM max TDP | up to 700 (configurable) | W | 2022 | Global | NVIDIA H100 product page |
| NVIDIA H100 PCIe / NVL max TDP | 350 / 350 to 400 | W | 2022-24 | Global | NVIDIA H100 NVL product brief |
| NVIDIA H200 SXM max TDP | up to 700 (configurable) | W | 2023 | Global | NVIDIA H200 datasheet |
| AMD Instinct MI300X max TBP | 750 | W | 2023 | Global | AMD MI300X datasheet |
| NVIDIA B200 / GB200 Blackwell per GPU | about 1,000 air, about 1,200 liquid | W | 2024-25 | Global | derived from NVIDIA GB200 NVL72 rack figures |
| AMD Instinct MI350X max TBP | 1,000 | W | 2025 | Global | AMD MI350X datasheet |
| AMD Instinct MI355X max TBP (liquid only) | 1,400 | W | 2025 | Global | AMD MI355X datasheet |
| NVIDIA B300 / GB300 Blackwell Ultra per GPU | about 1,400 (reported, not an NVIDIA datasheet figure) | W | 2025 | Global | Tom's Hardware |
| Google TPU v7 Ironwood, derived per chip | about 1,080 | W | 2025 | Global | derived from Google Ironwood announcement (9,216 chips, nearly 10 MW) |
| Cerebras WSE-3 wafer / CS-3 system | about 15,000 / 23,000 | W | 2024 | Global | Cerebras CS-3 |
| NVIDIA Rubin R200 per GPU (analyst estimate) | about 1,800 (Max Q) to 2,300 (Max P) | W | 2026 | Global | Ming-Chi Kuo supply chain note |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| NVIDIA DGX H200 system (8 GPUs) max power | 10.2 | kW | 2023 | Global | NVIDIA DGX H200 datasheet |
| NVIDIA GB200 NVL72 rack (72 GPUs) | about 120 | kW | 2024-25 | Global | NVIDIA GB200 NVL72 (specification table omits power; 120 kW is NVIDIA and partner deployment guidance) |
| NVIDIA GB300 NVL72 rack (72 GPUs) | up to 142 | kW | 2025 | Global | NVIDIA NVL72 AI Factory reference architecture |
| GB300 NVL72 power delivery | 8 shelves of 33 kW, six 5.5 kW PSUs each | n/a | 2025 | Global | NVIDIA reference architecture |
| Google TPU v7 Ironwood pod (9,216 chips) | nearly 10 | MW | 2025 | Global | |
| NVIDIA stated rack power today | exceeds 200 | kW | 2025 | Global | NVIDIA 800 VDC blog |
| NVIDIA projected IT rack power, 2027 (Kyber) | 1 | MW per rack | 2027 | Global | NVIDIA 800 VDC blog |
| Copper busbar in a 1 MW rack at 54 VDC | up to 200 | kg | 2025 | Global | NVIDIA 800 VDC blog |
| Copper in a 1 GW data centre | up to 200,000 | kg | 2025 | Global | NVIDIA 800 VDC blog |
| Operators with no rack above 30 kW | more than 80 | % of operators | 2025 | Global | Uptime Institute Global Data Center Survey 2025 |
| Organisations using direct liquid cooling | 22 | % | 2025 | Global | Uptime Institute cooling survey 2025 |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Global data centre electricity | 415 | TWh | 2024 | World | IEA, Energy and AI |
| Global data centre electricity, base case | about 945 | TWh | 2030 | World | IEA, Energy and AI |
| Servers share of data centre electricity | about 60 | % | 2024 | World | IEA, Energy and AI |
| Cooling share, efficient hyperscale to inefficient enterprise | 7 to over 30 | % | 2024 | World | IEA, Energy and AI |
| Storage share / networking share | about 5 / up to 5 | % | 2024 | World | IEA, Energy and AI |
| Canada total electricity generation | 625.2 | TWh | 2025 | Canada | Statistics Canada |
| Canada average electrical output | 71.4 | GW | 2025 | Canada | derived from Statistics Canada 625.2 TWh over 8,760 hours |
| Average Canadian household electricity use | 11,650 | kWh per year | 2022 | Canada | NRCan Comprehensive Energy Use Database |
Method: take the accelerator TDP, apply the system overhead (NVIDIA's own DGX H200 is 10.2 kW for eight 700 W GPUs, a multiplier of about 1.8; in a rack-scale system the overhead is already inside the published rack figure), add 8 to 10% for scale-out networking and storage outside the compute rack, then multiply by PUE.
| Accelerator | Chip TDP | IT W per accelerator | Facility W at PUE 1.15 | Facility W at PUE 1.30 | Accelerators per MW |
|---|---|---|---|---|---|
| H100 / H200 SXM | 700 W | about 1,400 | about 1,610 | about 1,820 | 550 to 620 |
| GB200 Blackwell in NVL72 | about 1,200 W | about 1,800 | about 2,070 | about 2,340 | 430 to 480 |
| GB300 Blackwell Ultra in NVL72 | about 1,400 W | about 2,130 | about 2,450 | about 2,770 | 360 to 410 |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Estimated cost per H100 or H200 | 25,000 | US$ | 2026 | Global | Epoch AI methodology |
| Estimated cost per B200 / B300 | 37,000 / 43,000 | US$ | 2026 | Global | Epoch AI methodology |
| Jensen Huang on Blackwell GPU price | 30,000 to 40,000 | US$ | 2024 | Global | TechSpot reporting a CNBC interview |
| Fully equipped GB200 NVL72 rack | about 3,000,000 | US$ | 2025 | Global | HSBC estimate via TweakTown |
| Chip and rack capital, 100 MW Blackwell campus | about 2.2 | US$ billion | 2026 | Global | derived: about 725 NVL72 racks at US$3 million |
| AI technology fit-out per MW | up to 25 | US$ million | 2026 | Global | JLL 2026 Global Data Center Outlook (via brief 08) |
| Jensen Huang on cost of 1 GW of AI factory | 50 to 60, of which about 35 is NVIDIA | US$ billion | 2025 | Global | Crypto Briefing report of G20 remarks |
| NVIDIA data centre revenue, fiscal 2026 | 193.7 | US$ billion | 2026 | Global | NVIDIA |
| NVIDIA AI accelerators shipped, calendar 2025 (estimate) | about 4.46 | million units | 2025 | Global | Epoch AI |
| Measured model FLOPs utilisation, 16,000 H100 Llama 3 run | 41 (range 38 to 43) | % | 2024 | United States | Meta, The Llama 3 Herd of Models |
| Hardware interruptions in a 54 day training run | 466 | interruptions | 2024 | United States | Meta, The Llama 3 Herd of Models |
| Amazon server useful life | 5, reduced from 6 | years | 2025 | United States | Amazon 10-K FY2025 |
| Meta server useful life | 5 to 5.5, raised from 5 | years | 2025 | United States | Meta 10-K FY2025 |
| Alphabet server useful life | 6 | years | 2025 | United States | Alphabet 10-K FY2025 |
| Burry estimate of understated depreciation, 2026-28 | 176 | US$ billion | 2025 | United States | CNBC |
Nothing in this section is a product. The most useful discipline is to sort every claim into three tenses: what has flown and worked, what has been filed with a regulator, and what has been said on a stage. The gap between the three is about three orders of magnitude.
| Operator | Hardware | Date | What it did | Source |
|---|---|---|---|---|
| ADA Space and Zhejiang Lab (China) | 12 satellites, Three-Body Computing Constellation | 14 May 2025 | 5 POPS combined, 30 TB storage, 100 Gbps laser links (company claims). Target constellation 2,800 satellites and 1,000 POPS, 100 satellites by 2027 | SpaceNews |
| Axiom Space with Red Hat | AxDCU-1 prototype unit on the ISS | August 2025 | Hybrid cloud, AI/ML and cybersecurity workloads on orbit | Axiom Space |
| Starcloud with NVIDIA | Starcloud-1, 60 kg, one NVIDIA H100 | Launched 2 November 2025 on Falcon 9 Bandwagon-4 | First data centre class GPU in orbit; trained nanoGPT on Shakespeare in December 2025, the first language model trained in space; also ran Gemma | Starcloud |
| Axiom Space | Two free-flying Orbital Data Center nodes | 11 January 2026 | Optical links at 2.5 Gbps, upgradable to 10 Gbps+, on Kepler's relay constellation. Power described only as "kilowatts" | Axiom Space |
| Lonestar Data Holdings | "Freedom", an 8 TB SSD and one FPGA on Intuitive Machines IM-2 | 26 February 2025 | Lunar transit success; the lander tipped over on landing | DCD |
The first operational orbital AI computing constellation is Chinese, launched about six months before either Starcloud-1 or Google's paper. That is the most useful geopolitical fact in this section. Note also the honest scale: nanoGPT is a teaching-scale model, and Axiom's operating optical links run at 2.5 Gbps against Google's 1.6 Tbps bench demo.
| Operator | Filing | Date | Scale | Source |
|---|---|---|---|---|
| SpaceX | FCC ICFS SAT-LOA-20260108-00016, "SpaceX Orbital Data Center System" | filed 30 January 2026, accepted 4 February 2026 | up to 1,000,000 satellites, 500 to 2,000 km, 30 degree and sun-synchronous | FCC DA 26-113 |
| Blue Origin, Project Sunrise | FCC SAT-LOA-20260310-00118 | 19 March 2026 | up to 51,600 data centre satellites, plus a 5,408 satellite TeraWave relay constellation | SpaceNews |
| Starcloud | FCC filing | 2026 | up to 88,000 satellites | TechCrunch |
Those three filings total roughly 1.14 million satellites. There are about 11,000 operational payloads in orbit today and about 40,000 tracked objects (European Space Agency, Annual Space Environment Report, data to end 2024, published April 2025). A filing is an option bought cheaply; treat it as such.
A precision point that matters. Starlink V2 mini downlink is about 100 Gbps and V3 is expected at about 1 Tbps downlink; the inter-satellite laser links are about 100 Gbps. Google's own paper independently states Starlink's laser system operates at about 100 Gbps over up to about 5,400 km. Quoting "1 Tbps lasers" conflates the downlink with the laser link, and is the most common error in coverage of this topic.
Announced 4 November 2025, with a paper submitted to arXiv on 22 November 2025 (arXiv 2511.19468) and a partnership with Planet Labs to launch two prototype satellites by early 2027. The measured results are genuinely new science.
| Finding | Value | Status |
|---|---|---|
| Radiation environment in target dawn-dusk sun-synchronous orbit | about 150 rad(Si) per year behind 10 mm aluminium | analysis |
| Five-year mission total ionizing dose requirement | about 750 rad(Si) | requirement |
| First irregularities, in high bandwidth memory | 2 krad(Si), about 3x the requirement | demonstrated, ground beam test |
| Maximum dose tested with no hard failures | 15 krad(Si) | demonstrated, ground beam test |
| Silent data corruption rate from single event effects | about 1 event per 17 rad, about 1 failure per 3 million inferences | demonstrated |
| Free-space optical link, bench demonstrator | 800 Gbps one way, 1.6 Tbps bidirectional | demonstrated on a bench, not in orbit |
| Aggregate bandwidth required per link | on the order of 10 Tbps | design requirement |
| Formation flying | 81 satellites, 1 km radius, 650 km altitude, neighbours 100 to 200 m apart | simulation |
| Solar energy advantage over a mid-latitude panel | up to 8 times more per year | analysis |
| Launch cost breakeven | about US$200 per kg to LEO | analysis |
| Radiator area, mass or temperature | not published anywhere in the paper | absent |
Google's economic argument, and it is worth quoting precisely because it is so often over-read: at its own assumption of US$3,600 per kg for Falcon 9 the launched power price is about US$14,700 per kW-year; at US$200 per kg it falls to about US$810 per kW-year, against US terrestrial data centre power costs of about US$570 to US$3,000 per kW-year. Google concludes that at US$200 per kg "the cost of launch amortized over spacecraft lifetime could be roughly comparable to data center energy costs, on a per-kW basis". That sentence compares launch cost only against energy cost only. It excludes the satellite, the radiator, the chips and all ground infrastructure. Getting to US$200 per kg requires a sustained 20% learning rate and about 180 Starship launches a year, and Google notes this is "still far below stated launch targets for Starship".
| Question | The number | Verdict |
|---|---|---|
| Solar | Solar constant 1,361 W per square metre (NASA TSIS-1, measured). At 22 to 30% cell efficiency, about 300 to 400 W per square metre delivered. SpaceX's own AI1 claim is 250 W per square metre. In dawn-dusk sun-synchronous orbit the capacity factor approaches 1.0 against roughly 0.19 for a mid-latitude terrestrial panel. | Favours space. But only in one narrow orbital band that every player wants; generic LEO at 400 to 500 km gets only about 60% solar exposure. |
| Cooling | In vacuum the only way to shed heat is to radiate it: P = A x sigma x T to the fourth. NASA's operating ISS radiators reject 70 kW from 475 square metres weighing 6,736 kg, that is 147 W per square metre and 96 kg per kW. NASA's Photovoltaic Radiator does better at 330 W per square metre and 52.9 kg per kW. SpaceX claims 1,400 W per square metre. Google publishes nothing. | The decisive objection. A 1 MW orbital facility needs about 96 tonnes of ISS-class radiator alone. SpaceX's claim is roughly 10x the only large operating example, and unverified. |
| Launch cost | SpaceX's own published price is US$74 million for up to 22,000 kg to LEO, that is about US$3,364 per kg. Google assumes US$3,600 per kg for Falcon 9 reusable. Transporter rideshare lists at about US$7,000 per kg. Analysts estimate SpaceX's internal marginal cost near US$629 per kg. Starship targets range from about US$67 to US$250 per kg. | The gating variable. The spread between US$629 and US$7,000 per kg for the same rocket tells you how much depends on which number an advocate picks. |
| Mass per MW | A Starlink V2 mini is 575 kg for about 28 kW, that is 20.5 kg per kW, or 20.5 tonnes per MW, for a complete flight-proven spacecraft. At US$3,364 per kg that is about US$69 million per MW just to launch, US$69 billion for a gigawatt. At US$200 per kg it falls to about US$4.1 million per MW. | Launch cost must fall about 18 times before the arithmetic changes character. |
| Radiation | Google's measured results: no hard failures to 15 krad(Si), against a five-year requirement of 750 rad(Si). Silent data corruption at about 1 event per 17 rad. | The weakest objection. Commercial silicon survives better than expected. But Google explicitly says the impact on training "requires further study". |
| Latency | Light travel time at 550 km is 1.83 ms one way, 3.67 ms round trip; SpaceX claims about 3 ms for AI1. Real measured Starlink median peak-hour latency in the US is about 26 ms; multi-hop inter-satellite paths accumulate 30 to 80 ms one way. | Fine for inference, irrelevant for training, because training is bandwidth-bound, not latency-bound to the ground. |
| Networking | Van Berkel (TU Eindhoven, July 2026) for an 8,000 node system: bisection bandwidth 28,800 TB/s for a terrestrial Clos fabric against 2.25 TB/s for a 2D orbital torus and 10 TB/s for a 3D torus. Network latency 4 microseconds against 1,800 and 600. | The objection that does not go away. About 1,000 times lower bisection bandwidth, raising training cost "100+ times". This is geometric, not economic, so cheaper launch does not fix it. |
| Servicing | Google's own words: "Currently, failed TPUs are manually replaced by technicians, which is relatively simple and low-cost on Earth, but obviously impracticable in space. The simplest solution is redundant provisioning." Meta measured a hardware failure roughly every three hours on a 16,000 GPU cluster. | Structural cost penalty. Every failed accelerator is a permanent loss, paid for with spare capacity launched in advance. |
| Debris and sky | Over 1.2 million objects larger than 1 cm already in LEO; over 1,400 recorded impacts on the ISS. Marcy (March 2026) calculates that a 4 km by 4 km array at 500 km would span about 0.4 degrees, comparable to the Moon, at magnitude about -5.5 to -7, roughly 100 times brighter than the brightest stars. | The social licence problem, in orbit. Exactly the same argument Canadian communities are having about buildings, moved 500 km up. |
| Carbon | The European Commission's ASCEND study (Thales Alenia Space with Airbus, HPE, ArianeGroup and DLR, published June 2024) concluded that orbital data centres would only meaningfully cut digital carbon emissions with "a launcher ten times less emissive over its entire lifecycle". | No such launcher has been proposed. This is the least quoted and most disciplined finding in the literature. |
The honest synthesis is more interesting than either the hype or the dismissal: inference may well move to orbit; frontier training almost certainly will not this decade. Van Berkel puts it directly: cost-effective frontier training in space "within the next 2-3 years is not credible and even a 10-year horizon appears optimistic with current technology trends".
One more signal is worth more than any forecast. In August 2026 SpaceX, the company proposing a million compute satellites, was building a natural gas power plant in Texas, hiring a natural gas trading team, and starting in-house turbine blade manufacturing to cut generator delivery delays by 18 months, all for terrestrial AI data centres. Watch what the capital does, not what the founder says.
| Option | The number | Canadian status | Source |
|---|---|---|---|
| Small modular reactors | Four BWRX-300 units at Darlington, 1,200 MW, budgeted at C$20.9 billion, with C$7.7 billion for the first 300 MW unit in service in 2030, at a projected 14.9 cents per kWh | Under construction; the most advanced grid-scale SMR programme in the G7 | World Nuclear News, May 2025 (see brief 02) |
| Natural gas with carbon capture | Alberta's Malachite One proposes 930 MW of on-site gas with carbon capture under consideration, plus a 74.9 MW grid request, for a 1,000 MW data centre | Proposed, August 2026. Alberta's AESO capped interim grid connections at 1,200 MW against roughly 20 GW of applications, so almost every Alberta project is bring-your-own-gas | See brief 03 |
| Geothermal | O'Leary Ventures' Wonder Valley (7,500 MW proposed, 1,400 MW phase 1) lists possible geothermal alongside off-grid gas | Proposed only; no Canadian geothermal is powering a data centre today | See brief 03 |
| Hydro repowering and new build | Hydro-Quebec's Action Plan 2035 targets 3,800 to 4,200 MW of new hydro plus 10,000 MW of wind, inside a C$155 to 185 billion programme | Committed but slow; Quebec now screens every load above 5 MW | See brief 02 |
| Curtailable and grid-interactive load | Manitoba's Bill 20 already gives the Crown utility curtailment powers for crypto load; the same instrument could apply to AI | The most under-used Canadian lever: a data centre that accepts curtailment can be connected years earlier | See brief 04 |
| Waste heat reuse | QScale's 96 MW at Levis could heat 15,000 households and avoid 146,576 tonnes of CO2 a year; Stockholm supplies about 3.5% of city heat from data centres; Bell's Thompson Rivers University site feeds a campus district energy system | Real but early: the Levis greenhouses were still ramping in 2026, and TELUS's "150,000 homes" claim for Vancouver is unverified | See brief 05 |
The pattern is that Canada's real frontier options are boring, slow and already on the books. None of them arrive faster than a gas turbine, and all of them arrive faster than a gigawatt in orbit.
Three hardware facts bear directly on where Canadian data centres get built.
Liquid cooling changes what the climate is worth, and mostly reduces it. The old Canadian pitch was free cooling: cold outside air means the chillers run less, so PUE falls and the power bill falls with it. That advantage is real and quantifiable. Cooling is 7% of load in an efficient hyperscale facility and over 30% in an inefficient one (IEA, April 2025), and the climate is worth roughly 0.2 to 0.3 on PUE. On a fixed 80 MW IT load, moving from PUE 1.45 to 1.20 removes 20 MW of facility draw, which at a 90% load factor is 158 GWh a year, worth about C$8.7 million at 5.5 cents per kWh and about C$20.5 million at 13 cents. But the AI racks arriving now are liquid cooled by vendor mandate: NVIDIA ships GB200 and GB300 NVL72 only as liquid-cooled racks, and AMD's MI355X is liquid only. Direct-to-chip cooling captures most of the heat in a closed loop and is far less sensitive to outside air temperature than an air-cooled hall. So the marginal value of Canadian cold falls just as the absolute value of Canadian electricity price and carbon intensity rises. The Canadian argument has to shift from "our air is cold" to "our electricity is cheap, clean and, where there is capacity, available", plus the one cold-climate bonus that liquid cooling creates rather than destroys: usable waste heat. Bell's Thompson Rivers University site feeds its heat into a campus district energy system, and TELUS claims its BC cluster will produce waste heat equivalent to heating 150,000 homes, a claim this research set has not verified. Warm water out of a cold-plate loop is worth something in Kamloops in February and nothing in Phoenix in July.
The chip supply chain is a tariff exposure, not just a procurement problem. No AI accelerator is made in Canada. The United States applies a 25% Section 232 tariff to a subset of semiconductors and derivative products, with exemptions for goods used in US domestic production including US data centres, and there is no CUSMA-compliant exemption (Government of Canada, Trade Commissioner Service, updated 27 August 2026). That asymmetry runs against Canadian siting: the same rack can be cheaper on the American side of the border. Add NVIDIA's own figure of up to 200 kg of copper busbar per megawatt-class rack and up to 200,000 kg of copper per gigawatt facility, and the equipment supply chain, rather than the chip, becomes the part with Canadian content: transformers, switchgear, busbar, cooling distribution units and copper. Canada mines copper; it does not make GPUs.
Orbital compute is not a threat to a Canadian siting decision this decade. Google's own analysis says orbital compute becomes cost-comparable to terrestrial energy costs only if launch reaches about US$200 per kilogram to low Earth orbit, which its learning curve puts in the mid-2030s and only if roughly 180 Starship launches a year are sustained. The only accelerator-class hardware demonstrated in orbit is a single NVIDIA H100 on a 60 kg satellite, and the strongest quantified objection, a roughly 1,000-fold bisection bandwidth deficit for distributed training, does not improve with cheaper launch. Every larger constellation is a regulatory filing or a statement. The right way for a Canadian decision maker to treat space is as a terminal-value question, not a siting question: it belongs in the residual value assumption for a 15 or 20 year asset, not in the choice between Kamloops and Sturgeon County.
Canada's AI data-centre boom is really two stories that are easy to confuse. The first is an announcement wave, concentrated in Alberta, that adds up to more electricity than the province has ever consumed at once. The second is a much shorter list of projects that have secured land, power, a tenant and a construction contract. The distance between the two lists is where the business questions live.
Start with what is real. Meta's Sturgeon County campus is the anchor. Announced and broken ground on July 8, 2026, it is a 1 GW, AI-optimized facility with more than C$13 billion of private capital, about 3,000 construction jobs and 300-plus permanent roles. Its power plan shows how Alberta now works: a 970 MW grid position won under AESO's one-time Phase 1 process, a 250 MW supply contract with Capital Power from the second half of 2028, and a dedicated 932 MW combined-cycle gas plant, Greenlight, owned by Pembina, Morgan Stanley Infrastructure Partners and Kineticor, that took final investment decision on July 2, 2026 for service in the second half of 2030. Meta expects to be running two years before its own plant is finished, so the grid carries the campus in between. The second Alberta project with a grid contract is TransAlta's Keephills site, where CPP Investments and Brookfield signed a memorandum of understanding on February 27, 2026 for an initial 230 MW that could grow to 1 GW.
Outside Alberta, the projects under construction are smaller and mostly hydro-fed. Bell's 300 MW campus outside Regina (C$1.7 billion, tenants Cerebras and CoreWeave, first data halls in the first half of 2027) is the largest purpose-built AI site being built in Canada today and the only one where a Crown utility, SaskPower, agreed to supply the full load. Microsoft is spending C$7.5 billion over two years on its Quebec City and Toronto regions, QScale is adding 60 MW in Lévis for C$700 million under new owner Goldman Sachs, Vantage is finishing a 32 MW building in Quebec City, Keel (formerly Bitfarms) is consolidating 96 MW of bitcoin capacity in Sherbrooke into an AI campus, eStruxture's 90 MW CAL-3 near Calgary opens in fall 2026, and TELUS opened a sold-out Rimouski facility in September 2025 with 85 MW secured from BC Hydro for a Kamloops and Vancouver cluster that scales past 150 MW by 2032.
Now the announcement wave. AESO counted 29 projects and 16 GW of requests in June 2025, "over 20,000 MW" by September 2025, and the province reported 19,565 MW on July 30, 2026, against a record peak of about 12,800 MW. Alberta Data Centre Watch lists 30 active projects with a published maximum of 13.1 GW. The biggest names, Wonder Valley (7.5 GW, C$70 billion), Beacon's six campuses (roughly 2,000 MW), Malachite One (1 GW), Travers (up to 2,000 MW), Wild Rose (1.3 GW) and Newell (1.2 GW), are applications, not projects. Wonder Valley illustrates the gap: 20 months after its announcement it has a land deal, a water certificate held by the municipality, an exemption from provincial environmental assessment, no announced tenant, no gas-plant partner, and a construction start that has slipped from 2026 to about late 2028.
Alberta's response to the queue is the most important policy development in the country. AESO's interim limit of 1,200 MW through 2028 was allocated pro rata among 15 qualified projects holding 4,800 MW; after a trading window and withdrawals, two projects took everything. The province then passed Bill 8 and Bill 12 (December 11, 2025) and filed the Data Centre Regulation on June 9, 2026. The model is "bring your own power": a data centre that pairs its demand with new dedicated generation or storage goes to the front of the connection queue, may use up to three years of bridging grid supply inside an initial 1,600 MW pool, and pays a levy of 1 to 2 per cent of the value of its computing equipment, lower if it draws less from the grid. Developers, not existing customers, pay for transmission upgrades. In practice this means every large Alberta project is also a gas-plant project, which pulls in a second set of constraints: turbine delivery slots that now stretch beyond five years, capital costs that have doubled in two years, Alberta Utilities Commission siting approval, water licences that rank behind existing users, and carbon exposure.
The other provinces are rationing. British Columbia replaced first-come, first-served with a competitive call, capped at 400 MW per two years and 145 MW per project, and permanently banned crypto connections. Quebec requires ministerial authorization for any load of 5 MW or more, evaluates projects comparatively, and is doubling the data-centre rate to about 13 cents per kWh from November 1, 2026. Ontario now requires approval under section 28.1 of the Electricity Act, and its draft Playbook makes data centres pay full grid costs, screens them for jobs, sovereignty and community benefit, and creates a higher Class C rate. Saskatchewan will only consider Canadian-owned projects that supply their own power. Manitoba passed a law letting Manitoba Hydro refuse large loads and its premier walked away from a gas-fired hyperscale proposal. Nova Scotia has no active file. New Brunswick is consulting on a framework while a 390 MW gas-and-grid project at Lorneville sits in environmental assessment. Ottawa's 100 MW-plus sovereign data-centre call closed February 15, 2026 and had named no proponents by September 2, 2026, although TELUS says it is advancing work under it.
Which roadblock binds where? In Alberta it is no longer policy but execution: siting and social licence (Rocky View, Olds, Sturgeon County), generation lead times, water, and above all the absence of tenants and financing for speculative land. In British Columbia and Quebec the binding constraint is administrative allocation of scarce hydro, and the price of it. In Ontario it is process time and cost. In Saskatchewan and Manitoba it is Crown-utility capacity and politics. In New Brunswick it is emissions and environmental assessment. Nationally, the financing market has turned selective: lenders want investment-grade tenants, and the tenants (Meta, Microsoft, CoreWeave, Cerebras, Cohere) are few.
For students, the useful frame is a funnel. Roughly 20 GW is requested in Alberta; 4.8 GW qualified; 1.2 GW is contracted; about 1.3 GW (Meta plus Keephills Phase I) is credibly funded; and, across all of Canada, less than 1 GW of new AI-grade capacity is actually under construction in 2026. Watch the events that move projects down the funnel: BC Hydro's call results (fall 2026), Ontario's final Playbook (fall 2026), the Régie's decision on Quebec's tariff, AESO's first Phase 2 bring-your-own-generation intake, federal MOUs, a gas-plant partner for Wonder Valley, the Rocky View moratorium, Synapse's appeal, and first power at Meta's campus in 2028.
Ordered by announced size. "n/d" means not disclosed in sources reviewed. Status is as of the latest source (date in brackets). Rows marked "tracker" rely on the independent Alberta Data Centre Watch tracker and have not been confirmed against filings.
| Province | Binding constraint | Evidence | Source |
|---|---|---|---|
| Alberta | Grid connection capacity and queue (high) | 19,565 MW requested vs 1,200 MW allocated (July 30, 2026); peak ~12,800 MW; Phase 1 closed with two projects; Phase 2 BYOG intakes roughly every nine months; 1,600 MW bridging pool | [4], [1], [5] |
| Alberta | Generation lead times and cost (high) | Large gas turbine backlogs over five years; gas capex doubled in two years; Greenlight (932 MW) costs ~C$4 billion, 2.6x a similar plant two years earlier, and arrives in H2 2030, after Meta needs power | [22], [21], [8] |
| Alberta | Municipal zoning and social licence (high) | Rocky View refusal 6-1 (Sept 2025) and moratorium 5-2 (July 2026); hundreds rallied in Morinville against Meta; 4 in 5 Albertans concerned about costs and environment | [17], [18], [20] |
| Alberta | Regulatory siting of on-site generation (high) | AUC denied Synapse's 1.4 GW plant at Olds (Aug 17, 2026) as too close to the community; ~1,500 parties applied to participate | [19] |
| Alberta | Water licensing (medium) | Water Act licences rank junior to existing holders; southern basins closed to new surface-water licences since 2006; Wonder Valley's 24 million cubic metres per year certificate held via the municipality; five projects publish 13.8 million litres per day | [4], [13], [15] |
| Alberta | Tenant and financing uncertainty (high) | Wonder Valley has no tenant and a late-2028 start; most tracker projects are applications; lenders shut to non-investment-grade tenants; land speculation reported | [12], [15], [40] |
| Alberta | Levy and rule uncertainty (medium) | AESO extended Phase 1 contract deadline (Aug to Oct 2025) for the levy; levy of 1 to 2 per cent on equipment from Dec 31, 2026; regulation only filed June 9, 2026 | [2], [5], [6] |
| Alberta | Power price impacts (medium) | AESO acknowledges prices rise when load arrives before generation; Pembina Institute expects higher and more volatile rates | [20], [21] |
| British Columbia | Capped, competitive allocation (high) | 400 MW per two years (300 MW AI, 100 MW conventional), 145 MW per project cap, bid security C$25,000 per MW; call closed March 2026; decisions fall 2026; crypto connections banned permanently; resource industries exempt | [40], [41], [42] |
| British Columbia | Community opposition (medium) | ~750 marchers May 23, 2026 and a second march June 27; concerns on water during restrictions and consultation; petition reported at 15,000 signatures | [31] |
| Saskatchewan | Utility supply and ownership rules (high) | SaskPower could supply Bell's 300 MW but future projects must self-supply "behind the fence"; Canadian ownership required; 30-plus applications pending (Aug 27, 2026) | [27] |
| Manitoba | Utility capacity and political veto (high) | Manitoba Hydro says it cannot connect new energy-intensive users; legislation lets Hydro reject large loads; premier dropped the Ritchot hyperscale project (June 2026); 4,200-signature petition | [28], [29] |
| Ontario | Process length and full-cost rules (high) | Section 28.1 approval (in force Dec 11, 2025); system and connection impact assessments over 12 months for loads above 10 MW; OEB leave to construct 6 to 12-plus months; draft Playbook (Aug 13, 2026) requires full cost recovery, screening, and a Class C rate above 1 MW; final rules due fall 2026 | [36] |
| Ontario | Local approvals (medium) | Steelport hyperscale campus in Hamilton refused by the Committee of Adjustment after opposition on power, water, noise and waterfront use | [29] |
| Quebec | Ministerial authorization and tariff (high) | Loads of 5 MW or more need MEIE authorization with comparative evaluation (Bill 69, June 2025); proposed data-centre rate ~13 cents per kWh (about double) from Nov 1, 2026, subject to Régie hearings in fall 2026; sector expected to grow from ~190 MW to ~1,000 MW by 2035 | [33] |
| New Brunswick | Environmental assessment and emissions (high) | Lorneville gas plant would emit ~750,000 tonnes CO2 a year (~6.6% of provincial emissions), clear 27 ha of wetland and 3.5 ha of old-growth forest; EIA under way; moratorium motion blocked June 2026; provincial framework out for comment to Oct 2, 2026 | [38] |
| Nova Scotia | Electricity supply (high) | Premier: "not a today thing"; support only if power can be supplied safely; no active file | [38] |
| Newfoundland and Labrador | Transmission and framework gap (medium) | About 17 MW of crypto load in Labrador; no AI-specific framework; Labrador transmission limits | [29] |
| Federal | Sovereignty screening and selection lag (medium) | 100 MW-plus call closed Feb 15, 2026; MOU-based selection; no proponents named on the ISED page as of Sept 2, 2026; Cohere funding criticized because CoreWeave operates the site | [37] |
Canada's governments agree on the destination and disagree on the road. Every order of government now says AI data centres matter for sovereignty, but the federal government controls neither the electricity nor the land, so the real gatekeepers are provincial ministers, Crown utilities, system operators and municipal councils. That split explains why the same 18 months produced a federal call for gigawatt-scale "sovereign" data centres alongside caps, rate hikes, moratoria and rejections in most provinces.
Start with Ottawa. The Canadian Sovereign AI Compute Strategy, announced in Budget 2024 and launched in December 2024, is a $2 billion package: a public supercomputer through SCIP, a commercial stream originally called the AI Compute Challenge, and an access fund for small firms. The Carney government, elected 28 April 2025, created a dedicated Minister of Artificial Intelligence and Digital Innovation (Evan Solomon, 13 May 2025) and folded AI into its "build Canada" and "energy superpower" framing: Bill C-5's Building Canada Act promises two-year federal decisions on national-interest projects, and the Major Projects Office (Calgary, August 2025) coordinates approvals and financing. Budget 2025 (4 November 2025) put $925.6 million over five years toward a sovereign public AI infrastructure, largely re-labelling Budget 2024 money, enabled the CIB to invest in AI infrastructure, raised the CIB's envelope to $45 billion, doubled Indigenous loan guarantees to $10 billion, and extended accelerated write-offs through the Productivity Super-Deduction (up to $9 billion a year of output, per the April 2026 Spring Economic Update). It also confirmed the Clean Electricity investment tax credit without conditions on provinces, which matters for Crown utilities building supply for large loads.
The distinctive federal move on data centres came in January 2026: a call for Canadian firms and consortia to propose sovereign AI data centres above 100 MW, judged on seven factors (economic benefit, Indigenous participation, sovereignty, energy, performance, readiness, cost and ownership). The reward is an MOU that "explores mechanisms", and intake forms are shared with the CIB, Export Development Canada, Invest in Canada, the Major Projects Office and provinces. ISED was explicit that the $2 billion envelope would not fund these projects. The one visible result, TELUS's Kamloops and Vancouver cluster (May 2026), is a modest 85 to 150 MW. The June 2026 "AI for All" strategy elevates sovereign compute to a pillar, promises a "world-leading public AI supercomputer", positions the government as an anchor customer and expands the Global Talent Stream, but the primary release contains no megawatt target; secondary summaries cite 850 MW by 2030 and 2.3 GW later. Meanwhile the digital sovereignty debate (the US CLOUD Act's reach over US-controlled providers, and CUSMA Article 19.12, which restricts data localisation mandates except for federal procurement and national security) gives Ottawa a rationale for wanting Canadian-owned, Canadian-governed capacity, and critics such as Open Canada argue that funding a facility operated by a US provider does not deliver it.
Alberta wrote the most ambitious script and then hit physics. Its December 2024 strategy leans on deregulated power, gas, cold weather and a concierge program, with Minister Glubish talking about $100 billion of projects. Requests flooded in: 29 projects for more than 16 GW by June 2025, roughly 19.6 GW by 2026 against an all-time peak of 12.8 GW. AESO's answer was a 1,200 MW interim allocation through 2028, fully taken by two projects (Meta's 970 MW and Keephills 230 MW), and then a permanent "tethering" rule: the Data Centre Regulation (June 2026) prioritises projects paired with new dedicated generation or storage, allows a bridging period of up to three years, requires data centres to be curtailed first in emergencies, and the BYOG process opens 1,600 MW of bridging capacity in intakes roughly every nine months against a $15,000 per MW commitment. Alberta's four public commitments (no subsidies, grid first, water protected under the Water Act with new licences junior to existing ones, and a levy of up to 2 per cent on computing equipment) are meant to answer the affordability backlash seen in US states. Meta's $13 billion Sturgeon County campus, powered by a 932 MW gas plant built by Pembina, Morgan Stanley Infrastructure Partners and Kineticor, is the template; the province claims Meta's transmission fees could cut the transmission share of household bills by up to 6 per cent. The cost is carbon (about 150 million cubic feet of gas per day) and local friction: Rocky View County approved Beacon's 900-acre hub in 2025, rejected two other projects, and imposed a moratorium in July 2026.
Ontario is the clearest case of a province taking discretion away from its regulators. Bill 40 (December 2025) added an economic-growth mandate to the Independent Electricity System Operator (IESO) and the Ontario Energy Board (OEB) and created section 28.1 of the Electricity Act, under which large loads cannot connect without meeting prescribed requirements approved by the Minister. The August 2026 Data Centre Playbook fills that in: a System Impact Assessment (feasibility and full cost recovery, including on-site generation) and a Strategic Priority Assessment on three pillars (economic development, data security and digital sovereignty, community investment and environment). Ontario will "compete on value, not incentives", offering only non-financial help such as permitting facilitation, and proposes a separate rate class that keeps new data centres out of the Industrial Conservation Initiative. The scale of the queue, potentially more than 10,000 MW against a 25,000 MW peak, is why. Municipalities are moving faster than the province: Mississauga and Oakville paused approvals in July and August 2026.
Quebec's turn is the most striking because it once marketed cheap hydro to the industry. Since 2023 any project above 5 MW needs the Minister of Economy, Innovation and Energy's approval; Bill 69 (June 2025) made allocation comparative, judged on benefits per megawatt, and required an integrated resource plan (the PGIRE 2026-2050, launched June 2026). Hydro-Québec's Action Plan 2035 calls for 8,000 to 9,000 MW of new capacity and $155 to 185 billion of investment, so every megawatt to a data centre competes with electrification. The proposed Rate CD (about 13 cents per kWh, roughly double the large-power rate) and a 19.5-cent crypto rate go to Régie hearings in October 2026, and operators are already litigating the ramp-up underperformance charge. Yet Microsoft, Google, Vantage, QScale and OVHcloud keep building around Quebec City, Lévis and Beauharnois: the province is pricing, not closing the door.
British Columbia sits between Alberta and Quebec. Faced with limited firm supply, it legislated an exit from first-come, first-served (Bill 31) and capped new data centre load at 400 MW for two years, allocated by a competitive Call for Demand that scores price, cost-effectiveness to BC Hydro, economic and community benefit, data sovereignty, First Nations benefit and environmental performance. Fifteen applications for about 800 MW compete for that tranche, with results due by the end of September 2026. In parallel, Bill 14 streamlines permitting for nine wind projects and the North Coast Transmission Line, and the 2025 Call for Power added more than 3,000 MW of wind and solar, so the constraint is timing rather than intent. Premier Eby's government pairs this with a "Look West" pitch for sovereign AI, visible in the TELUS cluster and Bell's six planned BC AI facilities.
The smaller provinces show the same pattern in miniature. Saskatchewan let SaskPower build 300 MW for Bell (partly by extending coal, which the opposition disputes) and then closed that door: from August 2026 new projects must be Canadian-owned and self-powered. Manitoba requires ministerial priority designation above 5 MW, levies data centres, and rejected a 100 MW hyperscale project on farmland. New Brunswick refused a moratorium but promised limits on a 390 MW gas-backed proposal at Saint John. Nova Scotia is not pursuing projects; Newfoundland and Labrador is absorbed by Churchill Falls; Yukon has nothing to offer a large load.
Two cross-cutting threads matter for students. First, Indigenous participation has become a formal screening criterion federally, in BC and in Alberta's strategy, backed by the $10 billion federal loan guarantee program, and the leading projects (Bell with George Gordon First Nation, Woodland Cree's majority-owned 650 MW plan, Prophet River's letter of intent) show equity or land partnerships as a path to social licence. Second, the binding constraint everywhere is firm electricity and who pays for it, which is why the policy vocabulary has converged on "full cost", "bring your own power", "curtailable" and "community benefit". Governments want the data centres; they no longer want to pay for the power.
The economics of an AI data centre are unusual. A hyperscale campus is a capital project of oil-sands scale that behaves, once built, like a very large and very quiet electricity customer. Meta's Sturgeon County project illustrates the shape: $13 billion of investment, 1,750 acres, a 932 MW gas plant next door, more than 3,000 construction workers at peak, and then about 300 permanent staff, with 30 more at the power plant. Virginia's independent legislative audit found the same pattern at a mature scale: the industry supports 74,000 jobs and USD 9.1 billion of GDP a year, but most of it comes from construction, and a typical building runs with about 50 people, half of them contractors. Brookings' county-level work confirms that a first large data centre lifts local data-processing employment by 56 per cent over a decade but produces only 100 to 200 jobs and no measurable wage gain. Industry-commissioned multipliers (PwC's 4.5 indirect jobs per direct job) are much larger because they count the whole supply chain nationally, which is a different question from what a host community gets. The "few permanent jobs" critique is therefore accurate, and 57 per cent of Canadians already believe it. The honest case for a data centre is not jobs per megawatt; it is capital, tax base, and strategic compute.
The tax base is real but shaped by policy. Alberta expects about $250 million a year from the Meta project across royalties on roughly 150 million cubic feet of gas a day, a levy, property taxes and transmission fees, and Sturgeon County expects around $40 million a year, which would make Meta one of its largest taxpayers. Two design choices limit the municipal share: computing equipment, the bulk of the capital cost, is exempt from municipal assessment, and the province's new 2 per cent levy on that equipment is fully offset against corporate income tax, so it raises nothing from a profitable operator. Quebec has gone the other way, proposing a 13 cents per kWh rate that roughly doubles what data centres pay, on the logic that the province's surplus of near-zero-carbon power (1.7 grams of CO2 per kWh) is scarce and valuable. Hydro-Québec's own results show why: nine-month 2025 net income of $2.8 billion leaned heavily on $1.4 billion of external-market sales, and a captive industrial customer paying double the large-power rate is more attractive than volatile exports.
Electricity rates are where the argument is decided. The US evidence is now hard to dismiss. PJM's independent monitor attributes 40 per cent of the USD 16.4-billion December 2025 capacity auction to data centres, and 46 per cent of USD 63.6 billion across four auctions, with capacity prices up from USD 28.92 to USD 333.44 per MW-day in three years. Virginia's audit projects USD 14 to 37 a month more for Dominion households by 2040, and Henrico County has started asking teachers to switch off lights after a 25 per cent power-cost increase. The policy response has been rate classes and collateral: Dominion's new class requires 14-year contracts and USD 1.5 million per MW; Georgia certified 9,985 MW of new plants but made Georgia Power backstop the cost through 2031 if the data centres do not show up. Alberta's framework has the same instinct (a "cost causation" rule, mandatory own generation, transmission fees that the province says will cut the transmission line item by up to 6 per cent), but a gap in timing. Meta will draw up to 970 MW from the grid for two to three years before Greenlight runs, and the Pembina Institute, using the producers' own forecasts of pool prices near $100 per MWh, estimates $267 to $462 a year of extra cost per household in 2027 to 2031, dwarfing the transmission saving of under $20. The provincial government calls this fearmongering; the AESO acknowledges pool prices will rise while transmission costs fall. Students should treat the direction as contested and the mechanism as settled: bridging load on a tight grid raises prices until new supply arrives.
Environmentally, the province is the decision. Alberta's grid delivered 540 grams of CO2 per kWh in 2023 to 2024 and Saskatchewan's 730, while Quebec, Manitoba, British Columbia and Ontario sit between 1.7 and 30. A 1 GW campus at 90 per cent utilization uses about 7.9 TWh a year, which on dedicated combined-cycle gas is roughly 3 Mt of CO2, the figure Pembina attaches to Meta and about a tenth of Alberta's entire electricity sector. Blake Shaffer's estimate that 6.5 GW of gas-fed data centres would double Alberta's electricity emissions, and RBC's 16 Mt for 6 GW, point the same way. On Quebec hydro the same load would emit about 10,000 tonnes. Two policy moves lock in the high-carbon path: the November 2025 Canada-Alberta MOU suspended the Clean Electricity Regulations, and the AESO's draft bring-your-own-generation rule treats only thermal plants as acceptable, which makes hybrid wind, solar and battery supply uneconomic even though TD Economics finds turbine backlogs of over five years and battery costs down 27 per cent in a year. Meta's promise to "match" its use with renewable certificates does not change the physical electrons.
Water is the most emotional issue and the most fixable. Modern closed-loop dry cooling can eliminate operational cooling water, as Meta claims for Sturgeon and Lancaster's agreement enforces, and hyperscaler water usage effectiveness has fallen to 0.19 to 0.27 litres per kWh. The IEA's caution is that more than 60 per cent of a hyperscale site's water footprint is indirect, in thermal power generation and chip manufacturing; a gas-powered campus in Alberta moves water use from the server hall to the power plant. Land, noise and diesel backup are what neighbours actually experience, and the Olds decision, where the regulator rejected a 1.4 GW gas plant with 1.8 GW of diesel backup as too close to homes after about 1,500 people registered as intervenors, shows that siting can fail even in a pro-development province.
Social licence follows from all of the above. Polling is consistent across Abacus, Nanos, Leger and Angus Reid: Canadians are split on data centres nationally, opposed to subsidies (64 per cent), opposed to a site near home (68 per cent), and near-unanimous (81 to 82 per cent) that operators should pay their full costs and face strict regulation. Municipal politics has caught up: Rocky View County's 6 to 1 rejection and later moratorium, Oakville and Mississauga's one-year freezes, Hamilton's near-miss, Manitoba's cancelled rural project and three Vancouver marches all happened within twelve months. The complaints are less about AI than about process: NDAs signed by a Hamilton city-owned corporation and by the Town of Olds, two-week comment periods, and land-use notices that described a 26 MW AI facility as "bulk data storage". The models that seem to earn consent share three features: the developer pays full grid costs, benefits are written into enforceable agreements (Lancaster's USD 20.25 million and water cap; Meta's $60 million for local roads and water), and ownership is shared, as in Woodland Cree First Nation's majority-owned project or British Columbia's call that scores First Nations and community benefits. Ireland, where data centres now take 23 per cent of metered electricity and new connections must bring 80 per cent new renewables, and the Netherlands, which lost Meta's Zeewolde campus and then confined hyperscale sites to two locations, show what happens when governments regulate after the backlash rather than before it.
Finally, demand uncertainty cuts both ways. Alberta's 20.7 GW of requests exceed its entire peak load; PJM's monitor says USD 6.2 billion of one auction paid for data centres that do not yet exist; USD 64 billion of US projects were blocked or delayed by local opposition in a year; and Wonder Valley, once promised for 2027, now hopes to start construction in late 2028 with no tenant. A province that builds gas plants, pipelines and transmission for speculative load can strand them if AI demand disappoints, and a province that refuses to plan can lose the investment to Texas or Quebec. The management question for this session is which contracts, tariffs and ownership structures let Canada capture the capital and the compute without exporting the costs to households, farmland and the climate.
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Meta Sturgeon County campus investment | 13 | CAD billion | 2026 | Alberta | Meta |
| Meta construction jobs at peak / permanent jobs | 3,000+ / ~300 | jobs | 2026 | Alberta | Alberta.ca |
| Greenlight gas plant: capacity, cost, jobs | 932 MW, $4.6B, ~1,000 construction, 30 permanent | mixed | 2026 | Alberta | Sturgeon County |
| Permanent jobs per 100 MW implied by Meta | ~30 | jobs per 100 MW | 2026 | Alberta | derived from Alberta.ca |
| Typical Virginia data centre staff (250,000 sq ft) / peak construction crew | ~50 (half contractors) / ~1,500 | workers | 2024 | Virginia | JLARC summary |
| Virginia industry: jobs, labour income, GDP | 74,000 / USD 5.5B / USD 9.1B | per year | 2024 | Virginia | JLARC |
| Jobs in a typical US county after its first large data centre | 100 to 200 | jobs | 2026 | US | Brookings |
| Operations staffing intensity (as reported) | 0.15 to 0.35 | FTE per MW | 2025 | US | Hamm Institute |
| US employment multiplier (industry study) | 4.5 | indirect jobs per direct job | 2024 | US | PwC for Data Center Coalition |
| Subsidy cost per job in 11 US megadeals (as reported) | 1.95 | USD million per job | 2016 | US | Good Jobs First |
| Provincial benefit from Meta project | ~250 | CAD million per year | 2026 | Alberta | Alberta.ca |
| Sturgeon County property tax from Meta | ~40 | CAD million per year | 2026 | Alberta | Alberta.ca |
| Alberta computing-equipment levy | 2 (offset against corporate tax) | per cent | 2025 | Alberta | RMA |
| Local data-centre revenue share in five mature Virginia localities | <1 to 31 | per cent of local revenue | 2024 | Virginia | JLARC summary |
| PJM December 2025 auction cost / data-centre share | USD 16.4B / 40 | billion / per cent | 2026 | PJM | Utility Dive |
| PJM capacity price, 2024/25 vs 2027/28 | 28.92 vs 333.44 | USD per MW-day | 2025 | PJM | Utility Dive |
| Dominion residential impact by 2040 | 14 to 37 | USD per month (real) | 2024 | Virginia | JLARC |
| Dominion GS-5 class: contract term / collateral | 14 years / USD 1.5M per MW | mixed | 2025 | Virginia | Virginia Mercury |
| Georgia new generation certified (80% for data centres) | 9,985 | MW | 2025 | Georgia | Georgia PSC |
| Henrico County power-cost increase | 25 | per cent | 2026 | Virginia | Newsweek |
| Alberta household bill impact of Meta, 2027 to 2031 | 267 to 462 | CAD per year | 2026 | Alberta | Pembina |
| Claimed transmission-charge reduction from Meta fees | up to 6 (under $20 a year) | per cent | 2026 | Alberta | Alberta.ca |
| Hydro-Québec proposed data-centre rate vs current | 13 vs ~6.5 | cents per kWh | 2026 | Quebec | Hydro-Québec |
| Hydro-Québec nine-month net income / external-market sales | 2,830 / 1,426 | CAD million | 2025 | Quebec | Hydro-Québec Q3 bulletin |
| BC Hydro export revenue, first nine months (as reported) | 2.05 | CAD billion | 2025 | BC | Business in Vancouver |
| Gas use by Meta campus | ~150 | million cubic feet per day | 2026 | Alberta | Alberta.ca |
| Alberta grid requests vs peak load | 20.7 vs ~12 | GW | 2025 | Alberta | DeSmog |
| BC capacity offered vs requested, 2026 to 2028 | 400 vs ~800 | MW | 2026 | BC | BLG |
| Potential Canadian capex if proposals proceed | 100 | CAD billion | 2024 | Canada | RBC |
| Canada active vs planned capacity (York University) | 1.6 (194 sites) vs 22.2 (213 projects) | GW | 2026 | Canada | Canadian Press |
| US projects blocked or delayed by opposition | 64 | USD billion | 2025 | US | Data Center Watch |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Grid consumption intensity: AB / SK / ON / QC / MB / BC / NS / NB | 540 / 730 / 30 / 1.7 / 2.0 / 15 / 690 / 300 | g CO2e per kWh | 2023 to 2024 | provinces | ECCC |
| Projected intensity 2026: AB / ON / BC | 438 / 59 / 18 | g CO2e per kWh | 2026 | provinces | ECCC |
| Generation intensity: AB / SK / ON / QC / MB / BC / Canada | 470 / 630 / 35 / 1.2 / 1.3 / 14 / 100 | g CO2e per kWh | 2022 | provinces | CER profiles |
| Alberta electricity-sector emissions | 19.4 | Mt CO2e | 2022 | Alberta | CER Alberta |
| Electricity use of a 1 GW campus at 90% load | 7.9 | TWh per year | calc | any | this brief |
| Emissions of Meta campus on gas (Pembina) | ~3 (about 10% of AB electricity emissions) | Mt CO2 per year | 2026 | Alberta | Energy Mix |
| Load that would double Alberta electricity emissions | 6,455 | MW on gas | 2024 | Alberta | CBC (Shaffer) |
| 6 GW of gas-powered data centres | +16 (3% of national) | Mt CO2e per year | 2024 | Canada | RBC |
| Wonder Valley (up to 9 GW) emissions | 26 to 30 | Mt CO2 per year | 2026 | Alberta | Energy Mix |
| US hyperscale fleet carbon intensity vs grid | 545 vs 370 | g CO2 per kWh | 2025 | US | arXiv (Harvard) |
| Water use, 100 MW US hyperscale site (60%+ indirect) | ~2 | million litres per day | 2025 | US | IEA |
| US direct / indirect data-centre water | 66 / ~800 | billion litres | 2023 | US | LBNL |
| Global data-centre water consumption, 2023 to 2030 | 560 to 1,200 | billion litres per year | 2025 | Global | IEA |
| Water usage effectiveness: industry avg / AWS / Meta / Microsoft | 1.80 / 0.19 / 0.20 / 0.27 | litres per kWh | 2024 to 2025 | Global | Dgtl Infra, Microsoft |
| Google water consumed / emissions | 31 billion litres / 11.5 Mt (+51% vs 2019) | mixed | 2024 | Global | |
| Microsoft emissions change | +25 | per cent year over year | FY2025 | Global | Microsoft |
| Conventional large data centre water use (Conference Board) | ~19 | million litres per day | 2025 | Canada | VOCM |
| Wonder Valley preliminary water licence | 24 | million m3 per year | 2026 | Alberta | ELC |
| Land: Meta / Rocky View proposal / Zeewolde / Project Blue | 1,750 acres / 448 ha / 166 ha / 290 acres | area | 2022 to 2026 | various | Meta, CBC |
| Noise: diesel generators / cooling towers at 400 ft | 105 / 70 | dB / dBA | 2026 | US | EESI |
| Diesel backup proposed at Olds | 1.8 | GW | 2026 | Alberta | Epoch Times |
| Generative-AI e-waste, cumulative 2020 to 2030 | 1.2 to 5.0 | million tonnes | 2024 | Global | Nature Computational Science |
| QScale recoverable heat / households / CO2e saved | 96 MW / 15,000+ / 146,576 t per year | mixed | 2023 | Quebec | SustainableBiz |
| Stockholm heat from data centres (target) | 3.5 (10) | per cent of city heat | 2026 | Sweden | Eurelectric |
| US AI data-centre CO2 by 2030 (mitigation potential) | 24 to 44 (73%) | Mt per year | 2025 | US | Cornell / Nature Sustainability |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Support for a data centre in own community / oppose / depends | 16 / 34 / 39 | per cent | 2026 | Canada | Abacus |
| Say tech companies should pay full cost / want strict regulation | 81 / 82 | per cent | 2026 | Canada | Abacus |
| Say data centres do not create enough long-term jobs | 57 | per cent | 2026 | Canada | Benefits and Pensions Monitor (Abacus) |
| Oppose government incentives (Prairies fully opposed) | 64 (49.9) | per cent | 2026 | Canada | Globe and Mail / Nanos |
| Worried about bills / environment; support vs oppose in own province | 81 / 79; 44 vs 42 | per cent | 2026 | Canada | Canadian Press / Leger |
| Oppose a large data centre within a few blocks | 68 | per cent | 2026 | Canada | CBC citing Angus Reid |
| US: oppose new data centre in neighbourhood (Gallup) / local development (Heatmap) | 70 / 75 | per cent | 2026 | US | Wikipedia summary, Energy Mix |
| Rocky View County vote / speakers against vs for | 6 to 1 / 50+ vs 4 | count | 2025 | Alberta | CBC |
| Rocky View moratorium vote | 5 to 2 | count | 2026 | Alberta | Medicine Hat News |
| Sturgeon County protest turnout | 200+ | people | 2026 | Alberta | Postmedia via Yahoo |
| Olds hearing intervenors (granted standing) | ~1,500 (900+) | parties | 2026 | Alberta | Epoch Times |
| Vancouver rallies (May / June) and petition | 500 to 700 / hundreds to 1,200; 15,000 to 17,000 signatures | people | 2026 | BC | CBC, Daily Hive |
| Hamilton moratorium vote | defeated 10 to 6 | count | 2026 | Ontario | CHCH |
| Oakville / Mississauga moratoria | 1 year each | duration | 2026 | Ontario | CBC, City of Mississauga |
| Manitoba petition against rural AI data centre | 13,500+ | signatures | 2026 | Manitoba | CBC |
| National day of action | 14 | cities | 2026 | Canada | National Observer |
| Ireland: data-centre share of metered electricity; estimated extra household cost 2015 to 2023 | 23; ~EUR 360 | per cent; EUR | 2025 | Ireland | RTE / CSO |
| Zeewolde cancelled campus: power / land / jobs promised | 200 MW / 166 ha / 400 | mixed | 2022 | Netherlands | Silicon Republic |
| Lancaster CBA value / water cap | USD 20.25M / 20,000 gallons per day | mixed | 2025 | Pennsylvania | Columbia Climate Law |
| US community benefit agreements found / publicly posted | 8 / 1 | count | 2026 | US | FAS |
| Woodland Cree Mihta Askiy project (majority First Nation owned) | 650 | MW on-site gas | 2025 | Alberta | CBC |
| Benefit (evidence; confidence) | Cost (evidence; confidence) |
|---|---|
| Large private capital: $17.6 billion for the Meta campus plus Greenlight plant; RBC sees $100 billion nationally if proposals proceed (Alberta.ca 2026; RBC 2024). Confidence: high for announced projects, low for the $100 billion. | Few permanent jobs: ~300 per GW at Meta, 30 at a 932 MW plant, ~50 per Virginia building; 57 per cent of Canadians already think the jobs do not justify the resources (Alberta.ca 2026; JLARC 2024; Abacus 2026). Confidence: high. |
| Construction employment and supply chain: 3,000+ trades at peak in Sturgeon County; most Virginia construction spending stays in-state; TC Energy's Edmonton-area pipeline capacity sold out (Meta 2026; JLARC 2024; Global News 2026). Confidence: high. | Turbine and transformer bottlenecks inflate costs: gas plant capex doubled in two years, turbine backlogs over five years (TD Economics 2026; IEA 2026). Confidence: high. |
| Public revenue: ~$250 million a year to Alberta, ~$40 million a year to Sturgeon County; Virginia localities collect up to 31 per cent of local revenue from data centres (Alberta.ca 2026; JLARC 2024). Confidence: medium. | Revenue leakage by design: computing equipment exempt from municipal tax; 2 per cent levy fully offset against corporate income tax; US megadeals cost ~USD 1.95 million per job (Alberta Municipalities 2026; RMA 2025; Good Jobs First, as reported). Confidence: medium. |
| Premium utility revenue for surplus clean power: Hydro-Québec's 13 cents per kWh rate on ~190 MW today and ~1,000 MW by 2035; Hydro-Québec earned $1,426 million on external markets in nine months of 2025 (Hydro-Québec 2026, 2025). Confidence: high. | Higher wholesale prices during grid-bridging: $267 to $462 per Alberta household per year in 2027 to 2031; producers forecast pool prices up to $100/MWh (Pembina 2026). Confidence: medium; the province disputes it. |
| Spreading fixed grid costs: Meta's ~$200 million a year in transmission fees could cut the transmission line item up to 6 per cent; Georgia Power claims ~USD 102 a year for a typical customer (Alberta.ca 2026; WABE, as reported). Confidence: medium. | Cost shifting where rules lag: data centres were 40 per cent of PJM's USD 16.4-billion auction; Dominion customers face USD 14 to 37 more per month by 2040; Henrico County's power costs rose 25 per cent (Utility Dive 2026; JLARC 2024; Newsweek 2026). Confidence: high. |
| Heat reuse: QScale's 96 MW could heat 15,000 households and avoid 146,576 tonnes a year; Stockholm supplies 3.5 per cent of city heat from data centres (SustainableBiz 2023; Eurelectric 2026). Confidence: medium; Lévis greenhouses still ramping. | Emissions on gas: about 3 Mt CO2 a year per GW; 6.5 GW would double Alberta's electricity emissions; US hyperscale fleet runs at 545 g/kWh (Pembina 2026; Shaffer 2024; arXiv 2026). Confidence: medium to high. |
| Water-light designs exist: Meta's closed-loop dry cooling claims no operational cooling water; Telus claims 90 per cent less water; Lancaster capped use at 20,000 gallons a day (Meta 2026; Telus via Vancouver Is Awesome 2026; Columbia 2026). Confidence: medium; claims are the developers'. | Indirect water and local conflict: 60 per cent of a hyperscale site's water is indirect; US indirect water ~800 billion litres; Project Blue wells up to 31 million gallons a year; Wonder Valley licence 24 million m3 (IEA 2025; LBNL 2024; KJZZ 2026; ELC 2026). Confidence: high. |
| Community benefit packages: Meta's $60 million for roads and water plus grants; Lancaster's USD 20.25 million CBA (Meta 2026; Columbia 2026). Confidence: high. | Opportunity cost of clean megawatts: 100 MW equals the annual use of ~350,000 EVs or 40,000 to 64,000 homes; BC could offer only 400 MW against ~800 MW requested (Climate Institute 2025; CBC citing York University 2026; BLG 2026). Confidence: medium. |
| Indigenous ownership: Woodland Cree's majority-owned 650 MW project; BC scores First Nations benefits in its call (CBC 2025; BLG 2026). Confidence: medium. | Stranded-asset risk: USD 6.2 billion of one PJM auction for unbuilt data centres; 20.7 GW requested against 12 GW peak in Alberta; Georgia forced a utility backstop; USD 64 billion of US projects blocked or delayed (Utility Dive 2026; DeSmog 2026; Georgia PSC 2025; Data Center Watch 2025). Confidence: medium. |
| Grid modernization and surplus generation: hyperscalers often build 1.5 times their need and sell surplus; Suncor's 800 MW cogeneration lowered early-2026 prices (The Hub 2026). Confidence: low to medium. | Noise, land and diesel: 105 dB generators, 70 dBA cooling towers; 448 ha of farmland at Rocky View; 1.8 GW of diesel backup at Olds (EESI 2026; CBC 2025; Epoch Times 2026). Confidence: high. |
| Secrecy and trust: NDAs in Hamilton and Olds; only 1 of 8 US CBAs public; 68 per cent of Canadians oppose a nearby site (National Observer 2026; Narwhal 2026; FAS 2026; Angus Reid 2026). Confidence: high. |
Canada entered 2025 as the most integrated trading partner of the United States and enters the autumn of 2026 in an open tariff war with it. For anyone deciding where to put an AI data centre, the story matters less for the headline rates than for what it reveals about three things: which inputs are taxed, whether electrons or intelligence are the better export, and how much policy risk sits on top of a 20-year asset.
The first phase of the war, from February 2025, was built on IEEPA and framed around fentanyl. Executive Order 14193 set 25 percent on Canadian goods and 10 percent on energy from March 4, 2025, and Executive Order 14325 lifted the general rate to 35 percent on August 1, 2025. The critical fact for business was the March 7, 2025 carve-out for CUSMA-compliant goods, which covered roughly 95 percent of Canadian exports according to the trade minister. The fentanyl tariffs therefore hurt selectively, while the Section 232 measures on steel and aluminum (50 percent from June 4, 2025), autos (25 percent from April 3, 2025), copper and lumber did the real damage to specific industries. Canada retaliated in March 2025 on about $60 billion of US goods, then on September 1, 2025 removed most of those counter-tariffs to mirror the CUSMA exemption, keeping only steel, aluminum and autos. The digital services tax was sacrificed on June 29, 2025 to restart talks; Ontario's Reagan advertisement ended them again in October.
The legal ground then shifted twice. On February 20, 2026 the Supreme Court ruled 6-3 that IEEPA does not authorise tariffs. The administration replaced the fentanyl tariffs within days with a 10 percent Section 122 surcharge that again exempted CUSMA goods and energy, and used the 150-day window to prepare Section 301 findings. When that surcharge expired on July 24, 2026 the US turned to the untested Section 338 of the 1930 Tariff Act: three proclamations signed July 20, 2026 set 50 percent duties on listed Canadian goods, worth about $28 billion or 5 percent of exports, with no CUSMA exemption. A three-day pause on August 18 and a presidential announcement of a "DEAL" were followed by Canada's decision on August 21 to walk away. The interim terms on the table would have lowered US auto tariffs to 15 percent and metals to 25 percent, but excluded medium and heavy trucks, obliged Canada to drop its counter-tariffs and provincial alcohol bans, and constrained future Canadian trade deals and cultural policy. Canada's answer from September 8, 2026 is a rate-for-rate list of $27.6 billion.
Sitting under all of this is the July 1, 2026 CUSMA joint review, at which the US declined to renew. The agreement stays in force to 2036 but now lives year to year, and the US agenda for 2027 includes 50 percent US parts content in vehicles, tighter rules on Chinese inputs, dairy, alcohol and what the US Trade Representative called "digital trade alignment". That last item is the one that touches data centres directly. Chapter 19 of CUSMA already forbids data-localisation requirements (Article 19.12) and restrictions on cross-border data flows (Article 19.11) for commercial purposes. A federal sovereign-cloud strategy that mandates Canadian hosting for government or regulated data can be squared with those articles through the public-policy exception, but it invites exactly the kind of challenge the US is signalling.
For the data-centre builder, the tariff map is more favourable than the headlines suggest. Graphics processors and servers enter Canada from Taiwan, Mexico and Vietnam without touching US tariffs; the January 2026 US chip tariff is narrow and exempts chips destined for US data centres, and the AI Diffusion Rule that briefly rationed chips by country tier was rescinded in May 2025. The tariffs that do bite are on the power and cooling side. Since April 6, 2026 the US charges Section 232 duties on the full value of transformers, switchgear, racks and copper cabling, at 25 percent for most items and 50 percent for some copper goods, with a temporary 15 percent band for very large transformers. Those duties raise US project costs, not Canadian ones, and the August 26, 2026 grid-equipment emergency order tightens US supply further. On the Canadian side the costs come from Ottawa's own counter-tariffs: 25 percent on US steel and aluminum since March 2025, 25 percent on steel derivatives since December 2025, and from September 8, 2026 duties of up to 50 percent on US appliances and electronics. A project that sources switchgear from Wisconsin or racks from Ohio pays more; one that sources from Europe or Asia does not. The Buy Canadian rule for federally funded projects over $25 million pushes the same way.
Energy is where Canada's leverage and its temptation both lie. In 2025 Canada shipped 3.9 million barrels a day of crude, 8.6 billion cubic feet a day of gas and 32.7 terawatt-hours of electricity to the United States, supplying 63 percent of US crude imports, nearly all of its gas imports and 81 percent of its electricity imports. Ontario tested electricity as a weapon on March 10, 2025 and withdrew it within a day after Trump threatened 50 percent on steel; in August 2026 Ontario and Quebec floated the idea again while the Prime Minister, Alberta and Saskatchewan rejected export taxes. The federal answer is to expand rather than withhold. The Churchill Falls and Gull Island agreement of August 17, 2026 (net present value $49 billion) reserves 985 megawatts of transmission access into New York and New England, the Champlain Hudson line began delivering Quebec power to New York in January 2026, and Ottawa wants to double grid capacity by 2050 and triple LNG exports, with German buyers already signed. In parallel, the "export intelligence" thesis is being tested in Alberta, where Meta's $13 billion, 1 gigawatt campus will run on a purpose-built gas plant, and in British Columbia, where TELUS is scaling to 150 megawatts of hydro-powered sovereign compute. The honest summary is that Canada is trying to export both electrons and intelligence, and the binding constraint is local consent: 68 percent of Canadians would oppose a large data centre near their home and four in five Albertans worry about their power bills.
The sovereignty argument strengthened through the war. The CLOUD Act lets US authorities reach data held by US-controlled firms wherever it sits, and three US firms take about 85 percent of Canadian cloud spending. That is the addressable market for TELUS, Bell, Cohere and the federal program, and it explains why a Canadian government that once feared a US retaliation over "digital" policy still launched a large-scale sovereign data-centre call in January 2026. Public opinion supports the direction: 46 percent agree Canada needs domestic AI infrastructure, 90 percent reject annexation, and Canadians cut trips to the US by a quarter in 2025.
What could go wrong? The United States is competing for the same capital and chips with permitting waivers, federal land and Japanese-financed gas plants, and the hyperscalers plan to spend around US$760 billion in 2026, almost all of it at home. Canada is outside Pax Silica, the US-led technology alliance, and the semiconductor proclamation holds a "phase two" of broad chip tariffs in reserve. Section 338 itself may not survive the courts, which cuts both ways: relief for exporters, and more volatility. The macro cost of no deal is modest in aggregate (RBC estimates 0.4 percent of GDP) but concentrated in Ontario and Quebec manufacturing. For a data-centre investor the balance is a cost advantage on power equipment, strong and growing demand for Canadian electricity and Canadian-controlled compute, and a policy environment in which the rules of North American trade will be renegotiated every year until 2036.
Dates are the date of the action; where signing and effect differ, both are shown. Source numbers refer to the list at the end.
| Date | Measure | Value | Status | Source |
|---|---|---|---|---|
| Mar 4, 2025 | 25% on US consumer goods (Phase 1) | $30 billion | Removed Sept 1, 2025 | [27] |
| Mar 13, 2025 | 25% on US steel ($12.6 billion), aluminum ($3 billion), other ($14.2 billion) | $29.8 billion | Steel and aluminum kept; other removed Sept 1, 2025 | [27] |
| Apr 9, 2025 | 25% on non-CUSMA US vehicles and non-North-American content | n/a | In force (cited by Proclamation 11048) | [27][8] |
| Apr 15, 2025 | Remission for manufacturing inputs; Large Enterprise Tariff Loan Facility | six months, extended | Remission on US steel ended Jan 31, 2026 | [1][28] |
| Dec 26, 2025 | 25% on steel derivatives; quota cuts for non-FTA (20% of 2024) and FTA (75%) steel | $10 billion | In force | [28] |
| Sept 8, 2026 | 15%, 25% and 50% "rate for rate" on 700-plus US products (steel, dairy, appliances, farm equipment, pulp and paper, electronics) | $27.6 billion (US$19.9 billion) | Announced Aug 25, 2026; seafood dropped Aug 26 | [25][51] |
| Aug 25, 2026 | Support: Regional Tariff Response Initiative $1.5 billion; BDC liquidity $500 million; Canada Strong Diversification Fund $2 billion; worker and employer supports $3.5 billion | $7.5 billion (on top of about $25 billion since 2025) | Announced | [25][23] |
| Indicator | Value | As of | Source |
|---|---|---|---|
| Share of Canadian merchandise exports going to the US | 72% (87% in 2000) | 2025 | [46] |
| Share of Canadian exports to the US that are CUSMA compliant | about 95% | Feb 2026 (Minister LeBlanc) | [9] |
| Canadian exports covered by the Section 338 tariffs | about 5% to 5.5% of exports to the US (about $28 billion) | Aug 2026 | [23][47][46] |
| Energy exports to the US (crude, refined, gas, NGLs) | $157.5 billion; 20.2% of all goods exports | 2025 (CER, May 27, 2026) | [33] |
| Crude exports to the US | 3.9 million b/d (90.1% of Canadian crude exports); $126.1 billion; 63.4% of US crude imports | 2025 | [33] |
| Natural gas exports to the US | 8.6 Bcf/d; $12.5 billion; nearly 100% of US gas imports | 2025 | [33][34] |
| Electricity exports | 32.7 TWh; $3.3 billion; 81.3% of US electricity imports; imports 22.1 TWh ($1.4 billion) | 2025 | [33] |
| US-Canada total energy trade (US view) | US$137 billion (-11%); US imports from Canada US$111 billion; crude US$94.7 billion | 2025 (EIA, Jul 29, 2026) | [34] |
| Prime Minister's dependence figures | Canada supplies 99% of US gas imports, 85% of electricity imports, 60% of crude | Aug 22, 2026 | [24] |
| Canadian return trips from the US | 29.1 million, -25.4%; overseas trips 14.2 million, +9.2% | 2025 (StatCan, Feb 23, 2026) | [35] |
| Canadian travel spending in the US | $18.8 billion (leisure visits -21.5%, -3.2 million) | 2025 | [36] |
| Trans-border travel to the US | -8.7% year over year | Jul 2026 | [36] |
| US spirits exports to Canada | -63% (about US$725 million lost) | 2025 (DISCUS) | [51] |
| Foreign direct investment into Canada | $96.8 billion, highest since 2007 | 2025 (TD Economics via [57]) | [57] |
| Macro cost of no deal | about 0.4% of GDP and employment (RBC); 87,000 jobs at risk (Tombe); Quebec -0.3% of GVA by 2028 (Oxford Economics) | Aug to Sept 2026 | [46][58] |
| Date | Actor | Announcement | Scale | Source |
|---|---|---|---|---|
| Budget 2024 (ongoing) | Government of Canada | Sovereign AI Compute Strategy | $2 billion: up to $700 million AI Compute Challenge, up to $1 billion public infrastructure, up to $300 million AI Compute Access Fund | [29] |
| Mar 20, 2025 | ISED and Cohere | Federal investment in Cohere; CoreWeave facility in Cambridge, Ontario as anchor site | up to $240 million | [31] |
| Sept 2025 | TELUS | Rimouski sovereign AI facility opens (sold out) | n/a | [30] |
| Jan 15 to Feb 15, 2026 | ISED | Call for proposals: Enabling Large-Scale Sovereign AI Data Centres | no funding committed yet (May 2026) | [30] |
| May 11, 2026 | TELUS and Canada | MOU for a BC AI factory cluster (Kamloops, two Vancouver sites) | 60,000-plus GPUs; 150 MW by 2032 (85 MW initial); about $9 billion economic value | [30] |
| Jun 2, 2026 | Bitdeer | Fox Creek, Alberta gas plant plus data centre | 101 MW generation, about 100 MW compute | [59] |
| Jun 4 to 10, 2026 | Government of Canada; RBC | "AI for All" strategy (equity stakes, sovereign foundation); RBC notes targets of 850 MW by 2030 scaling to 2.3 GW | n/a | [42] |
| Jun 18, 2026 | HIVE (BUZZ HPC), Bell AI Fabric, Cohere | Three-year GPU contract in BC (Merritt) | US$220 million; 2,304 Grace Blackwell GPUs | [32] |
| Jul 8, 2026 | Meta | First Canadian data centre, Sturgeon County, Alberta; Greenlight gas plant ($4.2 billion, 932 to 970 MW); Capital Power 250 MW from H2 2028 | $13 billion; about 1 GW; 3,000 construction jobs; about $250 million a year to Alberta | [38] |
| Jul 14, 2026 | HUMAIN (Saudi Arabia) and Cohere | Compute supply and Arabic models partnership | at least 50 MW from late 2027 | [32] |
| Aug 17, 2026 | Canada, Quebec, Newfoundland and Labrador | Churchill Falls and Gull Island agreement | NPV $49 billion; Gull Island 2,700 MW; wind 2,000 MW; 985 MW export access; federal $3.5 billion NPV | [37] |
| Aug 20, 2026 | Anthropic | Hiring a Canada compute lead and Alberta community manager | "gigawatts of compute" (aspiration) | [39] |
| Sept 14 to 15, 2026 | Government of Canada, CPP Investments, PSP | Canada Investment Summit | target up to $1 trillion over five years | [60] |
| US comparators | Amazon, Alphabet, Microsoft, Meta | 2026 capital spending plans; US data-centre equipment imports; federal-land campuses | about US$760 billion combined capex (2026); US$653.1 billion equipment imports (2025); Piketon 10 GW, Paducah US$100 billion | [45][49] |
Direction is for Canada's AI data-centre opportunity. Magnitude and confidence are the analyst's judgment from the cited evidence.
| Factor | Direction for Canada | Magnitude | Confidence | Evidence (as of Sept 2, 2026) |
|---|---|---|---|---|
| US Section 232 duties on the full value of transformers, switchgear, racks and copper cabling (25% to 50%) raise US build costs but not Canadian ones | Positive (relative cost) | Medium | Medium | Proclamations 11021 and 11032; US power-infrastructure imports US$77 billion in 2025 (transformers US$35.4 billion). Illustrative arithmetic only: if tariff-exposed electrical and mechanical gear is 20 to 30 percent of a US project's capex and faces 25 percent, US capex rises roughly 5 to 7 percent. [18][45] |
| Canada's own counter-tariffs on US steel, aluminum, steel derivatives (25%) and, from Sept 8, 2026, US electronics and appliances (15% to 50%) raise Canadian project costs for US-sourced inputs | Negative | Medium | Medium-high | Finance Canada lists; Buy Canadian rules for federally funded projects over $25 million. [25][28] |
| GPU and server imports into Canada face no US tariff; the 25% US chip tariff is narrow and exempts US data-centre use; H200-class exports to China now licensed case by case | Neutral to positive | Low | Medium | Proclamation 11002; BIS rule of Jan 15, 2026. Watch the "phase two" broad chip tariff and Canada's absence from Pax Silica. [10][11][26] |
| CLOUD Act exposure drives demand for Canadian-owned, Canadian-operated compute | Positive | Medium | Medium-high | 85 percent of Canadian cloud spend goes to three US firms; federal sovereign program; TELUS, Bell-Cohere, provincial sovereign-cloud procurements. [42][30][32][43] |
| CUSMA uncertainty: no renewal, annual reviews, US demands for "digital trade alignment"; Articles 19.11 and 19.12 limit localisation mandates | Negative (policy risk) | Medium-high | Medium | USTR statement Jul 1, 2026; Greer Jul 22, 2026; Chapter 19 text; Bloomberg Aug 20, 2026. [19][22][48][52] |
| Risk of US restrictions on Canadian-hosted compute or chip access | Negative (tail risk) | Low-medium | Low | No restriction found; AI Diffusion Rule (Canada top tier) rescinded May 13, 2025; American AI Exports Program targets allies; but Canada left out of Pax Silica and Trump said Canada will "no longer be treated like a State" (Aug 24, 2026). [12][13][16][26][51] |
| US demand for Canadian power (New England, New York, Midwest) | Positive | High | High | 81.3 percent of US electricity imports; CHPE line live January 2026; Churchill Falls deal reserves 240 MW CHPE and 200 MW NECEC access; New York imports over US$20 billion of Canadian goods a year. [33][34][37][61] |
| Electricity as a bargaining chip (Ontario March 2025; Ontario and Quebec August 2026) | Negative (reliability perception) | Medium | Medium | Surcharge withdrawn within a day in 2025; Carney rejects energy leverage (Jul 29, 2026); western premiers oppose export taxes (Aug 31, 2026). [51][48][53] |
| Keeping power at home to host compute ("export intelligence") | Positive | High | Medium | Meta 1 GW in Alberta; TELUS 150 MW in BC; Alberta in talks with at least 60 proponents; grid-doubling plan; but 68 percent local opposition and 81 percent bill anxiety. [38][30][41][40][17] |
| US federal push (AI Action Plan, EO 14318 permitting, federal-land campuses, Japanese-financed gas plants) competes for capital and chips | Negative | High | High | 13 GW-plus on DOE sites; about US$760 billion hyperscaler capex in 2026, overwhelmingly US-located. [14][15][49] |
| US grid and political constraints (Texas freeze, 474 GW queue, PJM curtailment rules, data-centre backlash in 21 midterm races) push developers to look north | Positive | Medium | Medium | Reuters Sept 1, 2026. [50] |
| Trade-war macro shock (0.4 percent of GDP; weaker dollar; Quebec hardest hit) | Mixed | Low-medium | Medium | Weaker Canadian dollar lowers Canadian operating costs in US dollar terms but raises imported equipment costs. [46][58] |
| Diversification partners (EU SAFE and LNG offtake, UK CPTPP accession Sept 1, 2026, India CEPA push, Gulf compute links) | Positive | Low-medium | Medium | German LNG deals; HUMAIN-Cohere; MGX's US$49 billion fund has no verified Canadian deal; Canada Investment Summit Sept 14 to 15, 2026. [16b][32][54][60] |
| Sovereignty sentiment (boycotts, 45 percent name Trump a top issue, defence procurement shifting to Europe) supports "made in Canada" compute procurement | Positive | Medium | Medium | Abacus Aug 30, 2026; $60 billion defence industrial strategy Aug 27, 2026; Buy Canadian policy. [28][58] |
Canada's relationship with artificial intelligence is a story of an early lead that has been hard to bank. The technical foundations of the current boom were laid in Canadian universities: Geoffrey Hinton's deep-learning work at the University of Toronto earned a share of the 2024 Nobel Prize in Physics, Yoshua Bengio built Mila in Montreal into what it describes as the largest concentration of deep-learning academic researchers in the world, and Richard Sutton's reinforcement-learning research at the University of Alberta and Amii was recognized with the 2024 ACM Turing Award announced in March 2025. The Canadian Institute for Advanced Research (CIFAR) funded these people for decades, and in 2017 Ottawa turned that bet into the world's first national AI strategy, the Pan-Canadian AI Strategy, with $125 million, followed by $443.8 million in 2021 and $174 million in late 2024. More than 150 Canada CIFAR AI Chairs have been funded across the three institutes (Vector in Toronto, Mila in Montreal, Amii in Edmonton), and the June 2026 federal strategy promises to grow the program to nearly 200 chairs.
The people are still here, at least in aggregate. Stanford's 2026 AI Index counts 31,450 top AI authors and inventors working in Canada in 2025, the fifth-largest pool in the world and the sixth-largest per capita. AI-related job postings were 3.0 percent of all Canadian postings in 2025, fifth globally, and Canada leads the G7 in AI research papers per person. Yet two numbers should worry students who plan to build careers here. The same AI Index shows that Canada's net flow of AI authors and inventors, which was strongly positive around 2020, fell to minus 7.1 in 2025. And the federal government's own AI for All strategy concedes that nearly 70 percent of Canadian-led startups end up headquartered outside the country. Tenstorrent, a chip designer founded in Toronto, moved its headquarters to California in 2024 to satisfy an investor's ownership caps and prepare for a US listing, while keeping 140 engineers in Toronto. Untether AI, another Toronto chip startup, shut down in June 2025 when AMD hired its engineering team and dropped its products. The counter-flow is real but small: the Global Impact+ initiative announced in August 2026 recruited 64 scholars, 48 of them from US universities, with $504 million over eight years drawn from Budget 2025's $1.7 billion talent envelope, and applications from US scientists to Canadian posts reportedly jumped after the US administration's research cuts. On immigration, the signals are mixed: a new Express Entry category for researchers and senior managers with Canadian experience opened in February 2026, but the Start-Up Visa program was suspended on January 1, 2026 after wait times passed ten years.
The compute picture is where the gap between reputation and capacity is widest. The last comprehensive comparison, by The Dais in March 2024 using the November 2023 TOP500 list, put Canada at 41 petaflops, about 0.7 percent of global supercomputing performance, last in the G7 and half of the United Kingdom, the next-lowest member. Canadian researchers largely train on foreign clouds; three US firms take roughly 85 percent of Canadian cloud infrastructure spending, and Cohere, the country's flagship model company, rents its Canadian capacity from a US operator, CoreWeave, in a Cambridge, Ontario facility that Ottawa backed with up to $240 million toward a $725 million project. The federal response has come in three waves: the $2 billion Canadian Sovereign AI Compute Strategy from Budget 2024 (a $700 million AI Compute Challenge, up to $1 billion for a public supercomputer, and a $300 million access fund), the $925.6 million for sovereign public AI infrastructure and $1.7 billion for researcher recruitment in Budget 2025, and the $2.3 billion AI for All strategy of June 2026, which adds $700 million to the Compute Access Fund and commits to a "world-leading" public supercomputer. The strategy also states the scale of the problem plainly: Canada's commercial players will need about 5.5 GW of AI compute by 2030, while the partnerships now being finalized propose 850 MW by 2030 with room to scale to 2.3 GW. In other words, even if every announced sovereign project lands, most Canadian AI workloads in 2030 will still run in facilities owned by foreign hyperscalers, which is exactly why Microsoft's $19 billion Canadian program (2023 to 2027) and Meta's $13 billion, 1 GW Alberta campus announced in July 2026 matter so much.
Capital tells a similar story of strength that leaks abroad. Canadian venture investment was $8.0 billion in 2025, down 6 percent, but AI took 54 cents of every dollar and drove the largest rounds: Cohere's climb to a USD 7 billion valuation in September 2025 (with Nvidia, AMD, PSP Investments, HOOPP and BDC among investors), Waabi's USD 750 million Series C in January 2026, and Clio's USD 500 million Series G at a USD 5 billion valuation alongside its USD 1 billion acquisition of vLex. Xanadu became the first new Canadian tech listing on the TSX since 2021 when it debuted in March 2026, and in August 2026 secured a $195 million federal loan for a photonics plant in Toronto. Cohere's April 2026 merger with Aleph Alpha, at a reported combined value of about USD 20 billion and with EUR 500 million from Germany's Schwarz Group, keeps the head office in Toronto but makes the company transatlantic. Meanwhile, Canada's largest pools of patient capital are financing the AI build-out mostly elsewhere. CPP Investments' data-centre commitments since mid-2025 add up to roughly $6 billion, of which $225 million is in Ontario and the rest in Europe, the Nordics, India and a global platform with EQT. Brookfield's USD 100 billion AI infrastructure program, anchored by Nvidia and Kuwait's sovereign fund, has named multi-billion projects in Sweden and France but, as of July 2026, none in Canada. Whether Canadian institutions treat domestic data centres as investable at scale is one of the open questions of the next two years.
What would a wave of data centres mean for jobs? The evidence is that construction is labour-intensive and operations are not. Meta's Alberta campus expects more than 3,000 construction workers at peak but about 300 permanent staff; Telus's three British Columbia facilities claim 1,000 construction jobs and 525 permanent roles for 151 MW of capacity. The larger employment effect is indirect: electrical trades, transmission and generation work, cooling and mechanical contractors, and the professional services (law, engineering, project finance, regulatory affairs) that each 100 MW project requires. Alberta's interconnection queue holds more than 10 GW of proposals against a 1,200 MW connection cap, and the Pembina Institute estimates that Meta's project alone could add $267 to $462 a year to household electricity bills between 2027 and 2031, which is why the policy fight is now about who pays for the grid.
The think-tank consensus that emerges from 2025 and 2026 is unusually coherent. On energy, C.D. Howe, the Canadian Climate Institute and Pembina all want data-centre approvals tied to honest electricity pricing, cost allocation to large users, and demand flexibility. On sovereignty, C.D. Howe, IRPP authors and the Digital Research Alliance want a public supercomputer with a refresh budget and public compute reserved for research, while RBC and the Council of Canadian Innovators want the government and the banks to act as anchor customers for Canadian providers. On competition, C.D. Howe proposes spot and forward markets for compute and rules against self-preferencing by infrastructure owners. On talent, Universities Canada, PPF and Mitacs want AI literacy across disciplines and structured pathways from research to company formation. For MBA, MM and MBAN students the practical lesson is that the coming Canadian AI economy will be built as much by people who can site, finance, power and staff a 100 MW facility, and by managers who can move a firm from a 12 percent adoption rate toward the 60 percent target, as by the researchers who started it.
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Global AI Vibrancy Tool overall rank | 10 of 36 (score 15.56; US 78.60, China 36.95, India 21.59) | rank | 2025 release (data to 2024) | Canada | Stanford HAI via AffairsCloud, https://affairscloud.com/stanfords-global-ai-vibrancy-tool-2025-usa-tops-india-ranks-3rd/ |
| Tortoise Global AI Index overall rank | 8 of 83 (4th in 2021) | rank | Sept 2024 edition (latest found) | Canada | Tortoise Media, https://www.tortoisemedia.com/data/global-ai |
| Tortoise sub-pillar ranks | Government strategy 3rd; commercial 6th; operating environment 16th; infrastructure 18th | rank | 2024 | Canada | Logan Wealth citing Tortoise, https://www.loganwealth.com/resources/artificial-intelligence-can-canada-be-a-player |
| Private AI investment, single year | USD 2.89 billion (5th globally) in 2024; USD 4.28 billion (5th, behind US 285.9, China 12.4, UK 5.9, France 4.4) in 2025 | USD billion | 2024, 2025 | Canada | Stanford AI Index 2025 and 2026, https://hai.stanford.edu/ai-index |
| Private AI investment, cumulative | USD 15.31 billion 2013 to 2024 (4th); USD 19.59 billion 2013 to 2025 (4th, after US 757.3, China 131.8, UK 34.1) | USD billion | 2024, 2025 | Canada | Stanford AI Index 2025 and 2026 |
| Newly funded AI companies | 51 in 2024 (8th); 79 in 2025 (7th); 560 cumulative 2013 to 2025 (4th) | count | 2024, 2025 | Canada | Stanford AI Index 2025 and 2026 |
| Notable AI models released | 1 in 2024 and 1 in 2025 (US 59, China 35, South Korea 8 in 2025) | count | 2025 | Canada | Stanford AI Index 2026 (Epoch AI data) |
| Data centres counted | 337 (5th: US 5,427; Germany 529; UK 523; China 449) | count | 2025 | Canada | Stanford AI Index 2026 (Cloudscene data) |
| Generative AI adoption, share of population | 35.0 percent (rank 14) | percent | 2025 | Canada | Stanford AI Index 2026 |
| Trust and literacy | 44th of 47 on AI training and literacy; 42nd of 47 on trust in AI; 24 percent of Canadians have had any AI training | rank | 2025 study cited 2026 | Canada | KPMG and University of Melbourne cited in AI for All, https://ised-isde.canada.ca/site/ised/sites/default/files/documents/ai-strategy-en.pdf |
| Business AI adoption | 12 percent of businesses used AI mid-2024 to mid-2025; 14.5 percent planning by mid-2026; SMEs about 8 percent versus Nordic 29 to 42 percent | percent | 2025 | Canada | Statistics Canada cited in AI for All (June 2026); C.D. Howe Commentary 712 (April 2026) |
| Organizations that have implemented AI | 26 percent versus 34 percent globally | percent | 2025 | Canada | Deloitte Canada, https://www.deloitte.com/ca/en/about/press-room/canada-ai-future.html |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Top AI authors and inventors | 31,450 (5th after US 220,520; India 50,460; Germany 48,520; UK 34,370) | people | 2025 | Canada | Stanford AI Index 2026 (Zeki data), https://hai.stanford.edu/ai-index/2026-ai-index-report |
| Top AI authors and inventors per 100,000 people | 76.2 (6th; Switzerland 110.5; Singapore 109.5) | per 100,000 | 2025 | Canada | Stanford AI Index 2026 |
| Net flow of AI authors and inventors | minus 7.1 in 2025, after strong inflow around 2020 | net count index | 2025 | Canada | Stanford AI Index 2026 |
| Net AI talent migration (LinkedIn) | plus 1.23 per 10,000 LinkedIn members (US 1.22) | per 10,000 | 2025 | Canada | Stanford AI Index 2026 (LinkedIn data) |
| AI talent concentration (LinkedIn) | 0.93 percent of members in 2024 (up 166 percent since 2016); 1.01 percent in 2025 | percent | 2024, 2025 | Canada | Stanford AI Index 2025 and 2026 |
| AI job postings share | 1.41 percent of all postings in 2024; 3.00 percent in 2025 (5th globally) | percent | 2024, 2025 | Canada | Stanford AI Index 2025 and 2026 (Lightcast data) |
| Relative AI skill penetration | 1.30 (6th) 2015 to 2024; 1.54 (5th) 2015 to 2025 | index | 2024, 2025 | Canada | Stanford AI Index 2025 and 2026 |
| Top-tier AI researchers | 6th globally, 3 percent of the world's total | rank, percent | 2022 (cited 2024) | Canada | ISED What We Heard report, https://ised-isde.canada.ca/site/ised/en/what-we-heard-report-consultations-ai-compute |
| AI papers per capita | Leads the G7 since 2019 | rank | 2019 to 2024 | Canada | ISED What We Heard report (Nov 2024) |
| New ICT graduates | Bachelor's 13,590; master's 3,342; PhD 324 | graduates | 2023 | Canada | Stanford AI Index 2026 (OECD data) |
| New AI PhDs | Up 22 percent from 2022 to 2024, with the increase going to academia | percent | 2024 | US and Canada | Stanford AI Index 2026 (CRA Taulbee data) |
| Canadian-led startups headquartered outside Canada | Nearly 70 percent | percent | 2026 statement | Canada | AI for All strategy, ISED, June 2026 |
| Immigrants who leave Canada | 1 in 5 within 25 years; doctorate holders nearly twice as likely to leave as bachelor's holders | share | 2025 report | Canada | Institute for Canadian Citizenship and Conference Board "Leaky Bucket" via The Hub, https://thehub.ca/2026/04/22/canadas-brain-drain-is-only-half-the-story/ |
| Researchers recruited from abroad | 64 scholars, 48 from US universities (Cornell, Harvard, Yale, MIT); $504 million over eight years from the $1.7 billion Budget 2025 envelope | people, CAD | Aug 2026 | Canada | BetaKit, https://betakit.com/canada-poaches-64-global-scholars-in-bid-to-bolster-domestic-talent-pipeline/ |
| Canada CIFAR AI Chairs | More than 125 currently supported (CIFAR); over 150 funded to date; to grow from 130 to nearly 200 | researchers | 2026 | Canada | CIFAR, https://cifar.ca/ai/ ; AI for All (June 2026) |
| AI institute scale | Vector: 950+ researchers and faculty, 30+ industry partnerships; Mila: 1,400+ community, 905 students and interns trained in 2022-23, about 120 industry partners; Amii: figures not published on site | people | 2026 (site) | Toronto, Montreal, Edmonton | https://vectorinstitute.ai/about/ ; https://mila.quebec/en/mila ; https://www.amii.ca/about |
| Mitacs AI investment | $174.4 million directed to AI initiatives since 2018; 46,000 interns; 31 percent hired by partners | CAD million | 2025 | Canada | BetaKit, https://betakit.com/canadas-ai-edge-is-human/ |
| Data-centre jobs (examples) | Meta Alberta: 3,000+ construction, about 300 permanent; Telus BC: 1,000 construction, 525 permanent; Xanadu Toronto photonics plant: 275 | jobs | 2026 | AB, BC, ON | Invest Alberta (July 2026); BetaKit (May 2026); BetaKit (Aug 2026) |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| TOP500 supercomputing performance | 41.21 petaflops, about 0.7 percent of global; US 3,726; Japan 670; Germany 256; France 173; UK 82 | petaflops | Nov 2023 list | Canada | The Dais "Can Canada Compute?", https://dais.ca/reports/can-canada-compute/ |
| Per-capita compute gap | US 10.6 times Canada; Japan 7.6 times; France 2.4 times; Germany 1.9 times; UK 1.2 times | ratio | 2024 | G7 | The Dais (March 2024) |
| Estimated AI compute need | 5.5 GW for commercial players by 2030 | gigawatts | 2030 | Canada | AI for All strategy (June 2026) |
| Sovereign compute pipeline | 850 MW by 2030 scaling to 2.3 GW; large-scale data centres of at least 100 MW; 160 proposals received | MW | 2026 | Canada | AI for All (June 2026); BetaKit on Telus (May 2026) |
| Sovereign AI Compute Strategy | $2 billion over five years: up to $700 million AI Compute Challenge; up to $1 billion public supercomputing (about $890 million build layer under SCIP from 2026-27; $200 million near-term augmentation); $300 million AI Compute Access Fund | CAD | 2024 to 2029 | Canada | ISED, https://ised-isde.canada.ca/site/ised/en/canadian-sovereign-ai-compute-strategy |
| First compute grants | Cohere: up to $240 million toward a $725 million CoreWeave-operated facility in Cambridge, Ontario (operational August 2025); University of Toronto: $42.5 million to triple Trillium GPU capacity (Nov 2025) | CAD | 2024 to 2025 | Ontario | BetaKit; The Globe and Mail |
| Telus Sovereign AI Factory | Rimouski site opened Sept 2025; BC plan (May 2026): 75,500 Nvidia GPUs across Kamloops (25 MW), Vancouver Mount Pleasant (26 MW) and downtown Vancouver (100 MW, early 2029); $9 billion economic activity claimed | GPUs, MW | 2025 to 2029 | QC, BC | Telus; BetaKit, https://betakit.com/steel-concrete-and-code-feds-and-telus-announce-three-ai-data-centres-in-bc/ |
| Bell AI Fabric | Six data centres, 459+ MW planned, Groq processors, first BC sites 2025 | MW | 2025 | BC, MB, QC | BetaKit, https://betakit.com/bell-to-build-six-ai-data-centres-in-canada-as-telcos-compete-on-infrastructure/ |
| Foreign ownership of cloud and data centres | Three US firms take about 85 percent of Canada's cloud infrastructure spending and about 88 percent of enterprise foundation-model usage; US firms own nearly one-third of Canada's 283 data centres; 7 US firms and 1 Canadian (ThinkOn) on the federal cloud shortlist | percent | 2025 to 2026 | Canada | RBC Thought Leadership (June 2026); BetaKit (Sept 2025) |
| Alberta interconnection queue | More than 10 GW of proposed data centres; AESO capped new large-load connections at 1,200 MW, fully allocated | GW | 2025 to 2026 | Alberta | Canadian Climate Institute (March 2025); The Hub (Aug 2026) |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Canadian venture capital, full year | $8.0 billion across 571 deals (dollars down 6 percent, deals down 12 percent); ICT $5.06 billion; zero IPOs; venture debt $1.40 billion | CAD | 2025 | Canada | CVCA Year-End 2025, https://www.cvca.ca/insights/market-reports/year-end-2025/ |
| AI share of venture dollars | 54 cents of every dollar; 23 percent of rounds; AI median pre-money valuations about 60 percent above the rest of market | percent | 2025 | Canada | Osler Deal Points via BetaKit, https://betakit.com/not-a-blip-ai-was-canadas-venture-market-mover-in-2025/ |
| Venture capital, first half | $2.69 billion across 250 deals, up 17 percent; 16 mega-deals worth $1.57 billion; Beacon Software $313 million; US investors in 28 percent of deals | CAD | H1 2026 | Canada | CVCA via Financial Post, https://finance.yahoo.com/news/venture-capital-investment-canada-jumps-100023869.html |
| Cohere | USD 7 billion valuation (Sept 2025); USD 240 million annualized revenue (Feb 2026); Aleph Alpha merger at reported USD 20 billion combined value with EUR 500 million from Schwarz Group (April 2026) | USD | 2025 to 2026 | Toronto | BetaKit, https://betakit.com/cohere-to-acquire-germanys-aleph-alpha-in-sovereign-ai-play/ |
| Brookfield AI infrastructure | USD 100 billion program; BAIIF USD 10 billion target, USD 5 billion secured at launch with Nvidia and Kuwait Investment Authority; Sweden SEK 95 billion (June 2025); France EUR 20 billion rising to EUR 30 billion (2025); Bloom Energy USD 5 billion; no Canadian project disclosed | mixed | Nov 2025 | Global | Brookfield; ION Analytics, https://ionanalytics.com/insights/infralogic/brookfields-wide-ranging-ai-infra-strategy/ |
| CPP Investments data-centre commitments | $225 million Cambridge, Ontario (Aug 2025); about $1.8 billion Goodman Europe (Dec 2025); USD 1.6 billion atNorth (Feb 2026); up to $1 billion CtrlS India (June 2026); $2.4 billion EQT and EdgeConneX (July 2026) | CAD and USD | 2025 to 2026 | Global | Investment Executive, https://www.investmentexecutive.com/?s=CPP+Investments+data+centre |
| Hyperscaler commitments in Canada | Microsoft $19 billion 2023 to 2027 (new capacity from H2 2026); Meta $13 billion, 1 GW, Sturgeon County, Alberta | CAD | 2025 to 2026 | Canada | Microsoft (Dec 2025); Invest Alberta (July 2026) |
| Federal AI funding, three steps | Budget 2024: $2.4 billion; Budget 2025: $925.6 million public AI infrastructure plus $1.7 billion for 1,000+ researchers; AI for All: $2.3 billion | CAD | 2024 to 2026 | Canada | Budget 2024 Chapter 4; Budget 2025 Chapter 1; BetaKit (June 2026) |
| Unit cost benchmarks | Hyperscale construction about $10 million per MW; compute hardware potentially more than $30 million per MW | CAD per MW | 2026 | Canada | Torys summarizing federal call, https://www.torys.com/our-latest-thinking/publications/2026/01/canada-promotes-investment-in-sovereign-large-scale-ai-data-centres |
| Dimension | Asset | Gap | Evidence |
|---|---|---|---|
| Research legacy | Hinton (Nobel 2024), Bengio (Turing 2018, LawZero 2025), Sutton (Turing 2024); first national AI strategy (2017); three institutes with 150+ CIFAR chairs | Only one notable model a year originates in Canada; Canadian labs train on foreign clouds | Stanford AI Index 2026; ISED AI for All (2026) |
| Talent | 5th in top AI authors and inventors; leads G7 in AI papers per capita; AI job postings 3.0 percent of all postings (5th) | Net flow of AI authors and inventors negative in 2025; 70 percent of Canadian-led startups end up headquartered abroad; Start-Up Visa suspended Jan 2026 after 10-year waits | Stanford AI Index 2026; AI for All; BetaKit (Dec 2025) |
| Compute | Clean grid (about 85 percent non-emitting), cool climate, 337 data centres; $2 billion sovereign strategy plus $925.6 million | 0.7 percent of global supercomputing performance (2023), last in G7; 5.5 GW need vs 850 MW pipeline; Alberta queue capped at 1,200 MW | The Dais 2024; AI for All 2026; Climate Institute 2025 |
| Companies | Cohere (USD 7 billion), Waabi (USD 750 million round), Clio (USD 5 billion), Xanadu (listed), Hypertec (Nvidia OEM), Ranovus (photonics) | Tenstorrent moved HQ to the US; Untether AI closed; Cohere rents compute from a US operator; no Canadian GPU fabrication | BetaKit; CRN; B2BNN (May 2026) |
| Capital | $8 billion venture market with AI at 54 percent; deep pension capital; BDC deployed $832 million in H1 2026 | Pension data-centre money mostly deployed abroad; zero IPOs in 2025 and H1 2026; US investors in 28 percent of deals and 56 percent of later-stage rounds | CVCA 2026; Investment Executive 2026 |
| Adoption | Individual generative AI use among the world's highest (35 percent of population, rank 14) | Business use 12 percent (target 60 percent by 2034); 44th of 47 on AI training and literacy | Stanford AI Index 2026; AI for All 2026 |
| Energy and grid | Renewable-heavy provinces (BC, QC, MB) attract sovereign projects; Alberta offers bring-your-own-generation | Six-year grid connection waits; Meta could add $267 to $462 a year to Alberta bills 2027 to 2031; Ontario demand up 65 percent by 2050 | RBC (Aug 2026); Pembina (Aug 2026); C.D. Howe (Aug 2026) |
| Stakeholder | Recommendation | Who made it | Date | Source |
|---|---|---|---|---|
| Federal government | Expand sovereign compute beyond the $2 billion strategy; create spot and forward markets for compute; support open-weight models; remove regulatory barriers to data-centre build-out | C.D. Howe Institute (Daniel Schwanen, Commentary 713) | 2026-04-15 | https://cdhowe.org/publication/chipping-in-a-canadian-guide-for-maintaining-competition-in-ai/ |
| Federal government | Update privacy law quickly; build open public data assets; fund StatCan's TechStat; keep SR&ED and accelerated capital cost allowance; mid-career skills strategy | C.D. Howe Institute (Rosalie Wyonch, Commentary 712) | 2026-04-09 | https://cdhowe.org/publication/from-hype-to-output-how-ai-investment-translates-to-real-productivity-gains/ |
| Federal government | Pilot private-sector access to confidential StatCan data, synthetic datasets, regional AI sandboxes, and a Bill C-27 successor with de-identification standards | C.D. Howe Institute (Anindya Sen, Commentary 706) | 2026-02-12 | https://cdhowe.org/publication/the-missing-pillar-of-canadas-ai-strategy-data-supply-chains/ |
| Federal government | Use anchor procurement to build domestic suppliers; convert AI for All into measurable milestones; give the public supercomputer a refresh cycle and budget | C.D. Howe Institute (Harvey Naglie) | 2026-06-10 | https://cdhowe.org/publication/executing-ai-for-all-how-to-get-a-capability-raising-result/ |
| Federal government | Make infrastructure funding conditional on clean-supply matching and demand flexibility; enforce Clean Electricity Regulations and carbon pricing; national clean-AI reporting standard | Canadian Climate Institute (Dale Beugin, Kate Harland) | 2026-05-26 | https://climateinstitute.ca/canadas-ai-and-electricity-strategies-can-and-should-be-mutually-reinforcing/ |
| Federal government | Create a Powering Canada Forward Fund with a national benefits test to expand grids while keeping delivery prices flat in real terms | Canadian Climate Institute (Beugin, Harland, Liebreich, Smith) | 2026-07-22 | https://climateinstitute.ca/policy-brief-powering-canada-forward-fund/ |
| Federal government | Prioritize public compute for non-commercial AI, shift funding from private support to public infrastructure, coordinate with aligned countries | IRPP Policy Options (Guillaume Beaumier, Hubert Cadieux) | 2026-05-06 | https://policyoptions.irpp.org/2026/04/ai-public-infrastructure/ |
| Federal government | Pursue small task-specific models, a Crown corporation for sovereign compute, and clean-powered data-centre parks with Indigenous governance | IRPP Policy Options (Anne Pasek and co-authors) | 2025-10-20 | https://policyoptions.irpp.org/2025/10/ai-made-in-canada/ |
| Federal government | Reform PIPEDA and the Privacy Act; use CUSMA carve-outs for data sovereignty; scale sovereign compute to 850 MW by 2030 and 2.3 GW; keep flexible procurement authority; retain AI graduates | RBC Thought Leadership | 2026-06-10 | https://www.rbc.com/en/thought-leadership/ai-technology-and-innovation/sovereign-ai-shaping-canadas-next-digital-chapter/ |
| Federal government | Raise AI safety funding well above $50 million; put mandatory skilling and inclusion clauses in AI procurement; regular StatCan reporting on AI's labour effects; align with the EU AI Act | Public Policy Forum (Shingai Manjengwa) | 2026-06-12 | https://ppforum.ca/ppf-media/six-key-takeaways-from-canadas-ai-strategy/ |
| Federal government | Give Canadian AI firms a clear roadmap to scale globally; act as an early customer; improve compute access and growth capital; crowd in domestic private investment | Council of Canadian Innovators (Laurent Carbonneau), MaRS (Grace Lee Reynolds), CVCA (Ben Bergen) via BetaKit | 2026-06-04 | https://betakit.com/canadas-ai-strategy-draws-mixed-reviews-from-across-the-tech-ecosystem/ |
| Federal government | Pro-innovation regulation; targeted incentives; sector AI centres; expand compute providers; fund upskilling; build public trust | Canadian Chamber of Commerce | 2026-02-10 | https://chamber.ca/policy-matters-the-big-questions-about-ai-and-canadian-business/ |
| Federal government | Invest in GPU-class high-performance computing and sustainable data centres; accelerate domestic semiconductor manufacturing; value-based procurement; multi-year partnerships with local vendors | Ontario Chamber of Commerce (letter to Minister Champagne) | 2024-09-06 | https://occ.ca/wp-content/uploads/ISED-AI-Compute-Consultation-Recommendations-from-the-OCC.pdf |
| Federal government | Consolidate the SCIP investment into one large GPU-intensive public supercomputer kept off foreign clouds | Digital Research Alliance of Canada | 2025 to 2026 | https://ai.alliancecan.ca/ |
| Federal government | Combine centralized cloud subsidies, allied joint purchasing (EuroHPC model) and a $400 million to $1 billion domestic build | The Dais, Toronto Metropolitan University (Dobbs, Hirsch-Allen) | 2024-03 | https://dais.ca/reports/can-canada-compute/ |
| Federal government | "Host extensively, control selectively, compete strategically, adopt aggressively"; be the demanding first customer for Canadian AI | The Hub (Pouya Daneshpajooh) | 2026-08-14 | https://thehub.ca/2026/08/14/canada-helped-build-modern-ai-data-centres-could-power-its-next-advantage/ |
| Federal government | Rewrite AI regulation to target frontier models rather than all "high-impact" uses; rely on existing consumer and privacy law for use-case harms | Macdonald-Laurier Institute (Ryan Khurana) | 2025-01-02 | https://macdonaldlaurier.ca/canada-has-a-nobel-prize-for-artificial-intelligence-but-our-ai-red-tape-will-strangle-us-ryan-khurana-in-the-globe-and-mail/ |
| Federal government | Harmonized public investment aimed at competitive strengths; focus the AI Safety Institute on real-world risks; risk-based AI procurement; AI literacy in the national strategy | Deloitte Canada, "Building Canada's brightest AI future" | 2025-03-25 | https://www.deloitte.com/ca/en/about/press-room/canada-ai-future.html |
| Federal government | Expand the International Education Strategy into a talent, research and innovation strategy; align university research with AI, defence and sovereignty priorities | Universities Canada | 2026-05-19 | https://univcan.ca/news/universities-call-for-integrated-federal-action-to-strengthen-canadas-productivity-skills-and-sovereign-capability/ |
| Provincial governments | Promote data-centre investment using regional advantages (Alberta power and cooling); manage environmental impacts; pool complementary AI resources across provinces | C.D. Howe Institute (Schwanen) | 2026-04-15 | as above |
| Provincial governments | Set clear frameworks for competing industrial loads; long-term energy plans; allocate more infrastructure cost to large users; enable direct power purchase agreements; prioritization frameworks for large connections | Canadian Climate Institute (Kate Harland) | 2025-03-31 | https://climateinstitute.ca/smart-way-integrate-artificial-intelligence-data-centres-canada-electricity-grids/ |
| Provincial governments (Alberta) | Make large users pay the full cost of delivered energy; prioritize demand-side management; let data centres use wind, solar and storage alongside gas; redesign the bring-your-own-generation policy | Pembina Institute (David Pickup, Will Noel) | 2026-08-26 | https://www.pembina.org/pub/footing-bill |
| Provincial governments | Reserve dedicated energy blocks for public compute; manage expansion so electrification projects keep access | IRPP Policy Options (Beaumier, Cadieux) | 2026-05-06 | as above |
| Provincial governments (Alberta) | Accelerate project approvals and permitting for data centres, petrochemicals and carbon capture | Business Council of Alberta | 2026-02-24 | https://businesscouncilab.com/advocacy-category/alberta-budget-2026-three-things-were-looking-for/ |
| Provincial governments and utilities | Publish long-term cost forecasts; communicate capital needs; let rates rise gradually in real terms instead of shifting costs to taxpayers | C.D. Howe Institute (Cole Diepold) | 2026-08-04 | https://cdhowe.org/publication/canada-needs-a-bigger-grid-customers-need-an-honest-conversation/ |
| Utilities and system operators | Design connection processes and rate structures that reward flexibility; use competitive allocation weighing alternative grid uses; build flexible grids rather than overbuilding | Canadian Climate Institute (Beugin, Harland) | 2026-05-26 | as above |
| Utilities and system operators | Approve only projects that let the grid absorb load without raising rates for surrounding communities | Kathleen Kauth (Mantle Climate) and Tyler Hamilton (MaRS) in The Globe and Mail | 2026-08-27 | https://www.theglobeandmail.com/business/commentary/article-canada-ai-data-centre-backlash-recommendations/ |
| Municipalities | Negotiate grid upgrades, financial participation for residents, local startup and researcher access, apprenticeships, and noise mitigation | Kauth and Hamilton, The Globe and Mail | 2026-08-27 | as above |
| Municipalities | Pre-screen sites at the local or regional level for energy capacity and environmental assessment; run approvals in parallel | C.D. Howe Institute (Wyonch) | 2026-04-09 | as above |
| Municipalities and host communities | Negotiate local procurement, apprenticeships, waste-heat use; reserve compute capacity for local researchers and startups at predictable prices | The Hub (Daneshpajooh) | 2026-08-14 | as above |
| Indigenous communities | Federal preference for projects with Indigenous participation; equity partnerships in data centres | ISED (evaluation criteria for large-scale sovereign AI data centres); The Hub | 2026-01-15; 2026-08-14 | https://ised-isde.canada.ca/site/ised/en/enabling-large-scale-sovereign-ai-data-centres |
| Indigenous communities | Local Indigenous governance of clean-powered data-centre parks; procurement access for Indigenous-owned suppliers | IRPP Policy Options (Pasek et al.); Ontario Chamber of Commerce | 2025-10-20; 2024-09-06 | as above |
| Investors | Track Cohere, Bell AI Fabric, Telus and the Sovereign Cloud Consortium; treat the July 2026 CUSMA review and bank procurement decisions as market signals | RBC Thought Leadership | 2026-06-10 | as above |
| Investors | Back proven Canadian firms committed to a long-term domestic presence rather than quick exits | RBC "Own the Stack" (John Stackhouse with Global Relay) | 2026-06-30 | https://www.rbc.com/en/thought-leadership/ai-technology-and-innovation/own-the-stack-canadas-data-sovereignty-test/ |
| Investors and growth-capital providers | Condition capital on commercialization and Canadian scaling, but keep conditions light | C.D. Howe Institute (Naglie) | 2026-06-10 | as above |
| Investors | Close the research-to-company gap with dedicated funds such as the Mila and Inovia USD 100 million Venture Scientist Fund | Mila and Inovia (cited in AI for All) | 2026-01 | AI for All strategy |
| Operators and hyperscalers | Invest in renewables and storage; provide load flexibility at peak; locate on former industrial sites with existing grid capacity | Canadian Climate Institute (Beugin, Harland) | 2026-05-26 | as above |
| Operators and hyperscalers | Report annual water and energy use; manage water to local watersheds; create local jobs and procurement; support Canadian efficiency technologies | Kauth and Hamilton, The Globe and Mail | 2026-08-27 | as above |
| Operators and hyperscalers | Transparent pricing; access provisions for emerging competitors; no self-preferencing; documented interoperability | C.D. Howe Institute (Schwanen) | 2026-04-15 | as above |
| Operators and hyperscalers | Finance dedicated generation and transmission ("power comes first"); closed-loop cooling; transparent environmental standards | The Hub (Daneshpajooh) | 2026-08-14 | as above |
| Operators and hyperscalers | Projects over 100 MW judged on Canadian ownership and control, data residency, Canadian vendors, Indigenous participation and minimal environmental impact | ISED call for large-scale sovereign AI data centres | 2026-01-15 | as above |
| Universities | Host secure sovereign compute and data infrastructure; expand AI literacy; deliver the 90,000 student placements | Universities Canada | 2026-06-04 | https://univcan.ca/news/universities-canada-statement-on-release-of-the-national-ai-strategy/ |
| Universities | Integrate AI across all disciplines, not just computer science | Public Policy Forum (Manjengwa) | 2026-06-12 | as above |
| Universities and research institutions | Secure reasonable access to compute and data for academic and non-profit research; join public-private data infrastructure partnerships | C.D. Howe Institute (Wyonch) | 2026-04-09 | as above |
| Businesses that consume AI | Experiment despite pilot failures; redesign processes and business models around AI; invest in training and reorganization as complementary assets | C.D. Howe Institute (Wyonch) | 2026-04-09 | as above |
| Businesses that consume AI | Move from ambition to activation; redesign roles and workflows; cloud-native data platforms with privacy built in; broad workforce AI fluency | Deloitte Canada, State of AI in the Enterprise 2026 (175 Canadian executives) | 2026 | https://www.deloitte.com/ca/en/issues/generative-ai/state-of-ai-in-enterprise.html |
| Businesses that consume AI | Scenario-plan three CUSMA outcomes; split workloads between hyperscale and sovereign systems; treat model weights, datasets and AI talent as strategic assets; banks' procurement choices in the next 24 months decide the sovereign cloud market | RBC Thought Leadership | 2026-06-10 | as above |
| Businesses that consume AI | Adopt AI rather than protect legacy systems; invest in AI literacy to choose vendors confidently | C.D. Howe Institute (Schwanen) | 2026-04-15 | as above |
| Businesses and AI developers | Avoid partnerships that lock junior partners into proprietary APIs; judge partnerships by capability transferred, not deal size | C.D. Howe Institute (Schwanen; Naglie) | 2026-04-15; 2026-06-10 | as above |
A data centre is a power plant in reverse. The economics start from a single number, the megawatt of critical IT load, and almost every cost and revenue line is quoted per MW or per kW. In 2025 the shell, electrical and mechanical systems cost about US$10.7 million per MW on JLL's global measure, rising to US$11.3 million in 2026, while Cushman & Wakefield's 2026 cost guide, which reflects denser, liquid-cooled halls, puts the average modern greenfield build at US$17.6 million per MW, 21% above its previous guide. That is only the building. Filling the halls with AI servers adds up to US$25 million per MW (JLL), so the all-in cost of a frontier campus is about US$35-40 million per MW; Epoch AI's estimates for named campuses such as Meta's Prometheus (562 MW, US$21.3 billion) cluster near US$37.9 million per MW. The IEA's decomposition explains why: accelerated servers were 10% of global data-centre investment in 2015 and will be 45% by 2030, and IT equipment is written off over four to six years while a transformer lasts thirty.
Operating costs follow the same logic. Electricity is the largest line for whoever runs the building, and the sector's average PUE of 1.54 (Uptime 2025) means that for every kWh a server uses, another half is spent on cooling and distribution; Goldman Sachs estimates cooling alone is 35-40% of a hyperscaler's energy use. New Canadian builds can reach a PUE of 1.3 or better because of the climate. Staffing is the next line, and it is constrained: 46% of operators cannot find qualified candidates and the biggest skills gap has shifted to operations management (Uptime 2025). Maintenance and refresh of IT equipment is the third, and it is where the depreciation debate lives.
Revenue comes in three models. Retail colocation sells space and power by the kW; CBRE's North American average was US$184 per kW per month in H2 2024, up 12.6% in a year, with Northern Virginia up 15% by Q1 2025 and vacancy below 1%. Wholesale or hyperscale leasing sells whole halls on long take-or-pay leases; Applied Digital's June 2026 lease of 210 MW to an investment-grade hyperscaler for at least US$5.2 billion over 15 years works out to about US$138 per kW per month, and Digital Realty reported cash renewal spreads of 25% and stabilised yields above 10% in Q2 2026. GPU-as-a-service, the "neocloud" model of CoreWeave, Nebius and Lambda, sells compute by the GPU-hour or by contracted MW. Its prices fell hard in 2024-25, with AWS cutting its H100 instance list price by 44% in June 2025 and the market median settling near US$2.50-3.00 per H100-hour, but 2026 brought a rebound as memory shortages and Blackwell demand tightened supply: Lambda raised its H100 list price to US$3.29 in April 2026, Nebius reported a 15% increase after auctioning capacity, and new Nebius contracts carry annual value above US$20 million per MW. The sovereign-cloud variant, in which a national telecom or operator sells "Canadian-controlled" capacity to governments and regulated industries, is now visible in Bell's AI Fabric (a 300 MW Saskatchewan site, C$1.3 billion of extra 2026 capex, and a C$220 million three-year contract with BUZZ HPC to serve Cohere) and TELUS's Kamloops AI data centre.
Who pays for all this? Increasingly not the hyperscalers' balance sheets. The four largest plan about US$760 billion of capital spending in 2026, and they have pushed a further US$1.09 trillion of future lease commitments and roughly US$3 trillion of purchase commitments and unstarted leases off their balance sheets (Reuters and the Wall Street Journal, August 2026). The template is Meta's Hyperion campus: a US$27 billion joint venture in which Blue Owl funds own 80%, Meta owns 20%, leases the buildings from 2029 and backstops the lenders with US$28 billion of residual value guarantees. Around that core sits a market of specialist capital: the Microsoft-BlackRock-GIP-MGX partnership that set out in 2024 to raise US$30 billion of equity and US$100 billion with debt, and that bought Aligned Data Centers for about US$40 billion in 2025; Nvidia's August 2026 alliance with Apollo, BlackRock, Blackstone, Brookfield, Goldman Sachs and KKR to mobilise over US$500 billion; KKR's Helix venture with the Kuwait Investment Authority, Nvidia and Vistra; Brookfield's record fundraising and its US$5 billion Bloom Energy commitment; and Canadian pension capital, with CPP Investments taking 51% of atNorth for US$1.3 billion in September 2026. Debt has followed: data-centre CMBS of about US$4.5 billion in Q1 2025 alone, GPU-backed loans from CoreWeave (US$3.1 billion) to GMI Cloud (US$947 million), Nebius's first secured facility and US$5.75 billion of converts, and a global convertible market that Barclays says is 60% AI-related. JLL's estimate that 100 GW of new capacity needs US$3 trillion, including US$870 billion of debt, is the scale to keep in mind.
The risks are of four kinds, and each is now observable rather than hypothetical. Obsolescence: Meta extended the useful lives of most servers to 5.5 years from January 2025, which lowered nine-month 2025 depreciation by US$2.29 billion, and the IEA's four-to-six-year obsolescence window is the counterargument that Michael Burry made loudly in November 2025 before deregistering his fund and shorting Nvidia, Palantir, Oracle and Nebius. Utilisation and pricing: CoreWeave's Q2 2026 adjusted operating margin was 5% despite revenue doubling, and Meta's July 2026 plan to sell its surplus compute knocked neocloud shares. Concentration: Microsoft was 62% of CoreWeave's 2024 revenue, and neocloud backlogs (CoreWeave US$104 billion, Nebius up to US$27 billion from Meta alone) depend on a handful of counterparties. Circularity: Nvidia invests in OpenAI and Anthropic, guarantees up to US$108.5 billion of obligations and extends payment terms to customers who buy its chips; AMD issued OpenAI and Meta warrants for 160 million shares each tied to GPU purchases; Oracle's remaining performance obligations jumped from US$138 billion to US$638 billion in a year on contracts with OpenAI; and lenders have begun demanding wider spreads on data-centre bonds, as the CyrusOne and QTS CMBS deals showed in August 2026. Power-price and political risk complete the list: Alberta's all-in large-power price swung from 23.8 cents CAD in 2023 to 8.0 cents in 2025, Texas froze new data-centre grid connections in September 2026 after its queue reached 474 GW, and US midterm campaigns spent US$31 million on ads, 99% against data centres.
For Canada the numbers cut both ways. Montréal's large-power price of 5.83 cents CAD (about 4.1 US cents) is less than half Virginia's 9.45 US cents, worth about US$104 million a year on a 200 MW campus, and Alberta's 2025 price of 8.02 cents CAD is competitive too. But Alberta's queue of more than 16 GW of applications against a 12 GW peak, Hydro-Québec's rationing of large blocks, and the political questions raised at Alberta's August 2026 town halls show that speed to power and social licence, not tariffs, decide where the capital lands. Meta's 1 GW, C$13 billion-plus Sturgeon County campus with 250 MW from Capital Power, CoreWeave anchoring eStruxture's CAL-3 in Calgary, Goldman Sachs Alternatives buying QScale in Lévis, and Anthropic advertising a Canadian compute lead are the early evidence that Canada is on the map.
For a Sauder graduate the practical lesson is that this is an infrastructure business wrapped around a technology business. The roles that are opening are the ones that sit at the seams: financing structures that reconcile 30-year buildings with five-year chips; power procurement that turns a volatile pool price into a bankable contract; site selection and government relations that convert a queue position into a connection date; procurement that manages 18-month transformer lead times; and analytics that forecast load and utilisation. None of these require an engineering degree, but all of them require the ability to read a tariff sheet, a lease and a GPU spec sheet in the same afternoon, and to be honest about which numbers are contested.
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Data-centre construction cost (shell, power, cooling) | 10.7 (2025), 11.3 (2026 forecast), 7.7 (2020) | US$ million per MW | 2025-2026 | Global | JLL, 2026 Global Data Center Outlook, 5 Jan 2026, https://www.jll.com/en-us/insights/global-data-center-outlook |
| Technology fit-out for AI (servers, GPUs, networking) | up to 25 | US$ million per MW | 2026 | Global | JLL, 2026 Global Data Center Outlook |
| Average greenfield development cost, modern facility | 17.6 (up 21% versus prior guide) | US$ million per MW | 2026 | US-led global sample | Cushman & Wakefield, 2026 Data Center Development Cost Guide, Aug 2026, https://www.cushmanwakefield.com/en/united-states/insights/data-center-development-cost-guide |
| Construction plus installations, non-IT | 6,000 to over 10,000 | US$ per kW of IT load | 2024 | Emerging markets to advanced economies | IEA, Energy and AI, Apr 2025 (citing Turner & Townsend 2024), https://www.iea.org/reports/energy-and-ai |
| All-in cost of large AI campuses (facility plus chips), for example Meta Prometheus 562 MW at US$21.3 billion | about 37.9 | US$ million per MW | 2025 dollars, updated 1 Sep 2026 | US | Epoch AI, Frontier Data Centers hub, https://epoch.ai/data/data-centers |
| Share of servers in total cost of ownership of a 1 GW AI data centre | about 60 | % | May 2026 | Global | Epoch AI data insight, 14 May 2026, via https://epoch.ai/data/data-centers |
| Accelerated servers as share of global data-centre investment | 10 (2015) rising to 45 (2030) | % | 2015-2030 | Global | IEA, Energy and AI, Apr 2025 |
| Global annual data-centre investment | over 500 (2024), over 800 per year before 2030; 4,200 cumulative 2025-2030 | US$ billion | 2024-2030 | Global | IEA, Energy and AI, Apr 2025 |
| Neocloud capex intensity (Nebius 2026 plan) | 20-25 billion for 800-1,000 MW, about 20-31 | US$ million per MW | 2026 | Global | Nebius Q2 2026 results, 12 Aug 2026, via The Register, https://www.theregister.com/off-prem/2026/08/12/rent-a-gpu-outfit-nebius-promises-rapid-1-gw-powerup-plan-isnt-nebulous/5287086 |
| Useful life of IT equipment versus transformer | 4-6 years versus about 30 years | years | 2025 | Global | IEA, Energy and AI, Apr 2025 |
| Meta's estimated useful life of most servers and network assets | 5.5 (raised from prior estimate, effective 1 Jan 2025); nine-month 2025 depreciation lower by US$2.29 billion | years | 2025 | US | Meta 10-Q for Q3 2025, 30 Oct 2025, https://investor.atmeta.com |
| Weighted average power usage effectiveness (PUE) | 1.54 overall; 1.44 for sites of 20 MW and above; 15% of respondents at 1.3 or better | ratio | 2025 | Global survey | Uptime Institute Global Data Center Survey 2025, https://uptimeinstitute.com/resources/research-and-reports/uptime-institute-global-data-center-survey-results-2025 |
| Cooling share of a hyperscaler's energy use | 35-40 | % | 2025 | Global | Goldman Sachs Research, 4 Feb 2025, https://www.goldmansachs.com/insights/articles/ai-to-drive-165-increase-in-data-center-power-demand-by-2030 |
| Data-centre power demand | 55 GW (2025 estimate), 84 GW (2027), 122 GW (2030), a 165% rise versus 2023 | GW | 2025-2030 | Global | Goldman Sachs Research, 4 Feb 2025 |
| Grid investment needed for data centres | about 720 | US$ billion through 2030 | 2025 | Global | Goldman Sachs Research, 4 Feb 2025 |
| Hydro-Québec Rate L (large-power industrial, minimum 5,000 kW) | 15.027 per kW of billing demand per month plus 3.821 cents per kWh | CAD | effective 1 Apr 2026 | Quebec | Hydro-Québec, 2026 Electricity Rates, https://www.hydroquebec.com/data/documents-donnees/pdf/electricity-rates.pdf |
| Average all-in price, large-power customer (5,000 kW, 3.06 GWh per month), excluding taxes | Montréal 5.83; Winnipeg 6.00; Calgary 8.02; Vancouver 8.42; Edmonton 10.17; Toronto 12.80; Seattle 13.31; Houston 14.35; New York 22.90; Boston 28.19 | cents CAD per kWh | rates in effect 1 Apr 2025 | North American cities | Hydro-Québec, Comparison of Electricity Prices in Major North American Cities 2025, https://www.hydroquebec.com/data/documents-donnees/pdf/comparison-electricity-prices.pdf |
| Calgary large-power price history | 10.25 (2021), 13.16 (2022), 23.77 (2023), 10.46 (2024), 8.02 (2025) | cents CAD per kWh | 2021-2025 | Alberta | Hydro-Québec comparison 2025 |
| Alberta average pool price | 43.68 (2025), down 30.4% from 62.78 (2024), lowest in eight years | CAD per MWh | 2025 | Alberta | AESO, 2025 Annual Market Statistics, 13 Mar 2026, https://www.aeso.ca/market/market-and-system-reporting/annual-market-statistic-reports |
| Virginia industrial electricity price | 9.45 (2025 average of monthly values); 10.09 (Jan-Jun 2026 average); 9.31 (Jun 2026) | US cents per kWh | 2025-2026 | Virginia | EIA Electric Power Monthly, Table 5.6.A, https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_5_6_a |
| US industrial electricity price | 8.61 (2025 average); 9.17 (Jun 2026) | US cents per kWh | 2025-2026 | US | EIA Electric Power Monthly, Table 5.6.A |
| Metric | Value | Unit | Year | Region | Source |
|---|---|---|---|---|---|
| Average asking colocation rate, 250-500 kW requirements | 184.06, up 12.6% year on year | US$ per kW per month | H2 2024 | North America primary markets | CBRE, North America Data Center Trends H2 2024, 26 Feb 2025, https://www.cbre.com/insights/reports/north-america-data-center-trends-h2-2024 |
| Colocation pricing change | +2.5% for 250-500 kW; up to +19% for 10 MW-plus deals (Northern Virginia +13.8%, Silicon Valley +19%, Chicago +15.4%) | % | H1 2025 | North America | CBRE, North America Data Center Trends H1 2025, 8 Sep 2025, https://www.cbre.com/insights/reports/north-america-data-center-trends-h1-2025 |
| Vacancy and construction | vacancy 1.6%; 5,242.5 MW under construction, 74.3% preleased; supply 8,155 MW (+43.4% year on year) | MW, % | H1 2025 | North America primary markets | CBRE H1 2025 |
| Colocation pricing by market | Northern Virginia +15% year on year (vacancy 0.76%); Phoenix about 190; London 180-215; Singapore 310-470; Tokyo 190-355 | US$ per kW per month | Q1 2025 | Global | CBRE, Global Data Center Trends 2025, 24 Jun 2025, https://www.cbre.com/insights/reports/global-data-center-trends-2025 |
| Hyperscale take-or-pay lease (Applied Digital, 210 MW, 15-year base term, investment-grade tenant) | at least 5.2 billion over 15 years, about 347 million a year, about 138 per kW per month; 12.7 billion if 30-year renewals exercised | US$ | Jun 2026 | US | Sherwood News, 9 Jun 2026, https://sherwood.news/markets/applied-digital-leaps-on-5-2-billion-deal-with-undisclosed-us-hyperscaler/ |
| Digital Realty renewal rent growth | +25.4% cash, +32.0% GAAP; stabilised development yields 10%-plus; record bookings US$307 million annualised (129.8 MW) | % | Q2 2026 | Global | Digital Realty Q2 2026 results, 23 Jul 2026, https://www.globenewswire.com/news-release/2026/07/23/3332571/0/en/digital-realty-reports-second-quarter-2026-results.html |
| AI cloud contract value (Nebius, contracts signed Q2 2026) | above 20 million per MW per year (20-25 million for medium-term leases; 40-50 million for short-term leases up to six months) | US$ per MW per year | Aug 2026 | Global | Nebius Q2 2026 call, via The Register (12 Aug 2026) and Sina Finance (12 Aug 2026) |
| Nebius-Microsoft dedicated capacity contract | up to 17.4 billion over five years, with about 6.96 billion of upfront payments | US$ | Sep 2025 | New Jersey, US | Nebius 20-F for 2025, 30 Apr 2026, https://nebius.com/newsroom |
| Nebius-Meta contracts | 2.9 billion (Nov 2025); up to about 27 billion (Mar 2026: 12 billion of dedicated clusters plus up to 15 billion for unsold capacity) | US$ | 2025-2026 | Global | Nebius 20-F for 2025 |
| AWS on-demand list price, p5.48xlarge (8 x H100), US East | 98.32 to 55.04 per instance-hour (about 12.29 to 6.88 per GPU-hour), a 44% cut | US$ per hour | 5 Jun 2025 | US | SkyPilot catalog price history, https://github.com/skypilot-org/skypilot-catalog |
| Lambda on-demand list price, 1 x H100 PCIe | 1.99 (2023-24); 2.49 (Feb 2024 to Feb 2026); 2.86 (Feb 2026); 3.29 (Apr 2026 onward) | US$ per GPU-hour | 2023-2026 | US | SkyPilot catalog price history |
| Market H100 rental price, 51 providers | lowest 1.25; median about 2.45-2.50; Google Cloud 4.86; Azure 11.06 | US$ per GPU-hour | 2 Sep 2026 | Global | computeprices.com, https://computeprices.com/gpus/h100 |
| Market median on-demand price, single GPU | H100 2.69 (May 2026) to 2.99 (Aug-Sep 2026); H200 3.49 to 3.99; B200 5.83 to 6.23 | US$ per GPU-hour | May-Sep 2026 | Global | computeprices daily offers (97,155 observations from 25 May 2026), via Drillr data tables |
| Neocloud price change after capacity auction | +15% | % | Aug 2026 | Global | Nebius, via Benzinga, 13 Aug 2026 |
| CoreWeave revenue and backlog | Q2 2026 revenue 2.575 billion (versus 1.212 billion a year earlier); remaining performance obligations 103.7 billion at 30 Jun 2026; 2026 revenue guidance 12.4-13.2 billion; 2026 capex 35-39 billion; power in use above 1.85 GW by year-end | US$ | Aug 2026 | Global | CoreWeave 10-Q and 8-K, 11-12 Aug 2026, https://investors.coreweave.com |
| CoreWeave cash payback on GPU investments (company claim) | about 2.5 years including customer prepayments | years | Mar 2025 | Global | CoreWeave S-1/A, 20 Mar 2025 |
| Deal or metric | Value | Unit | Date | Source |
|---|---|---|---|---|
| Global AI Infrastructure Investment Partnership (BlackRock, GIP, Microsoft, MGX; Nvidia supporting) | 30 billion of equity sought; up to 100 billion with debt | US$ | 17 Sep 2024 | Microsoft news release, https://news.microsoft.com/2024/09/17/blackrock-global-infrastructure-partners-microsoft-and-mgx-launch-new-ai-partnership-to-invest-in-data-centers-and-supporting-power-infrastructure/ |
| Acquisition of Aligned Data Centers by GIP, the AI Infrastructure Partnership and MGX | about 40 billion; completed July 2026 with a further 5 billion of growth capital | US$ | Oct 2025 | Wikipedia, Global Infrastructure Partners, https://en.wikipedia.org/wiki/Global_Infrastructure_Partners |
| Blackstone acquisition of AirTrunk (3 GW-plus platform, Asia-Pacific) | 24 billion AUD (about 16 billion USD) | AUD | 2024 | Wikipedia, AirTrunk, https://en.wikipedia.org/wiki/AirTrunk |
| CPP Investments and Equinix acquisition of atNorth (Nordics) | 4 billion; CPP Investments 51% (1.3 billion), Equinix 34% (895 million), Partners Group 10% | US$ | 2 Sep 2026 | PR Newswire, https://www.prnewswire.com/news-releases/cpp-investments-and-equinix-complete-atnorth-acquisition-to-support-growth-of-leading-nordic-data-center-platform-302867672.html |
| Digital Realty purchase of Blackstone's interest in three Northern Virginia data centres | 3.5 billion (plus a 2.346 billion secondary share sale by Blackstone) | US$ | 29 Jun 2026 | GlobeNewswire, https://www.globenewswire.com/news-release/2026/06/29/3319286/0/en/Digital-Realty-Announces-Purchase-of-Blackstone-Interest-in-Three-Northern-Virginia-Data-Centers.html |
| Meta Hyperion joint venture (Louisiana) | about 27 billion of development cost; Meta 20% and Blue Owl funds 80%; Meta lease commitment 12.31 billion from 2029; residual value guarantees up to 28 billion; Meta maximum exposure 45.95 billion | US$ | Oct 2025 (10-K of 29 Jan 2026) | Meta 10-K FY2025, https://investor.atmeta.com |
| Meta data-centre project debt | 12.5 billion priced at a higher rate than a similar 2025 deal; BlackRock-led financing of about 12-14 billion | US$ | 24-28 Jul 2026 | Wall Street Journal, https://www.wsj.com/finance/the-price-to-finance-the-ai-data-center-boom-is-rising-just-ask-meta-7894d503 ; Financial Times, 24 Jul 2026 |
| Nvidia financing platforms with Apollo, BlackRock, Blackstone, Brookfield, Goldman Sachs and KKR | target of over 500 billion of third-party capital | US$ | 10 Aug 2026 | PYMNTS, https://www.pymnts.com/news/artificial-intelligence/2026/goldman-sachs-mobilizes-investors-for-nvidias-500-billion-ai-infrastructure-push/ |
| Nvidia agreements with AI cloud providers and guarantees | 36 billion of agreements; guarantees of up to 108.5 billion; equity holdings 95.6 billion | US$ | 26 Aug 2026 | Nvidia disclosures via AOL/Bloomberg summary, https://www.aol.com/articles/nvidia-looking-more-central-bank-213156000.html |
| Apollo and Blackstone debt package for Anthropic's chip capacity (Broadcom-backed) | 35 billion | US$ | 5 Jun 2026 | Bloomberg, https://www.bloomberg.com/news/articles/2026-06-05/apollo-wraps-up-35-billion-debt-to-buy-ai-chips-for-anthropic |
| KKR, Kuwait Investment Authority, Nvidia and Vistra launch Helix Digital Infrastructure | over 10 billion committed | US$ | 11 Jun 2026 | Company release via news index |
| Brookfield commitments | up to 5 billion for Bloom Energy fuel cells at AI data centres (3 Jun 2026); 605 million debt led by Brookfield for 5C Group AI campuses (10 Aug 2026); record fundraising year driven by AI and infrastructure (5 Aug 2026) | US$ | 2026 | Bloomberg, PR Newswire, https://www.prnewswire.com/news-releases/5c-secures-more-than-usd-1-4-billion-to-power-north-americas-ai-infrastructure-302847289.html |
| GPU-backed and neocloud debt | CoreWeave 3.1 billion GPU-backed loan (Jul 2026) and over 20 billion of 2026 financing; IREN 3.65 billion investment-grade GPU facility and 2.4 billion Blue Owl-led loan (Aug 2026); Lambda 1 billion (Aug 2026); GMI Cloud 947 million (Sep 2026); Nebius 775 million first secured facility (Jul 2026) and 5.75 billion convertible notes (Aug 2026) | US$ | 2026 | Company releases via news index; Nebius newsroom |
| Big Tech future lease commitments for data centres (Microsoft, Meta, Oracle, Amazon, Alphabet) | about 1.09 trillion | US$ | 4 Aug 2026 | Reuters, https://www.reuters.com/business/retail-consumer/ai-data-centre-race-builds-1-trillion-lease-burden-big-tech-2026-08-04/ |
| Off-balance-sheet AI obligations of nine tech companies | about 3 trillion (1.9 trillion purchase commitments plus 1.2 trillion of unstarted leases) | US$ | filings to Jun 2026 | Wall Street Journal analysis via Yahoo Finance, https://finance.yahoo.com/markets/stocks/articles/alphabet-meta-microsoft-hiding-3-135343885.html |
| Oracle remaining performance obligations | 638 billion at 31 May 2026 versus 138 billion a year earlier | US$ | Jun 2026 | Oracle 10-K FY2026, 22 Jun 2026 |
| AMD warrants to OpenAI and Meta (up to 160 million shares each at US$0.01, vesting with up to 6 GW of GPU deployments) | none vested as of 27 Jun 2026 | shares | Oct 2025 and Feb 2026 | AMD 10-K FY2025 and 10-Q Q2 2026 |
| Data-centre CMBS issuance | about 4.5 billion in Q1 2025; in Aug 2026 CyrusOne and QTS deals had to widen pricing as risk premiums rose | US$ | 2025-2026 | CBRE H1 2025; Bloomberg Law, 6 Aug 2026, https://news.bloomberglaw.com/capital-markets/cmbs-investors-push-back-against-ai-as-luddite-trade-spreads |
| Debt required for 100 GW of new capacity by 2030 | about 870 billion of a 3 trillion total | US$ | Jan 2026 | JLL 2026 Global Data Center Outlook |
| Global convertible bond issuance | 186.8 billion year to date (362 deals), about 60% AI-related | US$ | 1 Sep 2026 | Dealogic and Barclays via Axios, https://www.axios.com/2026/09/02/ai-nvidia-zero-bonds |
| Green financing example | AirTrunk JPY 191.6 billion (US$1.24 billion) green loan for TOK1 | JPY | Mar 2026 | Wikipedia, AirTrunk |
| Canadian bank syndicate on Brookfield Infrastructure preferred units (Scotiabank, BMO, CIBC, National Bank, RBC, TD) | 100 million | CAD | 20 Aug 2026 | GlobeNewswire, https://www.globenewswire.com/news-release/2026/08/20/3348425/0/en/brookfield-infrastructure-to-issue-100-million-of-preferred-units.html |
Purpose: show, transparently, how capex, power cost and revenue interact, and why location changes the answer. All figures are order-of-magnitude estimates from the sources above; they are not a business plan.
Assumptions
| Item | Assumption | Basis |
|---|---|---|
| Critical IT load | 200 MW | Comparable to Meta Prometheus (562 MW), CoreWeave Denton (262 MW) or Bell's 300 MW Saskatchewan site |
| Power usage effectiveness (PUE) | 1.30 | New high-latitude builds reach 1.3 or better (Uptime 2025); fleet average is 1.54 |
| Average IT utilisation | 85% of nameplate | Assumption; AI training and inference clusters run near-continuously |
| Average facility draw | 200 x 1.30 x 0.85 = 221 MW | Derived |
| Annual energy | 221 MW x 8,760 h = 1,936 GWh | Derived |
| Peak billing demand | 260 MW (200 x 1.30) | Derived, used for demand charges |
| Facility capex (shell, electrical, mechanical) | US$14 million per MW (range 11.3-17.6) = US$2.8 billion (range US$2.3-3.5 billion) | JLL 2026 (11.3) and Cushman 2026 (17.6) |
| IT fit-out (GPUs, servers, networking, storage) | US$25 million per MW = US$5.0 billion | JLL 2026 (up to 25); consistent with Epoch's about 37.9 all-in and Nebius's 20-31 per MW |
| Total all-in capex | about US$7.8 billion (about US$39 million per MW) | Derived |
| Electricity price, Montréal | 5.83 cents CAD = 4.06 US cents per kWh | Hydro-Québec 2025 comparison (large-power profile), C$1 = US$0.697 |
| Electricity price, Calgary | 8.02 cents CAD = 5.59 US cents per kWh | Hydro-Québec 2025 comparison; consistent with the 2025 pool price of C$43.68 per MWh plus transmission and other charges |
| Electricity price, Northern Virginia | 9.45 US cents per kWh (2025 industrial average); 10.09 cents in H1 2026 | EIA Table 5.6.A |
| Exchange rate | C$1 = US$0.697 | Rate used in the Hydro-Québec 2025 comparison (1 Apr 2025) |
Step 1: annual electricity cost = 1,936 GWh x price
| Scenario | Price (US cents per kWh) | Annual power cost (US$ million) | Versus Virginia |
|---|---|---|---|
| Quebec (Montréal area) | 4.06 | 79 | saves 104 per year |
| Alberta (Calgary area) | 5.59 | 108 | saves 75 per year |
| Northern Virginia | 9.45 (2025) | 183 | baseline |
| Northern Virginia at H1 2026 prices | 10.09 | 195 |
Cross-check for Quebec using the actual 2026 Rate L tariff (C$15.027 per kW per month on 260,000 kW plus 3.821 cents per kWh on 1,936 GWh): C$46.9 million plus C$74.0 million = C$120.9 million, which is 6.24 cents CAD per kWh all-in, or about US$84 million. The published comparison figure (5.83 cents) is for a smaller 5 MW profile, so the 2026 tariff-based number is the better estimate for a large campus. Either way Quebec power is roughly half the Virginia cost. The catch is availability: Hydro-Québec allocates blocks of capacity to large loads and Quebec has been rationing supply to data centres, so price is not the binding constraint.
Alberta caution: the same Hydro-Québec comparison shows Calgary's large-power price at 23.77 cents CAD in 2023 and 10.46 cents in 2024, so an Alberta campus must budget for price volatility and hedge (a power purchase agreement, or PPA, with a generator such as Capital Power's 250 MW, ten-year-plus supply deal with Meta is one answer). Alberta's 2025 pool price was the lowest in eight years.
Step 2: revenue under two business models
Model A, wholesale landlord (the developer builds the powered shell and turnkey halls; a hyperscaler or neocloud brings its own IT and pays for power). Rent benchmark: about US$138 per kW per month (Applied Digital's 15-year take-or-pay lease, June 2026). Revenue = 200,000 kW x US$138 x 12 = US$331 million a year. If landlord operating costs (staff, maintenance, insurance, property taxes) absorb about 15% of rent, net operating income is about US$281 million, a 10.0% yield on US$2.8 billion of facility capex, which matches the "10%-plus" stabilised yields Digital Realty reported for Q2 2026. Simple payback on the facility is about ten years. For the tenant, power (US$79-183 million) equals 24-55% of rent, so the tenant's total occupancy cost is 30-36% lower in Quebec than in Virginia; that is why hyperscalers and their site-selection teams treat the power price as a first-order variable.
Model B, AI cloud operator (the same company owns the halls and the GPUs and sells compute). Revenue benchmark: US$20 million per MW per year of contracted capacity (Nebius, Q2 2026; the range was 20-25 million). Revenue = 200 MW x US$20 million = US$4.0 billion a year. If the operator achieves an adjusted EBITDA margin near the 60% that CoreWeave reported in 2025, EBITDA is about US$2.4 billion, giving a simple payback on US$7.8 billion of about 3.3 years; CoreWeave's own S-1 claimed about 2.5 years including customer prepayments. In this model electricity is only 2-5% of revenue (US$79-195 million against US$4.0 billion); the dominant cost is depreciation of US$5.0 billion of IT over five years (US$1.0 billion a year) plus interest on debt. Sensitivity: if contract pricing at renewal falls to about US$12 million per MW (roughly what H100-era pricing of US$2.50-3.00 per GPU-hour implies at 80% utilisation), revenue drops to US$2.4 billion and EBITDA to about US$1.4 billion, barely covering depreciation and interest. The 44% AWS price cut of June 2025 and the 2026 price rebound show that both directions are plausible.
What the example teaches: (1) chips are two-thirds of the capital and wear out in four to six years, so the return depends on utilisation and on pricing at renewal, not on the building; (2) cheap Canadian power is worth about US$40-50 per kW per month to a tenant, a real but second-order edge for an AI cloud and a first-order edge for a landlord; (3) speed to power and certainty of supply, not price alone, decide where campuses land, which is why Alberta's queue (over 16 GW of applications) and Quebec's allocation rules matter as much as tariffs.
| Role family | What the work is | Example employers in Canada | Skills that matter | Evidence or posting source |
|---|---|---|---|---|
| Infrastructure and project finance | Structuring construction loans, take-or-pay leases, asset-backed securities (ABS), GPU-backed loans and equity for campuses; underwriting tenant credit | RBC Capital Markets, TD Securities, BMO, Scotiabank, CIBC, National Bank (all in the Aug 2026 Brookfield Infrastructure syndicate); Brookfield; CPP Investments (atNorth, 51% for US$1.3 billion, Sep 2026); pension and infrastructure funds | Project-finance modelling, credit analysis, lease and PPA structuring, understanding residual-value guarantees | Meta 10-K (Hyperion structure); Nvidia's US$500 billion platforms with six financiers (Aug 2026); Vantage's global CFO Scott Beasley (Kellogg MBA) oversaw asset-backed securitisations (Vantage leadership page) |
| Energy trading and power procurement | Buying power for campuses, hedging price risk, negotiating PPAs and large-load tariffs, managing demand-response and on-site generation | Capital Power, TransAlta, Emera, Fortis, ENMAX, hyperscalers' energy teams; OpenAI is hiring a power-trading lead (Bloomberg, 11 Aug 2026) | Electricity market literacy (pool prices, transmission tariffs, capacity), derivatives, contract negotiation | Capital Power 250 MW agreement with Meta (8 Jul 2026); AESO 2025 statistics (pool price volatility) |
| Real-estate development and site selection | Finding powered land, securing grid connections and permits, structuring land and lease deals | Vantage (Montreal I-III, Quebec City), eStruxture (15 sites, 130 MW-plus), QScale (Lévis, 142 MW), Digital Realty and Equinix (Toronto), Anthropic's "Canadian Compute Lead" | Real-estate finance, zoning and utility processes, negotiation with municipalities and utilities | BetaKit, 20 Aug 2026 (Anthropic postings); Cushman 2026 ranking (Toronto 8th primary Americas market, Montreal 6th secondary) |
| Construction and programme management | Delivering multi-hundred-million-dollar builds on time; managing contractors, commissioning, budgets | PCL, EllisDon, Ledcor (attended AESO's 2025 large-load session), Bird, engineering firms; operators' construction teams | Scheduling, cost control, risk management, contracts; enough technical fluency to speak with electrical and mechanical engineers | Cushman 2026 (costs up 21% per MW; labour shortages a key driver); Uptime 2025 (electrical and mechanical skills gaps above 30%) |
| Supply chain and procurement | Sourcing transformers, switchgear, generators, chillers, chips and servers with long lead times; managing tariffs and logistics | Operators, hyperscalers, Hypertec (hardware for Bell AI Fabric), Vertiv, Schneider Electric, ABB, Eaton | Category management, supplier finance, inventory and lead-time analytics | Cushman 2026 ("long equipment lead times"); Nvidia disclosed US$279 billion of future supply commitments (Aug 2026); memory price increases of 13-18% quarter on quarter (TrendForce, Aug 2026) |
| Sustainability and ESG reporting | Power sourcing, carbon and water reporting, green loans and bonds, community benefit agreements | Operators, utilities, pension funds; Anthropic's "Data Centre Community Engagement Manager" (Alberta) | Carbon accounting, green-finance frameworks, stakeholder engagement | AirTrunk US$1.24 billion green loan (Mar 2026); Alberta's four commitments and town halls (Aug 2026); Bell's Regina coal controversy (Aug 2026) |
| Policy and government relations | Working with provinces, utilities and regulators on tariffs, allocation of capacity, incentives and community consent | Provincial ministries, AESO, IESO, BC Hydro, Hydro-Québec, industry associations, operators' public-affairs teams | Regulatory literacy, policy analysis, coalition building | AESO large-load framework (16 GW-plus queue, Jun 2025); Alberta town halls (Aug 2026); Texas grid-connection freeze (Sep 2026) |
| Management consulting focused on data centres and energy | Market sizing, site strategy, cost modelling, due diligence for investors and utilities | McKinsey, BCG, Bain, Deloitte, PwC (Strategy& bought AI consultancy Datasparq, Aug 2026), Accenture, engineering consultancies | Financial modelling, structured problem solving, energy-system knowledge | JLL, CBRE and Cushman outlooks are consultancy-style products; IEA Energy and AI |
| Cloud and AI product management | Pricing and packaging GPU capacity, capacity planning, customer onboarding, service-level design | AWS, Microsoft, Google Cloud (Canadian regions), Nvidia, CoreWeave (anchor tenant at eStruxture CAL-3, May 2026), Nebius, Lambda, Cohere | Unit economics of compute, pricing strategy, technical literacy | Nebius asset-light partner model (Jul 2026); Nebius price increase after auction (Aug 2026) |
| Sales, partnerships and business development | Selling colocation, AI capacity and connectivity; structuring anchor-tenant and channel deals | TELUS (Kamloops AI data centre, C$15 billion BC plan to 2030), Bell AI Fabric (300 MW Saskatchewan; Cohere and BUZZ HPC C$220 million three-year contract), eStruxture, Vantage, Equinix, Digital Realty | Enterprise sales, contract structuring, ecosystem knowledge | Cointelegraph, 18 Jun 2026 (HIVE/BUZZ HPC-Bell-Cohere); Castanet, 15 Aug 2026 (TELUS Kamloops) |
| Utilities and system operators | Large-load interconnection, tariff design, demand forecasting, rate cases | Hydro-Québec, BC Hydro (C$90 million Vancouver substation, Aug 2026), IESO, AESO, SaskPower, Capital Power, TransAlta, Emera, Fortis | Load forecasting, regulatory economics, stakeholder management | AESO Phase 1 large-load integration session (Jun 2025); federal C$70 billion hydro, wind and transmission package (17 Aug 2026) |
| Data-centre operators: commercial, finance and operations management | Leasing, revenue management, FP&A, capital raising, operations leadership | eStruxture (new CFO David Schwartz, 31 Aug 2026), Vantage Canada (VP and GM Maxime Guévin, MBA HEC Montréal), QScale, Equinix, Digital Realty, Beacon AI Centers, Bitdeer (Fox Creek, Alberta) | Real-estate and infrastructure finance, operations, people leadership | Uptime 2025: operations management is the largest skills gap (39%); eStruxture and Vantage leadership pages |
| Analytics (capacity planning, demand forecasting, energy optimisation, GPU utilisation) | Forecasting load and demand, optimising cooling and power, tracking GPU utilisation and pricing | Utilities, operators, neoclouds, hyperscalers, consultancies; Robert Half 2026 Canada guide: data scientist C$104,250-156,750, AI engineer C$89,000-140,000 | Statistics, forecasting, optimisation, cloud and data tooling, domain knowledge of power systems | Uptime 2025 (PUE and energy use are the most tracked metrics; fewer than half track others); AESO and IESO planning outlooks |
| Investment and asset management | Sourcing and managing data-centre and digital-infrastructure investments in pension, sovereign and private funds | CPP Investments, La Caisse, OMERS, BCI, Brookfield, Blackstone, KKR, Apollo (Canadian offices), Goldman Sachs Alternatives (owner of QScale since May 2026) | Valuation, deal execution, portfolio and asset management | Table C deals; Brookfield record fundraising year (Aug 2026) |
Compensation and workforce indications (Canada unless noted): electricians average C$38.62 per hour (4,700 salaries, Indeed Canada, 17 Aug 2026; journeyperson about C$79,071 a year; Wood Buffalo, Alberta C$50.49 per hour); data-centre technicians average C$30.52 per hour (Toronto C$35.95; Indeed Canada, 12 Aug 2026); Robert Half's 2026 Canada Salary Guide lists data scientists at C$104,250-156,750, machine-learning developers C$85,000-165,000, AI architects C$109,250-164,500 and controllers C$114,750-172,500. In the US, specialised data-centre construction commands pay premiums of about 32%, with electricians in Texas and Virginia earning US$114,000-280,000 including overtime (IBTimes, 31 Jul 2026, citing OpenAI's White House submission that its build-out could require about one-fifth of America's skilled-trades workforce within five years). Uptime Institute (2025): 46% of operators cannot find qualified candidates, 37% struggle to retain staff, 25% lose staff to competitors, and 75% of operators have workforces that are 10% women or less. Meta funded a US$115 million construction "Workforce Academy" with Associated Builders and Contractors (Jun 2026) and a building-trades partnership (Aug 2026); Associated Builders and Contractors said construction job openings hit a near two-year high in July 2026 on data-centre and power demand.
Career stories (named individuals, from company biographies and reference sources; none are Sauder-specific)
Skills a business graduate needs to be useful in this sector: (1) infrastructure financial modelling (project cash flows, debt sizing, lease and take-or-pay structures, ABS and residual-value guarantees); (2) energy-market literacy (pool prices and capacity, transmission tariffs, PPAs, PUE and load factors, interconnection queues); (3) regulatory literacy (large-load rules at AESO, IESO, BC Hydro and Hydro-Québec, municipal permitting, tax incentives, community consent); (4) AI and compute literacy sufficient to talk to engineers (what a GPU-hour is, why memory and networking matter, why utilisation drives returns); (5) negotiation of PPAs, leases and supply contracts; (6) analytics for forecasting demand, utilisation and prices.
Everyone named in this chapter, in the order they appear. Portraits are freely licensed; initials mean no free portrait exists. Attribution for every photograph is in the portrait credits at the end of the chapter.



































| Name | Role | Organisation | Why they matter here | Source |
|---|---|---|---|---|
| Geoffrey Hinton | University Professor Emeritus | University of Toronto | AlexNet and the Toronto claim; Nobel Physics 2024; argues profit motive is not enough | cs.toronto.edu |
| Yoshua Bengio | Professor; co-president, LawZero; chair, International AI Safety Report | Universite de Montreal, Mila, LawZero | Made Montreal an AI city; his risk framing enters the rooms where Canadian rules are set | yoshuabengio.org |
| Richard S. Sutton | Professor; chief scientific advisor, Amii | University of Alberta, Amii | The Bitter Lesson is the intellectual case for ever-larger compute; anchors Alberta research | amii.ca |
| Yann LeCun | Co-founder, AMI Labs | Advanced Machine Intelligence Labs | Public dissenter from scaling; AMI has a Montreal office; left Meta November 2025 | Wikipedia |
| Ilya Sutskever | Chief executive officer | Safe Superintelligence | Three U of T degrees, AlexNet, then all the value created elsewhere | Wikipedia |
| Alex Krizhevsky | Current role not verified | Formerly Google, Dessa | Wrote the code that started the GPU era, then went quiet | Wikipedia |
| Aidan Gomez | Co-founder and chief executive | Cohere | The Canadian company federal sovereign compute policy is built around | Wikipedia |
| Raquel Urtasun | Founder and chief executive; professor | Waabi, University of Toronto | Largest venture raise in Canadian history; argues algorithms substitute for brute force | BetaKit |
| Doina Precup | Associate dean; head of Montreal office | McGill University, Google DeepMind, Mila | Shows what Canada actually gets from big tech: a research lab, not a data centre | Wikipedia |
| Jensen Huang | Founder, president and chief executive | Nvidia | Every Canadian project depends on his chip allocation; first $5 trillion company | Wikipedia |
| Sam Altman | Chief executive officer | OpenAI | Stargate set the 10 GW benchmark against which Canada's 5.5 GW is measured | OpenAI |
| Mark Zuckerberg | Chairman and chief executive | Meta Platforms | The C$13 billion, 1 GW Sturgeon County campus, gas-fired, and the bill fight it started | Meta |
| Satya Nadella | Chairman and chief executive | Microsoft | Sets the capital envelope behind C$19 billion of Canadian spending, 2023 to 2027 | Microsoft |
| Brad Smith | Vice chair and president | Microsoft | Signed the five-point Canadian digital sovereignty plan, including a litigation pledge | Microsoft |
| Andy Jassy | President and chief executive | Amazon | Built AWS; runs the incumbent Canadian cloud that sovereignty arguments target | Wikipedia |
| Sundar Pichai | Chief executive officer | Alphabet and Google | Owns the Canadian inheritance commercially; Project Suncatcher moves compute to orbit | Wikipedia |
| Elon Musk | Chief executive officer | SpaceX (absorbed xAI), Tesla | Colossus at 150 MW as a yardstick; declared terrestrial data centres a dead end | Wikipedia |
| Lisa Su | Chair and chief executive | AMD | The only credible second source of AI accelerators for Canadian sovereign compute | Wikipedia |
| Jeff Bezos | Executive chairman; founder | Amazon, Blue Origin | Forecast gigawatt orbital data centres, directly challenging Canada's physical pitch | GeekWire |
| Mark Carney | Prime Minister of Canada | Government of Canada | Energy superpower framing; AI for All strategy, 4 June 2026, about 5.5 GW projected | pm.gc.ca |
| Evan Solomon | Minister of AI and Digital Innovation | Government of Canada | The world's first national AI minister, in post since May 2025, owns sovereign compute | House of Commons |
| Tim Hodgson | Minister of Energy and Natural Resources | Government of Canada | Holds the power half of the file; grid doubling by 2050 with gas as a bridge | Wikipedia |
| Michael Sabia | Clerk of the Privy Council | Government of Canada | Ran Hydro-Quebec until July 2025, then took over the federal public service | Wikipedia |
| Danielle Smith | Premier of Alberta | Government of Alberta | Bring-your-own-power model; the digital refinery framing; delivered the Meta campus | alberta.ca |
| Nate Glubish | Minister of Technology and Innovation | Government of Alberta | The $100 billion target, and the minister who took it to four hostile town halls | alberta.ca |
| Stephen Lecce | Minister of Energy and Mines | Government of Ontario | Community benefits plus 100 per cent cost recovery before grid connection; Bill 40 | ontario.ca |
| David Eby | Premier of British Columbia | Government of BC | Public utility as an allocation tool rather than an open door | BC Gov News |
| Adrian Dix | Minister of Energy and Climate Solutions | Government of BC | Operates the 400 MW competitive allocation process launched 30 January 2026 | BC Gov News |
| Ravi Kahlon | Minister of Jobs and Economic Growth | Government of BC | Look West criteria decide which projects win scarce clean power | BC Gov News |
| Christine Frechette | Premier of Quebec | Government of Quebec | Ran the energy and economy file before becoming premier on 15 April 2026 | quebec.ca |
| Bernard Drainville | Minister of Economy, Innovation and Energy | Government of Quebec | Now decides how much Hydro-Quebec power goes to data centres, and to whom | quebec.ca |
| Scott Moe | Premier of Saskatchewan | Government of Saskatchewan | A small grid taking a 300 MW load, partly gas-fired, with an Indigenous partner | saskatchewan.ca |
| Wab Kinew | Premier of Manitoba | Government of Manitoba | The first Canadian first minister to refuse a hyperscale project, 4 June 2026 | Global News |
| Claudine Bouchard | President and chief executive | Hydro-Quebec | Controls the largest pool of clean firm power in Canada | Hydro-Quebec |
| Charlotte Mitha | President and chief executive | BC Hydro | Runs the only Canadian utility formally rationing power to data centres | BC Hydro |
| Aaron Engen | President and chief executive | AESO | 1,200 MW available to 2028 against more than 20,000 MW proposed | AESO |
| Jason Fitzsimmons | President and chief executive | IESO | Must turn Ontario's new conditions into an actual connection queue | IESO |
| Kevin O'Leary | Founder and chairman | O'Leary Ventures | Wonder Valley: $70 billion, 7.5 GW announced, construction not before late 2028 | Wikipedia |
| Victor Dodig | President and chief executive | TELUS | Took over 1 July 2026; a banker now running a national compute strategy | TELUS |
| Darren Entwistle | Chief executive officer emeritus | TELUS | Built the sovereign AI factory strategy; retired 30 June 2026 after 26 years | TELUS |
| Mirko Bibic | President and chief executive | BCE and Bell Canada | Six announced AI data centres plus the 300 MW Saskatchewan project | BCE |
| Bruce Flatt | Chief executive, Brookfield Corporation | Brookfield | Where Canadian capital meets global AI infrastructure as an owner, not a host | Wikipedia |
| Avik Dey | President and chief executive | Capital Power | Genesee is one of the few Alberta sites that can actually host a hyperscale load | Capital Power |
| Joel Hunter | President and chief executive | TransAlta | Holds part of the scarce Alberta large-load capacity to 2028 | TransAlta |
| Todd Coleman | Founder, president and chief executive | eStruxture Data Centers | The largest Canadian-owned operator, and the domestic sovereignty alternative | eStruxture |
| Shawn Longman | Chief | George Gordon First Nation | Named Indigenous partner in Canada's largest purpose-built AI data centre | paNOW |
| Isaac Laboucan-Avirom | Chief | Woodland Cree First Nation | 51 per cent Indigenous equity, not benefit sharing, in an Alberta project | Indigenous Energy Monitor |
| Tobi Lutke | Chief executive officer | Shopify | Demand side: whether Canada will consume the compute it wants to host | Wikipedia |
| Crystal Kissel | Former Reeve, Rocky View County | Rocky View County | Presided over the first significant municipal refusal, 9 September 2025 | Rocky View County |
| David Pickup | Director of Electricity | Pembina Institute | Footing the Bill: $270 to $460 a year on a typical Alberta household | Pembina |
| Blake Shaffer | Associate professor; co-lead, Electricity Centre | University of Calgary | 20,000 MW proposed, and the claim it would double Alberta power emissions | blakeshaffer.ca |
| Rick Smith | President | Canadian Climate Institute | Occupies the middle ground: integrate data centres, do not just refuse them | climateinstitute.ca |
Geoffrey Hinton is University Professor Emeritus at the University of Toronto, where he has held an appointment since 1987. He is British-Canadian, shared the 2018 Turing Award with Yoshua Bengio and Yann LeCun, and won the 2024 Nobel Prize in Physics with John Hopfield. The 2012 AlexNet result that started the GPU era came out of his lab, and the three-person company he formed with Alex Krizhevsky and Ilya Sutskever was bought by Google in 2013. Since resigning from Google in May 2023 to speak freely about AI risk, he has argued that leaving the field to the profit motive of large companies will not be sufficient, which is the precise tension Canada faces as it courts hyperscaler capital.
Yoshua Bengio is a professor at the Universite de Montreal, founder and scientific advisor of Mila, co-president and scientific director of LawZero, and chair of the International AI Safety Report. He is the reason Montreal is an AI city and, indirectly, the reason Quebec's cheap hydro power became an AI story. The second International AI Safety Report, published on 6 February 2026, drew on more than 100 experts with 29 nations plus the UN, OECD and EU nominating panel members, so his framing of risk travels straight into the policy rooms where data-centre rules get written. LawZero, launched in Montreal in June 2025 with funding that includes the Canadian government, puts a safety institution physically inside the country that is trying to sell compute.
Richard S. Sutton is a professor of computing science at the University of Alberta, chief scientific advisor and fellow at Amii, a Canada CIFAR AI Chair, and a research scientist at Keen Technologies. He became a Canadian citizen in 2015 and renounced his US citizenship in 2017. He and Andrew Barto were named 2024 Turing Award recipients in March 2025 for the foundations of reinforcement learning. His 2019 essay The Bitter Lesson, arguing that general methods leveraging computation win by a large margin, is the single most-quoted intellectual justification for building ever-larger compute, which puts him in an awkward relationship to the Alberta build-out happening around him.
Yann LeCun left Meta in November 2025 after twelve years as chief AI scientist and co-founded Advanced Machine Intelligence (AMI) Labs with Alexandre LeBrun. AMI announced a $1.03 billion seed round at a $3.5 billion pre-money valuation on 10 March 2026, with a Paris headquarters and offices in New York, Montreal and Singapore. He matters to Canada twice: he is the most senior public dissenter from the view that scaling language models leads to real intelligence, which directly challenges the demand forecasts behind gigawatt campuses, and his new company is recruiting from the Montreal talent pool while making that argument.
Ilya Sutskever is chief executive of Safe Superintelligence Inc., a role he took after co-founder Daniel Gross left for Meta in mid 2025. He holds Israeli and Canadian citizenship and took a BSc, MSc and PhD at the University of Toronto between 2005 and 2013, receiving an honorary doctorate there in 2025. He is the clearest single illustration of Canada's export problem: AlexNet, then OpenAI, then a company valued at $32 billion in March 2025 with Nvidia announcing a $5 billion investment in July 2026, none of it in Canada.
Alex Krizhevsky is the first author of the AlexNet paper, the result that made GPU training standard and set this entire build-out in motion. He completed his PhD at the University of Toronto under Hinton, sold DNNresearch to Google in 2013, and left Google in September 2017 to join the Toronto startup Dessa. His current role could not be verified from any source, and no freely licensed portrait of him exists. For teaching purposes that is the point: the person whose code triggered hundreds of billions of dollars of capital spending is invisible in every announcement.
Aidan Gomez is co-founder and chief executive of Cohere, and co-authored Attention Is All You Need in 2017 as a 20-year-old Google Brain intern. He is British-Canadian, with a University of Toronto bachelor's degree and an Oxford PhD completed in 2024. Cohere is the company federal sovereign compute policy is effectively built around: it received federal backing for a multibillion-dollar Canadian data centre, Microsoft agreed in December 2025 to integrate Cohere's models into its services as part of its Canadian sovereignty plan, and Bell partnered with it on infrastructure. Cohere's acquisition of Germany's Aleph Alpha in April 2026 created a combined entity valued at around $20 billion.
Raquel Urtasun is founder and chief executive of Waabi and a professor at the University of Toronto. She is Spanish-Canadian, born in Pamplona and resident in Canada since 2014, and was elected a Fellow of the Royal Society in 2026. Waabi's January 2026 round of $750 million US, plus up to $250 million more from Uber, was described by Urtasun as the largest fundraise in Canadian history. Her technical argument, that simulation and better algorithms substitute for brute-force data collection, is a live counterweight to the assumption that AI progress requires all the gigawatts being planned.
Doina Precup is associate dean of research in McGill's faculty of science, a Canada Research Chair in machine learning, head of Google DeepMind's Montreal office since 2017, and a core academic member of Mila. She is the working example of what Canada actually gets from a hyperscaler that is not building here: a research lab employing researchers rather than a facility consuming gigawatts. She is also the most senior woman in the Canadian AI research establishment, which is worth noticing against the composition of the rest of this list.
Jensen Huang is founder, president and chief executive of Nvidia, which he incorporated on 5 April 1993 and which became the first company to exceed a $5 trillion market capitalisation in October 2025. Nothing in the Canadian build-out happens without his chips: Telus's Rimouski AI factory, Bell's projects and Cohere's compute all depend on Nvidia allocation and Nvidia pricing. His sovereign AI pitch, that every country should own its own compute, is now repeated almost verbatim by Canadian ministers.
Sam Altman runs OpenAI and promotes Stargate, announced at the White House on 21 January 2025 with SoftBank and Oracle and targeting 10 gigawatts in the United States by 2029. That is the benchmark against which Canada's own AI for All strategy, projecting about 5.5 gigawatts for the whole country, has to be read. In February 2026 OpenAI launched OpenAI for Countries, offering governments an equity stake in national Stargate projects in exchange for permitting, grid access and co-investment, which is exactly the kind of deal Canadian governments will be asked to weigh.
Mark Zuckerberg is behind the single largest private capital commitment in Canadian data-centre history. Meta broke ground in July 2026 on a campus in Sturgeon County, Alberta, worth more than C$13 billion and roughly one gigawatt, its first in Canada, its largest outside the United States, and powered by a new natural gas plant. Meta has promised $60 million of local infrastructure spending and at least $250 million a year for Alberta. Against Meta's 2026 capital-expenditure budget of roughly $145 billion the project is modest; against Alberta's grid it is transformative.
Satya Nadella sets Microsoft's capital envelope. Microsoft already runs Azure Canada Central and Canada East, and in December 2025 committed C$7.5 billion over two years inside a C$19 billion total for 2023 to 2027, including new capacity near Quebec City, with capacity coming online from the second half of 2026. Microsoft chose to compete in Canada on sovereignty guarantees rather than on price, which is the more interesting strategic fact.
Brad Smith, Microsoft's vice chair and president, is the executive who actually wrote and signed those commitments. His 9 December 2025 post called the announcement the most important commitment in Microsoft Canada's history and set out a five-point digital sovereignty plan: an Ottawa threat intelligence hub, in-country Copilot data processing from 2026, confidential computing and Azure Key Vault in Canadian regions, integration of Cohere's Canadian models, and a pledge to pursue every available legal and diplomatic avenue including litigation if Microsoft were ordered to suspend Canadian cloud services. That last item is the most concrete corporate answer yet to Canadian fears of US extraterritorial reach.
Andy Jassy is president and chief executive of Amazon and the person who built AWS before taking the top job in July 2021. AWS runs Canadian regions in Montreal and Calgary and is the incumbent against which every sovereign-cloud argument is made. Whether Amazon matches Microsoft's Canadian sovereignty commitments is an open question and a good one for students to track.
Sundar Pichai runs Alphabet and Google, which owns the Canadian AI inheritance commercially: it bought Hinton's DNNresearch in 2013 and runs the DeepMind Montreal office Doina Precup leads. Project Suncatcher, announced in late 2025, plans solar-powered satellite constellations carrying TPUs, with two prototype satellites to launch with Planet Labs by early 2027. If orbital compute works even partially, the value of Canadian cold air and clean firm power falls.
Elon Musk built Colossus in Memphis, fully operational from December 2024 at about 150 megawatts peak, then moved decisively off-planet. SpaceX acquired xAI on 2 February 2026 in an all-stock deal valuing xAI at $250 billion and SpaceX at $1 trillion, folded it in as SpaceXAI by July 2026, and filed with the FCC for a constellation of up to one million solar-powered satellites. He also holds Canadian citizenship through his mother and briefly attended Queen's University, which makes him an uncomfortable footnote in any Canadian talent-retention argument.
Lisa Su is chair and chief executive of AMD, and the answer to the question of whether there is a second source. Every Canadian sovereign compute plan is exposed to Nvidia allocation and pricing, and AMD's Instinct accelerators are the main hedge. With Huang she is a reminder that the physical layer of the AI economy is controlled by a handful of firms, none of them Canadian.
Jeff Bezos gave the orbital thesis its highest-profile endorsement at Italian Tech Week in Turin in October 2025, forecasting gigawatt data centres in orbit within ten to twenty years and arguing that constant solar power and no weather will let space beat the cost of terrestrial data centres within a couple of decades. That is a direct challenge to the Canadian pitch, which rests on physical geography.
Mark Carney has been Prime Minister since March 2025. His government launched AI for All, the national AI strategy, on 4 June 2026, built on trust, opportunity and sovereignty, and projecting around 5.5 gigawatts of Canadian AI compute demand. His energy superpower framing is what allows gas-fired data centres in Alberta to be presented as nation building, and reporting through 2026 traced federal permissiveness on gas-powered data centres in part to Alberta industry lobbying. He is the person who has to reconcile the emissions target with the compute pitch, and that reconciliation has not yet been made in public.
Evan Solomon is Minister of Artificial Intelligence and Digital Innovation and Minister responsible for the Federal Economic Development Agency for Southern Ontario, sworn in on 13 May 2025 as the world's first national AI minister and confirmed still in post through mid 2026. He owns the sovereign compute file: the Canadian Sovereign AI Compute Strategy, the AI Sovereign Compute Infrastructure Program, federal money behind Cohere's data centre, and the May 2026 Telus announcement of three British Columbia sites. He is also a first-time MP running a new department, which is itself a governance risk.
Tim Hodgson is Minister of Energy and Natural Resources, elected in April 2025 and sworn in that May. He holds the half of the file Solomon does not: Canada's AI ambitions are a power problem before they are a chip problem, and he is the minister arguing Canada must roughly double its grid by 2050 with natural gas as a bridging fuel. The Canada-Alberta memorandum of understanding explicitly includes AI data-centre infrastructure, which is where federal climate policy and provincial gas generation meet. No freely licensed portrait of him exists.
Michael Sabia became the 26th Clerk of the Privy Council on 7 July 2025, three days after leaving Hydro-Quebec, where he had been chief executive since May 2023. He is the hinge between Canada's electricity system and its federal government: he ran the largest clean-power utility in the country exactly when Quebec was deciding how much power to sell to data centres, then moved to run the federal public service. There is no free portrait of him, which is a small illustration of how invisible senior officials are next to the executives they negotiate with.
Danielle Smith has been Premier of Alberta since October 2022 and is the most aggressive provincial promoter of AI data centres in Canada. Her bring-your-own-power model, under which developers build their own generation and can sell surplus into the grid, is what made Alberta the front-runner and delivered the Meta campus. She has framed a data centre as a digital refinery converting natural gas into electricity, then compute, then intelligence. At an August 2026 virtual town hall, responding to the Pembina analysis, she said Albertans who want certainty on their bills can lock in at a price, which critics read as an admission that bills are at risk.
Nate Glubish has been Alberta's Minister of Technology and Innovation since 24 October 2022 and is the author of the ambition to see $100 billion of AI data centre construction under way within five years. In August 2026 he took that pitch to four town halls in Lacombe, Sturgeon County, Redwater and Ponoka, and was booed, jeered and sworn at. His response, that all he can offer is to do the best of his ability to ensure development is done responsibly, is markedly thinner than the strategy he is defending, and that gap is the story.
Stephen Lecce has been Ontario's Minister of Energy and Mines since 6 June 2024. Ontario has taken the opposite posture to Alberta: in July 2026 Lecce announced that AI data centres seeking a grid connection must demonstrate community benefits, pay 100 per cent of their energy costs, and satisfy broader provincial priorities, with Bill 40 giving the government power to set those prerequisites. The rules did not yet exist when he announced them, which is the gap critics point to, and observers note that even full cost recovery may not stop prices rising for everyone.
David Eby has been Premier of British Columbia since November 2022. He told the Vancouver Web Summit in May 2026 that he is an optimist about AI having seen both the opportunity and the threat, and that BC Hydro being a public utility gives the province a huge advantage. British Columbia is the test of whether a public utility can allocate scarce clean power deliberately rather than first come, first served.
Adrian Dix, Minister of Energy and Climate Solutions, is the official who actually operates that model. The 30 January 2026 release he fronted launched a competitive process capped at 100 MW for conventional data centres and 300 MW for AI data centres over the two years from 1 February 2026, with successful applicants to be notified in September 2026, and exempted traditional industries such as mining, forestry and LNG. Ravi Kahlon, Minister of Jobs and Economic Growth, supplies the selection criteria through the Look West strategy, which prioritises projects delivering the greatest economic and environmental benefits. Between them, Dix and Kahlon run the most explicit rationing scheme in the country.
Christine Frechette became the 33rd Premier of Quebec on 15 April 2026, after winning the Coalition Avenir Quebec leadership on 12 April with 57.9 per cent of the vote against Bernard Drainville. She is the second woman to lead Quebec. Uniquely among Canadian first ministers she ran the data-centre file directly before taking the top job, as Minister of Economy, Innovation and Energy from 5 September 2024 to 26 January 2026, the period when Hydro-Quebec set a data-centre rate and Quebec debated how much of its power to sell and to whom. Her open question, whether Quebec should host foreign-owned data centres or insist on Quebec ownership, is the sovereignty debate in its sharpest provincial form.
Bernard Drainville was appointed Minister of Economy, Innovation and Energy and Minister responsible for the Maritime Strategy in Frechette's 29-member cabinet on 21 April 2026, making him the superminister who inherited exactly the file she left. Quebec has the cheapest large-scale clean firm power in North America and the most explicit political anxiety about selling it to foreign technology companies, so his allocation and pricing decisions set the ceiling on Quebec's participation.
Scott Moe has been Premier of Saskatchewan since February 2018. Saskatchewan is the quiet case: the Bell facility in the RM of Sherwood near Regina is roughly $1.7 billion and 300 megawatts, about five per cent of the province's current generating capacity, will run partly on natural gas through SaskPower and TransGas, and carries an Indigenous partnership with George Gordon First Nation. It shows that a small grid can attract a very large load, and that the Indigenous participation question arrives with it.
Wab Kinew has been Premier of Manitoba since October 2023 and is the first Canadian first minister to publicly refuse a hyperscale AI data centre. On 4 June 2026 he rejected a project on 142 hectares near Ile des Chenes southeast of Winnipeg, proposed by the US company Jet.AI and British Columbia's Consensus Core Technologies and powered largely by gas turbines. He said there was a big threat to the environment and not much benefit to the economy, and that Manitobans want AI to serve them rather than the reverse. Manitoba has clean hydro power and said no anyway, which is the most important fact in the Canadian debate.
Claudine Bouchard became president and chief executive of Hydro-Quebec on 5 July 2025, after 25 years at the utility and two years as chief operating and infrastructure officer. She controls the largest pool of clean firm power in Canada and therefore the most sought-after grid connection in the country, and must balance data-centre sales against domestic electrification and a very large capital plan. She succeeded Michael Sabia, who left to run the federal public service, which shows how tightly this utility is tied to national policy.
Charlotte Mitha is president and chief executive of BC Hydro, having been named in May 2025 as Chris O'Riley retired after 35 years. Anyone still citing O'Riley as BC Hydro's chief executive is working from stale information. Mitha operates the mechanism that makes British Columbia different, and her January 2026 comments stressed that clarity for customers already in the interconnection queue is essential for maintaining confidence, which is the practical problem every Canadian utility now faces.
Aaron Engen has been president and chief executive of the Alberta Electric System Operator since 1 August 2024, after 25 years in investment banking, most recently as vice chair of investment and corporate banking at BMO Capital Markets. His organisation issues the numbers that decide whether Alberta's ambitions are physically possible: 1,200 MW of large-load capacity allowed to 2028, already claimed by TransAlta and a Pembina Pipeline and Kineticor joint venture, against more than 20,000 MW of proposed projects. That gap is the single most important fact in the Alberta story.
Jason Fitzsimmons is listed as president and chief executive of the Independent Electricity System Operator as of September 2026. Lesley Gallinger led the IESO from 2021, oversaw the largest resource procurement in Canadian history, and the board chair announced on 11 June 2026 that she would step down effective 1 August 2026, with a transition plan under way but no successor named at that time. The IESO now has to turn Lecce's community-benefit and full-cost conditions into a working connection queue for the largest electricity market in Canada.
Kevin O'Leary is promoting Wonder Valley, a proposed $70 billion, 7.5 gigawatt campus in the Greenview Industrial Gateway about 40 kilometres south of Grande Prairie, in partnership with the Municipal District of Greenview. Announced in December 2024 for a 2027 first phase, it has slipped: 2026 is the permitting year and construction is now hoped for late 2028. Alberta confirmed in April 2026 that no provincial environmental impact assessment would be required, Sturgeon Lake Cree Nation has objected, and on 2 September 2026 reporting alleged Greenview did not disclose an agreement during public hearings. In April 2026 he announced a separate 40,000 acre project in Box Elder County, Utah, which raises a reasonable question about focus. Wonder Valley is the best available case study in the distance between an announcement and a building.
Victor Dodig became TELUS president and chief executive on 1 July 2026, having been named chief executive designate on 12 February 2026 and joining full time on 1 May. He inherits a genuinely distinctive Canadian strategy. Darren Entwistle, who ran TELUS for 26 years and retired on 30 June 2026 with the title chief executive officer emeritus and an advisory role to Dodig until 30 April 2027, decided that a Canadian telecommunications company should own AI compute rather than rent it. TELUS opened Canada's first fully sovereign AI factory in Rimouski, Quebec in September 2025, reported as the country's fastest supercomputer on the TOP500 list and fully sold out; Kamloops follows in 2026, Vancouver's Mount Pleasant at the end of 2026, scaling past 150 MW by 2032. Whether a banker sustains a telecoms infrastructure bet is now a live question.
Mirko Bibic has been president and chief executive of BCE and Bell Canada since January 2020 and is confirmed in post on BCE's own leadership page in 2026. Bell announced six Canadian AI data centres in May 2025, partnered with Cohere in July 2025, and in March 2026 announced the roughly $1.7 billion, 300 MW Saskatchewan facility with George Gordon First Nation. Bell and TELUS competing directly on AI infrastructure is a structural change in how Canadian telecommunications capital gets deployed. No free portrait of Bibic exists on Wikimedia Commons.
Bruce Flatt is chief executive of Brookfield Corporation and chair of Brookfield Asset Management. He was born in Winnipeg in 1965, joined Brookfield in 1990, and became chief executive of the whole organisation in 2002. In February 2026 he handed the BAM chief executive role to Connor Teskey while keeping the chair and the Brookfield Corporation role, so anyone describing him as BAM's chief executive is out of date. Brookfield is where Canadian capital meets the global data-centre boom as an owner rather than a host, through renewable power agreements, data-centre platforms and AI infrastructure vehicles.
Avik Dey is president and chief executive of Capital Power and Joel Hunter is president and chief executive of TransAlta, and between them they control much of the Alberta generation that any hyperscale project needs. Dey has described the Genesee station west of Edmonton as probably one of the most attractive generation sites anywhere in North America, and told analysts in March 2026 that the pace of announcements has not matched market expectations, which is the most candid public statement any Canadian generator has made about how slowly these deals close. Hunter succeeded John Kousinioris, who retired effective 30 April 2026, so TransAlta changed leadership in the middle of the most consequential capacity allocation in its history.
Todd Coleman is founder, president, chief executive and board chair of eStruxture Data Centers, the largest Canadian-owned data-centre operator, founded in Montreal in 2017. He is the most direct test of whether sovereign compute can be supplied by a Canadian company rather than through commitments extracted from Microsoft or Amazon.
Shawn Longman is Chief of George Gordon First Nation, which signed a partnership with Bell covering Indigenous procurement participation and workforce development on the 300 MW facility near Regina, announced at the University of Regina on 16 March 2026. The project is projected to generate $12 billion of economic value for Saskatchewan, 80 full-time jobs, around 750 spinoff jobs and about 800 construction jobs, with construction starting in spring 2026 and operations in the first half of 2027. Isaac Laboucan-Avirom is Chief of Woodland Cree First Nation, which holds a 51 per cent stake in the Mihta Askiy data centre in northwestern Alberta with Sovereign Digital Infrastructure. That is equity ownership rather than benefit sharing, and it is a different and more consequential model. Neither leader has a freely licensed portrait.
Tobi Lutke is included on the demand side rather than the supply side. Shopify does not build data centres, but his 2025 internal memo requiring teams to justify why AI cannot do a job before hiring for it made Shopify the most-cited Canadian example of AI-first operations. Whether Canadian firms actually consume the compute Canada wants to host is a real question, and he is the closest thing to a national indicator of it.
Crystal Kissel was Reeve of Rocky View County when its council voted six to one on 9 September 2025 against the Kineticor Area Structure Plan, a roughly 448 hectare data-centre campus in the county's northeast quadrant with potential on-site natural gas generation. The public hearing ran more than ten hours, with over 50 residents speaking against and four in favour. She said the proposed plan did not align with the community's vision or with that of future generations who want to continue farming. She then lost her Division 3 seat to Alison Whiting in the October 2025 municipal election, and Sunny Samra is now reeve, so she is a historical rather than a current actor. The refusal stands as the template for local opposition across Alberta, and the fact that the reeve who led it was defeated weeks later is itself worth discussing.
David Pickup, director of electricity at the Pembina Institute, produced the most consequential piece of Canadian civil society analysis in this debate. Footing the Bill, published on 26 August 2026, estimated that Meta's Sturgeon County data centre could add $270 to $460 a year to a typical Albertan's electricity bill from 2027 to 2031, a 15 to 25 per cent increase over five years against average household electricity spending of about $1,700 in 2025, even after a possible 6 per cent reduction on the transmission portion. He noted that Albertans already pay some of the highest and most volatile electricity rates in the country. Danielle Smith responded to the report directly at a town hall the following day.
Blake Shaffer is an associate professor at the University of Calgary and co-lead, with Sara Hastings-Simon, of the new UCalgary Electricity Centre. He supplied the two numbers that govern the Alberta debate: 33 proposed provincial projects drawing more than 20,000 megawatts in total, and the estimate that building all of them would roughly double Alberta's electricity greenhouse gas emissions. He is not a straightforward opponent. He frames the cost question as a numerator and denominator problem, arguing that a data centre adds system costs but also adds demand across which fixed costs are spread, and that flexible data centres able to shift when they draw power could actually lower average costs. That nuance makes him the most useful single voice for a teaching case.
Rick Smith has been president of the Canadian Climate Institute since 2021. The Institute has produced the most sustained Canadian policy work on integrating AI data centres into electricity grids, including its March 2025 analysis of how to do it well and its May 2026 argument that Canada's AI and electricity strategies can and should be mutually reinforcing. Smith leads the organisation trying to occupy the middle ground between build-at-any-cost and outright refusal, which is where most Canadian policy will probably end up.
Every image below is a freely licensed file from Wikimedia Commons, downloaded at roughly 500 pixels wide using the Wikimedia thumbnail endpoint with a descriptive User-Agent, and verified as a real JPEG over 5 KB. No press photographs, agency images, corporate headshots or LinkedIn photos were used. CC BY and CC BY-SA files require attribution in the form given here; CC BY-SA additionally requires that any adapted version be shared under the same licence. Public domain files require no attribution but the credit is given anyway as good practice.
| Name | File | Licence | Author | Source page |
|---|---|---|---|---|
| Yoshua Bengio | bengio-yoshua.jpg | CC BY-SA 4.0 | Xuthoria (2025) | Commons |
| Jeff Bezos | bezos-jeff.jpg | Public domain (US federal) | SECWAR (2026) | Commons |
| Claudine Bouchard | bouchard-claudine.jpg | CC BY-SA 4.0 | Hydro Quebec (2025) | Commons |
| Mark Carney | carney-mark.jpg | CC BY-SA 4.0 | Lea-Kim (2025) | Commons |
| Adrian Dix | dix-adrian.jpg | CC BY 2.0 | BC NDP (2024) | Commons |
| Bernard Drainville | drainville-bernard.jpg | CC BY 3.0 | TVA Nouvelles (2024) | Commons |
| David Eby | eby-david.jpg | CC BY 2.0 | BC NDP (2024) | Commons |
| Bruce Flatt | flatt-bruce.jpg | CC BY-SA 4.0 | Todd France (2017) | Commons |
| Christine Frechette | frechette-christine.jpg | CC BY 3.0 | TVA Nouvelles (2024) | Commons |
| Nate Glubish | glubish-nate.jpg | CC BY-SA 4.0 | Ribbet32 (2017) | Commons |
| Aidan Gomez | gomez-aidan.jpg | CC BY-SA 4.0 | Gabriel Hutchinson (2025) | Commons |
| Geoffrey Hinton | hinton-geoffrey.jpg | CC BY-SA 4.0 | Cmichel67 (2026) | Commons |
| Jensen Huang | huang-jensen.jpg | Public domain (US federal) | The White House (2025) | Commons |
| Andy Jassy | jassy-andy.jpg | CC BY-SA 4.0 | Lisi Mezistrano Wolf (2021) | Commons |
| Ravi Kahlon | kahlon-ravi.jpg | CC BY 2.0 | BC NDP (2024) | Commons |
| Wab Kinew | kinew-wab.jpg | Public domain | Office of Governor Tim Walz and Lt. Governor Peggy Flanagan (2024) | Commons |
| Stephen Lecce | lecce-stephen.jpg | CC BY 2.0 | Taymaz Valley (2022) | Commons |
| Yann LeCun | lecun-yann.jpg | CC BY-SA 2.0 | Jeremy Barande, Ecole polytechnique (2024) | Commons |
| Tobi Lutke | lutke-tobi.jpg | CC BY-SA 4.0 | Benjamin Forrest (2019) | Commons |
| Scott Moe | moe-scott.jpg | Public domain (US federal) | Office of the EPA Administrator (2019) | Commons |
| Elon Musk | musk-elon.jpg | CC BY-SA 4.0 | Gage Skidmore (2025) | Commons |
| Satya Nadella | nadella-satya.jpg | CC BY-SA 4.0 | Brian Smale and Microsoft (2017) | Commons |
| Kevin O'Leary | oleary-kevin.jpg | CC BY-SA 4.0 | Philip Romano (2023) | Commons |
| Sundar Pichai | pichai-sundar.jpg | CC BY 4.0 | Lukasz Kobus, European Commission (2023) | Commons |
| Doina Precup | precup-doina.jpg | CC BY-SA 4.0 | Robincantin (2018) | Commons |
| Brad Smith | smith-brad.jpg | CC BY 2.0 | Web Summit (2018) | Commons |
| Danielle Smith | smith-danielle.jpg | CC BY 2.0 | Manning Centre, photo Jake Wright (2014) | Commons |
| Rick Smith | smith-rick.jpg | CC BY-SA 4.0 | Rp032923 (2019) | Commons |
| Evan Solomon | solomon-evan.jpg | CC BY 2.0 | Eurasia Group (2023) | Commons |
| Lisa Su | su-lisa.jpg | CC BY 4.0 | Fuzheado (2024) | Commons |
| Ilya Sutskever | sutskever-ilya.jpg | CC BY-SA 4.0 | Eladkarmel (2023) | Commons |
| Richard S. Sutton | sutton-richard.jpg | CC BY-SA 4.0 | Xuthoria (2025) | Commons |
| Raquel Urtasun | urtasun-raquel.jpg | CC BY-SA 4.0 | Raquel Urtasun (2021) | Commons |
| Mark Zuckerberg | zuckerberg-mark.jpg | Public domain (US federal) | The White House (2025) | Commons |
| Sam Altman | altman-sam.jpg | CC BY 4.0 | Office of the Prime Minister of Japan (2025) | Commons |
No acceptable free portrait exists on Wikimedia Commons for the following 17 people, and their image fields are set to null in the data file. Do not substitute a press photograph, corporate headshot or LinkedIn image for any of them.
Alex Krizhevsky, Tim Hodgson, Michael Sabia, Charlotte Mitha, Aaron Engen, Jason Fitzsimmons, Victor Dodig, Darren Entwistle, Mirko Bibic, Avik Dey, Joel Hunter, Todd Coleman, Shawn Longman, Isaac Laboucan-Avirom, Crystal Kissel, David Pickup, Blake Shaffer.
Two additional people who appear in the narrative also have no free portrait and no full record: Sara Hastings-Simon of the University of Calgary and Andrew Leach of the University of Alberta.
The research behind this book was produced on 2 September 2026 by fourteen artificial intelligence research agents working in parallel, one per dimension of the question. Each was given the same instructions: prefer primary sources, record a date and a link for every figure, cross-check headline numbers against at least two sources where possible, distinguish announced from under construction from operating, flag anything that could not be verified rather than dropping it, and write for a graduate business reader who does not have an engineering background.
Each agent produced three artifacts. A written brief of roughly seven thousand words, with key takeaways, tables, a narrative, a contested-figures section, open questions and a numbered source list. A machine-readable dataset in which every number carries its unit, year, region and source link. And a folder of downloaded primary documents with a manifest recording the file, the source, the publisher, the date and why it matters. Between them the agents ran roughly five hundred searches and saved 884 files totalling 716 megabytes. All twelve datasets validate as JSON, and every downloaded PDF was checked to confirm it is a real document rather than a saved error page.
This book is those 12 briefs, reordered into a single argument, with the front matter, chapter openers, figures and appendices added. The charts were generated from the datasets rather than redrawn by hand, so a figure and the table beside it cannot disagree. Nothing in the briefs was rewritten to make the argument tidier.
Every figure that appears in the executive summary, on a chapter opener or in a chart was reconciled against its source during preparation. Four unit errors were found and corrected in the companion software during that pass, all of them factors of a thousand in energy and emissions arithmetic. The figures used in the classroom materials were independently re-verified, and five of six needed rewording for precision.
The full body text of each brief has not been line-by-line fact checked. That is the honest limit of this document. Several claims were found to be unverifiable and are marked in each chapter's contested section. One research agent was interrupted by a usage limit before it could write its download manifest, which was afterwards reconstructed from the files on disk and is labelled as such.
It is not investment advice, and it is not a consulting deliverable. It was written to give graduate business students a shared, sourced foundation for an argument they were asked to make themselves, and to demonstrate what a person working with artificial intelligence tools can now assemble in a day. Where it expresses a view, in the executive summary and in the chapter openers, that view is the author's.
Two scores in the companion software are explicitly the author's judgement rather than published data: how much realistic spare room each province has, and how strong its social licence is. Both are shown with their reasoning. The per-province ceilings on project size in the siting tool are also judgement, with one exception: British Columbia's 145 megawatt limit per project, which is written into B.C. Reg. 8/2026.
The book is generated by research/book/build_book.py, which reads the briefs and datasets and writes
the HTML that becomes this PDF. The datasets are in research/data/, the briefs in
research/briefs/, the primary documents in research/downloads/, and the interactive
companion in research/app/. Re-running the build after editing any dataset regenerates every chart.
Every large Canadian data-centre project found in the research, ordered by announced size. Rows marked tracker come from an independent tracker and are not confirmed against filings. "Announced" is not "built": read the status field before using any of these figures.
Price is the large-power industrial rate for a 50,000 kilowatt customer at 85 per cent load factor, rates in effect 1 April 2025. Carbon intensity is the latest year available. Announced megawatts is the sum of every project found in the inventory, at every stage.
| Province | Price ¢/kWh | Non-emitting | gCO2/kWh | Announced MW | Supply outlook | The rule on large loads |
|---|---|---|---|---|---|---|
| British Columbia BC Hydro | 6.72 | 90.6% | 15 | 650 | deficit in dry years | Bill 31 (Royal Assent 27 Nov 2025): competitive call for demand; 300 MW AI + 100 MW data centres for Feb 2026 to Feb 2028 (150 + 50 MW in 2028-29); projects 10 to 145 MW; $25,000/MW bid security; applications closed 9 Mar 2026, results Sept 2026; about 800 MW |
| Alberta AESO (system operator), deregulated market | 7.99 | 21.6% | 490 | 25,346 | surplus energy, deficit firm connection capacity | AESO interim limit 1,200 MW allocated to GLDC (970 MW) and Keephills (230 MW); Phase 2 framework under development; Data Centre Regulation AR 117/2026 defines large data centre at 75 MW and prioritizes tethered projects with their own generation or storage. Pr |
| Saskatchewan SaskPower | 8.05 | 18.5% | 730 | 450 | constrained by dispatchable baseload | No cap or formal allocation process; Bell AI Fabric 300 MW near Regina ($1.7 billion initial, $12 billion total) with 300 MW gas backup, construction from spring 2026. |
| Manitoba Manitoba Hydro | 5.09 | 99.6% | 2.0 | 0 | surplus largely committed; tight by 2029 | Manitoba Hydro Act changes in force 1 Sept 2025: every request above 5 MW screened for eligibility and feasibility; cryptocurrency mining ineligible; 100 MW Jet.AI proposal rejected June 2026 (secondary source). |
| Ontario IESO, Hydro One, OPG | 12.66 | 82.5% | 38 | 27 | growing deficit from early 2030s | Electricity Act s.28.1 in force Dec 2025 (secondary source): connection of specified load facilities subject to regulatory requirements; Energy for Generations (July 2025) prioritizes data centres with local benefits; data centres 13% of new demand by 2035; IC |
| Quebec Hydro-Quebec | 5.52 | 98.7% | 1.7 | 188 | deficit emerging; surplus era over | Ministerial authorization required for any data centre load of 5 MW or more (since 2025); Bill 69 comparative allocation; proposed Rate CD about 13 cents/kWh for data centres (double current large-power rates), effective late 2026 subject to Regie; underuse ch |
| New Brunswick NB Power | 10.63 | 47.0% | 300 | 390 | deficit forecast by 2028 | No framework; NB Power seeks flexible, interruptible data centre loads; Lorneville (Saint John) proposal 190 MW (CBC Nov 2025) to 390 MW (secondary, Aug 2026). |
| Nova Scotia Nova Scotia Power; IESO Nova Scotia | 13.43 | 26.4% | 690 | 0 | deficit; coal exit by 2030 | No data centre framework; premier (June 2026): no active proposal, supply security first. |
| Newfoundland and Labrador NL Hydro | 7.66 | 97.4% | n/a | 0 | large surplus committed to Quebec | No data centre framework. |
| Prince Edward Island Maritime Electric | 11.27 | 99.0% | n/a | 0 | import dependent | None. |
Dated policy events from January 2024 to August 2026, federal, provincial and municipal.
Trade and technology-control events from January 2025 to August 2026, with the rate or value where one applies.
Terms used in this book, in plain language.
Every distinct source referenced by the datasets behind this book, 534 in total, ordered alphabetically. Each chapter also carries its own numbered source list with publisher and date. The downloaded documents themselves, 884 files and 716 megabytes, sit in research/downloads/ with a manifest per folder.
What this is, and how it differs from the other briefs. During the hardware research (brief 09) a sub-agent produced this separate body of findings on the terrestrial alternatives to grid power: small modular reactors, gas with and without carbon capture, geothermal, hydro uprating, flexible and curtailable load, and waste-heat reuse. It did not pass through the editing that the numbered briefs received, so it is filed here as a raw research note rather than as a chapter of the book.
Treat it accordingly. Every figure carries the URL it came from, and the note is explicit about which numbers are company claims, which are regulator or laboratory figures, and which sources could not be opened because of anti-scraping walls. Read those caveats before quoting anything.
Why it is worth keeping. Three findings in here are not covered anywhere else in this research set: the Duke University flexible-load study, which is the cheapest and fastest of all the options; the fact that almost none of the announced gas-for-AI projects actually commit to carbon capture; and the honest gaps in Canada, which has no confirmed reactor-to-data-centre agreement, no Canadian equivalent of the Duke study, and outside one Quebec greenhouse project no data-centre district heating with published figures.
The cheapest and fastest of the seven options is not a technology at all. It is agreeing to switch off occasionally. Duke University found that 76 to 98 gigawatts of new load could join the United States grid today if it accepted curtailment for 85 to 177 hours a year. Google has already contracted a gigawatt of exactly that. Compare it with Darlington: C$20.9 billion and more than five years for 1.2 gigawatts.
Darlington New Nuclear Project, Ontario. The only one of these actually being built.
| Item | Figure |
|---|---|
| Capacity per unit, GE Vernova Hitachi BWRX-300 | 300 MWe |
| Total for four units | 1,200 MW |
| Total capital cost, four units | C$20.9 billion (2024 dollars) |
| First unit, including shared infrastructure | C$7.7 billion |
| Fourth unit projected | C$4.1 billion, about 33% cheaper than the first |
| Licence to construct issued | 4 April 2025, valid to 31 March 2035 |
| Operating licence application | 25 March 2026 |
| Target in service, unit 1 | end of 2030; remaining units mid-2030s |
Announced economics, from the province and the federal Major Projects Office, are claims rather than outcomes: up to 18,000 annual construction jobs, 2,500 operating jobs, C$38.5 billion added to GDP over 65 years, more than 80% of spending to Canadian firms.
Sources: CNSC, World Nuclear News on the budget, Major Projects Office.
Reactor deals signed for data centres, all outside Canada and all pre-construction.
| Buyer and partner | Capacity | Announced | Status |
|---|---|---|---|
| Google with Kairos Power | up to 500 MW | 14 Oct 2024 | announced, first online target 2030 |
| Amazon with X-energy and Energy Northwest | 320 MW initial, up to 960 MW | Oct 2024 | pre-permit, operations in the 2030s |
| Meta, following its Dec 2024 request for proposals | up to 6.6 GW by 2035 | 9 Jan 2026 | announced: TerraPower 2.8 GW, Oklo 1.2 GW, Vistra 2.1 GW plus 433 MW of uprates |
| Microsoft with Constellation, Three Mile Island unit 1 restart | 835 to 837 MW | 20 Sep 2024 | US$1.6 billion, US DOE loan of US$1.0 billion closed Nov 2025 |
The Canadian finding is a negative one. No confirmed, signed Canadian reactor-to-data-centre power agreement exists in any primary source. SaskPower's own pages still state that no technology and no site have been selected. New Brunswick's utility news feed carries no reactor items to 31 August 2026. Darlington is utility generation for the grid, not contracted to any named data centre.
The framing point worth teaching: almost none of the announced gas-for-AI projects commit to carbon capture. It is repeatedly described as flexibility to add later.
Alberta. AESO's own June 2025 figure is 29 proposed projects and more than 16 GW seeking connection, against an interim limit of 1,200 MW to 2028, fully allocated to two projects: GLDC Load at 970 MW and Keephills Phase I at 230 MW. The widely quoted 20.7 GW figure appears in commentary, not on any AESO page, so cite it as reported. Phase 2 work ran from November 2025 to April 2026 and covers tethering agreements, with no curtailable-load provisions detailed. AESO newsroom, AESO large load projects.
A correction worth carrying. The C$100 billion figure attached to Alberta's AI Data Centres Strategy does not appear in the strategy document itself, which also contains no megawatt or gigawatt targets. It comes from ministerial statements reported in the press. Strategy PDF
Wonder Valley is registered in Alberta's major projects registry with status "proposed": phase 1 of 1.4 GW at C$12.0 billion, 7.5 GW and more than $70 billion at full build, natural gas with possible geothermal, no construction start recorded. Registry
Fervo Energy is the reference case for engineered geothermal.
| Item | Figure |
|---|---|
| Project Red, Nevada, demonstration | 3.5 MW, online 2023 |
| Drilling cost per well, first four Cape wells | US$9.4M falling to US$4.8M |
| Fastest Cape well | 21 days, a 70% reduction against 2022 |
| Cape Station, Utah | Phase I about 100 MW, Phase II 400 MW, total 500 MW |
| Status as at Q2 2026 | under construction; first power targeted Q4 2026 |
| Phase II target all-in cost | US$5,500 per kW |
| Google power purchase agreements | 115 MW Nevada (Jun 2024) plus 396 MW Cape Station (1 Sep 2026), option for about 600 MW more |
| Long-term target | 1.1 GW by 2030 |
Eavor, a Calgary company, achieved first electricity at Geretsried in Germany on 5 December 2025, rated 8.2 MW electric, about a year behind its original target, supported by a EUR 91.6 million European Innovation Fund grant. Eavor
The Canadian reality check, and the best single number in this note. Canada's total installed geothermal electricity capacity in 2024 was 6 megawatts, out of 156,388 MW nationally. Statistics Canada Table 25-10-0022-01
United States Department of Energy and Oak Ridge National Laboratory found that of a net 2.1 GW added to the American hydro fleet between 2010 and 2022, 1.4 GW came from upgrading existing plants, and that across the 155 plants with additions the median capacity increase was 15%, achievable through runner replacement and generator rewinds. The pace has since slowed from 193 MW a year to 66 MW a year. US Hydropower Market Report 2023
Hydro-Québec's 2035 Action Plan commits C$155 to 185 billion by 2035 for 8,000 to 9,000 MW of additional capacity, of which 3,800 to 4,200 MW is hydropower, plus 1,500 to 1,700 MW of wind and 1,600 to 1,800 MW from energy savings. Action Plan 2035
Canada's installed hydro capacity in 2024 was 83.05 GW, 53.1% of the national total, led by Quebec at 40.70 GW, British Columbia at 16.39 GW and Newfoundland and Labrador at 7.59 GW.
Norris, Profeta, Patino-Echeverri and Cowie-Haskell (2025), Rethinking Load Growth, Nicholas Institute, Duke University, NI R 25-01, published 13 February 2025. Nine years of hourly data across 22 balancing authorities serving 95% of United States peak load.
| Curtailment accepted | New load that could be integrated | Curtailment hours a year | Average event |
|---|---|---|---|
| 0.25% of uptime | 76 GW, about 10% of US peak demand | 85 | 1.7 hours |
| 0.5% | 98 GW | 177 | 2.1 hours |
| 1.0% | 126 GW | 366 | 2.5 hours |
| 5.0% | 215 GW | 1,848 | 4.5 hours |
United States systems run at a 53% average load factor, which is why the headroom exists. At the 0.5% limit, PJM alone offers 18 GW. Note that 88% of curtailment hours still retain at least half the new load.
Landing page. The institute's site blocks automated retrieval; the full text is also filed in an Illinois Commerce Commission docket at icc.illinois.gov, and the authors' own slide deck is at ISO New England.
Google has contracted a gigawatt of it. On 19 March 2026 Google said it had integrated 1 GW of demand response into long-term energy contracts with Indiana Michigan Power, the Tennessee Valley Authority, Entergy Arkansas, Minnesota Power and DTE Energy, by limiting or shifting machine-learning workloads. Its own caveat is that flexibility is limited and location-specific. Google
Emerald AI reports demonstrated pilots including a 25% load reduction sustained over three hours in Phoenix with Salt River Project, and a 96 MW power-flexible reference architecture in Virginia with Nvidia, Digital Realty and Dominion. These are company claims. Emerald AI
The Canadian gap. There is no published Canadian equivalent of the Duke study and no Canadian curtailable-load programme for data centres with verifiable megawatt figures. AESO's Phase 2 work is about connection sequencing and tethering, not curtailment. Ontario's system operator treats data centres as an uncertain step load rather than a flexibility resource. This is a genuine gap and a good student question.
QScale Q01, Lévis, Quebec, is the Canadian example. The campus is 142 MW with 114 MW of protected customer load, claims a power usage effectiveness below 1.2 and free cooling up to 80% of the year, and says up to 96 MW of waste heat could be distributed, enough to heat more than 15,000 Quebec households, with agricultural targets of 2,800 tonnes of small fruit and more than 80,000 tonnes of tomatoes a year. Every one of those is a projection or a potential, not a delivered figure. No primary source gives greenhouse hectares built, produce actually delivered, or carbon dioxide actually avoided. QScale Q01, Énergir partnership
Meta Odense, Denmark projects 165,000 MWh a year recovered, described as enough to warm 11,000 homes. Again a design projection; Meta does not publish delivered megawatt hours. Meta
Stockholm Exergi supplies the most useful commercial number in this section: it pays about 2 million Swedish krona a year for heat deliveries of 1 MW, which turns a cooling cost into a revenue line. Its network runs 3,000 km of heating pipe and 300 km of cooling pipe. Stockholm Exergi
Outside QScale, no other Canadian data-centre district heating project with published figures was found.
Generation mix, 2025, Statistics Canada Table 25-10-0015-01, total 625.2 TWh: hydro 343.37 TWh (54.92%), combustible fuels 143.43 (22.94%, of which non-renewable 134.14), nuclear 81.57 (13.05%), wind 50.49 (8.08%), solar 5.96 (0.95%). Provincial 2025 shares: Quebec 92.8% hydro, British Columbia 88.7% hydro, Ontario 46.1% nuclear, Alberta 76.0% combustible.
Canada Energy Regulator, Canada's Energy Future 2026, published 9 April 2026. Electricity demand grows 30% to 120% by 2050 depending on scenario. In the higher scenario, data centres are about a quarter of all demand growth, roughly 100 TWh. Total capacity reaches 310 GW by 2050. CER
Ontario system operator, 2026 Annual Planning Outlook, published 20 March 2026. Commercial data-centre demand grows from 4.5 TWh in 2027 to 22.6 TWh in 2050 in the reference case, 28.4 TWh in the high case and 14 TWh in the low case, which counts only projects with a completed system impact assessment. For contrast Ontario's entire commercial sector excluding data centres grows 41% over the same period. IESO
Hydro-Québec puts current data-centre peak at about 200 MW, growing to nearly 1,000 MW by 2035, with blockchain at about 115 MW and no growth expected.
The Nicholas Institute, Constellation, the Nuclear Regulatory Commission, Ontario Power Generation and Equinix all block automated retrieval. Figures attributed to them here came from mirrors, regulatory dockets or partner releases, and are labelled as such above. Open them in a browser before quoting.
This note went through an alarming episode. The research agent that produced it first delivered a long, heavily cited report. It then retracted the report and claimed it had fabricated the citations. It then withdrew that retraction and said the material was genuine after all.
Rather than take any of those three claims on faith, the underlying files were located on disk, and one high-stakes claim was checked against the primary source.
The result: the research is genuine and, on the test applied, accurate. The three source reports exist, run to 1,009 lines and carry 131 source URLs between them. The PJM capacity-price table, the most consequential set of numbers here, was verified line by line against PJM's own auction report. Every figure matched exactly, including the clearing prices, the cleared unforced capacity of 138,317.8 megawatts, and the price cap and floor. That report is saved alongside the note.
The lesson for a classroom is worth stating plainly. An AI research agent asserted twice without checking: once that its work was complete, and once that its work was invented. Both assertions were wrong, and the second would have destroyed good work. The fix in each case was to go and look at the artifact. That is the habit this whole project is trying to teach.
Everything below carries a source. The sections on Japan, Korea, Maharashtra and Uttar Pradesh remain genuinely unresearched, because several government sites blocked automated access. Those gaps are marked, and the agent's own "do not assert" list at the end is real and is the most useful part of the note.
Full source reports and the verification PDF: research/downloads/13-tariffs-and-large-load-rules/.
Quebec. Hydro-Québec has proposed a data-centre rate of 13 cents per kWh for loads above 5 MW, and 19.5 cents for cryptocurrency, announced 19 February 2026. It is proposed, not approved: it sits with the Régie de l'énergie as docket R-4333-2026, status open, with procedural decisions D-2026-025, D-2026-045 and D-2026-077. Quebec's data centres currently draw about 190 MW and blockchain about 115 MW.
The detail that news coverage misses: data centres do not take Rate L, which is reserved for subscriptions linked primarily to an industrial activity. They take Rate LG. From 1 April 2026 the two differ:
| Demand charge | Energy charge | |
|---|---|---|
| Rate L, industrial | $15.027 per kW | 3.821 cents per kWh |
| Rate LG, what a data centre pays | $16.571 per kW | 4.324 cents per kWh |
Rate LG also carries an unused available capacity charge of $38.502 per kW, which applies when demand falls below 60% of contracted capacity. Several operators are challenging its validity in the Québec Superior Court.
Bill 69 is in force. It requires ministerial authorisation for any request of 5 MW or more, or 50 kW or more for cryptographic use, with a 15 working day decision deadline for requests up to 50 MW at a site already served.
Sources: Hydro-Québec press release of 19 February 2026; the Régie docket page for R-4333-2026; Hydro-Québec's own tariff PDF; the official Bill 69 statute PDF.
Ontario. The Data Centre Playbook is a draft, out for comment under ERO notice 026-0853 until 12 September 2026. It proposes a separate Global Adjustment class for new data centres above about 1 MW, which would be ineligible for the Industrial Conservation Initiative. No special data-centre rate is in force in Ontario today. The IESO's 2026 Annual Planning Outlook forecasts Ontario demand growing 65% by 2050, with data centres 8.6% of demand in 2050 and an 8 TWh need emerging in 2032.
Alberta. The 1,200 MW interim limit announced 4 June 2025 applies at a 75 MW threshold. It was set against 29 projects and more than 16 GW of requests, and went entirely to two projects: GLDC Load at 970 MW and Keephills Phase I at 230 MW.
The bring-your-own-power route narrowed on 3 June 2025, when the Alberta Utilities Commission rejected the Coaldale project, ruling that self-supply generation cannot span multiple properties separated by roads and railways. Alberta's Bill 8 is referenced in commentary but could not be verified and should not be cited.
British Columbia, the finding worth knowing. BC gives qualifying data centres a discount, not a penalty. Rate Schedule 1894, the Clean BC Industrial Electrification Rate, treats a data centre as an "Innovation Customer" if contract demand exceeds 10,000 kVA, annual consumption exceeds 70 GWh, and the plant is not mining cryptocurrency. The rate is a multiplier on standard transmission service: 0.80 in years 1 to 5, 0.87 in year 6, 0.93 in year 7.
Standard rates from 1 April 2026: Rate Schedule 1830, transmission service, $12.178 per kVA and 4.914 cents per kWh. Rate Schedule 1600, large general service, $13.83 per kW and 6.79 cents per kWh. Rate Schedule 1823 was cancelled on 1 April 2026.
BC's allocation is the 100 MW conventional plus 300 MW AI split over two years, capped at 145 MW per project, with $25,000 per MW of bid security. This split belongs to British Columbia. It has been misattributed to Quebec in circulating summaries. Quebec allocates case by case and publishes no aggregate cap.
Source: BC Hydro's own Electric Tariff PDF; BLG for the allocation process.
Ireland. The Commission for Regulation of Utilities published its Large Energy User Connection Policy, CRU2025236, on 12 December 2025, and it is in force. Above 10 MVA a data centre must provide onsite or proximate dispatchable generation or storage matching its import capacity. Everything at or above 1 MVA must source at least 80% of annual demand from additional renewable generation in Ireland, phased over six years. System operators had to publish a connection process by 31 March 2026.
Ireland's data centres used 7,663 GWh in 2025, 23% of metered electricity, up 10% on the year against 2% for all other users. The 2024 figure was 22%. Residential dwellings together are 28%. Source: the Central Statistics Office release.
The commonly cited 2028 end date for the Dublin connection moratorium could not be verified. The 2021 pause itself is well established.
Virginia. The State Corporation Commission approved a new GS-5 rate class for customers at or above 25 MW, effective 1 January 2027. Large load customers must take and pay for service for at least 14 years, pay at least 85% of transmission and distribution costs monthly regardless of use, and post collateral of up to 60% of minimum charges. Customers served before 1 January 2016 are exempt.
The useful nuance: independent modelling by Arcadia found GS-5 can be cheaper than the existing GS-4 for a high-load-factor data centre. What GS-5 unambiguously does is transfer risk, through the 14-year term and the 85% floor. The popular framing that it simply makes data centres pay more is contested.
Source: the SCC's own fact sheet; Dominion's filed GS-4 tariff.
Senate Bill 6 became law in June 2025 and is being implemented through five separate PUCT projects, numbered 58479, 58480, 58481, 58482 and 58484. The interconnection standard, 16 TAC 25.194, was published for comment on 12 March 2026 with comments due 17 April 2026, and is proposed, not adopted. It applies at 75 MW. Large loads interconnected after 31 December 2025 must be curtailable during firm load shed. ERCOT's Batch Zero process groups projects of 75 MW and above.
As of a PUCT presentation in October 2025, large-load interconnection requests totalled 189 GW, nearly 69% of it data centres.
By June 2026 ERCOT reported more than 438 GW of large-load requests, nearly 89% of it data centres. That figure is an upper bound on speculative interest, not a forecast. ERCOT's own adjusted 2030 peak forecast is 139 GW, because it discounts data-centre requests to 49.8% of requested megawatts based on what actually energised at sites commissioned in 2022 to 2024, and officer-letter loads to 55.4%. From summer 2027 ERCOT models data centres as 100% curtailable. Proposed fees would be $50,000 per MW of financial security plus a $50,000 per MW non-refundable interconnection fee, so roughly $30 million for a 300 MW project before construction. Note that the same March 2026 document states $100,000 per MW in its preamble and $50,000 in the rule text; use the rule text.
The Energy Efficiency Act defines a data centre at 300 kW of non-redundant nominal connected load and sets binding limits:
| Requirement | Threshold |
|---|---|
| Power usage effectiveness, existing sites | 1.5 or below from 1 July 2027; 1.3 or below from 1 July 2030 |
| Power usage effectiveness, sites starting from 1 July 2026 | 1.2 or below |
| Waste heat reuse | 10% from July 2026, 15% from 2027, 20% from 2028 |
| Renewable electricity, balance-sheet basis | 50% from 1 January 2024, 100% from 1 January 2027 |
Germany's new industrial electricity price floor of 50 euros per megawatt hour was approved as state aid in April 2026 under case SA.120495, running 2026 to 2028 with a budget of 3.8 billion euros. Data centres almost certainly do not qualify, because eligibility follows a list of manufacturing and mining activities, and data processing and hosting is neither. Treat that last point as a strong inference rather than a verified fact. A 2026 amendment to the Act is in draft and its numbers are not verified.
Hydro-Québec's North American comparison, at 50,000 kW and 85% load factor, rates in effect 1 April 2025, Canadian cents per kWh excluding taxes. This is the single best exhibit in the note.
| City | ¢/kWh | City | ¢/kWh |
|---|---|---|---|
| Winnipeg | 5.09 | Chicago | 9.25 |
| Montréal | 5.52 | Toronto | 12.66 |
| Vancouver | 6.72 | Houston | 12.90 |
| Calgary | 7.99 | New York | 22.88 |
| Edmonton | 8.05 | Boston | 24.58 |
| 21-city average | 11.61 |
Quebec's proposed 13 cents would sit above that 21-city average, above Toronto and above Houston.
United States Energy Information Administration, industrial, US cents per kWh: Texas 6.58 in June 2026 and 6.65 year to date; Virginia 9.31 and 10.08; Pennsylvania 8.87 rising to 10.91 year to date; United States average 9.17 and 8.89.
Eurostat, industrial, euro cents per kWh, second half of 2025. Band ID is 2,000 to 19,999 MWh a year, band IG is 150,000 MWh and above, which is the hyperscale band. Prices excluding all taxes:
| Country | Band ID | Band IG |
|---|---|---|
| Norway | 6.38 | 4.08 |
| Sweden | 8.46 | 6.39 |
| Netherlands | 14.25 | 9.19 |
| Germany | 16.13 | 11.90 |
| Ireland | 21.18 | 15.62 |
| European Union average | 15.96 | 10.96 |
Ireland is the most expensive non-household market in the Union. Note how far apart the two bands are: a hyperscale campus pays roughly a third less than a mid-sized industrial user in the same country, which is why quoting the wrong band is the commonest error in cross-country price comparison.
These figures were independently verified against PJM's own 2028/2029 Base Residual Auction Report, saved in the downloads folder.
| Delivery year | Clearing price, $/MW-day | Cleared UCAP, MW | Total cost |
|---|---|---|---|
| 2024/25 | 28.92 | 147,478.9 | $2.2bn |
| 2025/26 | 269.92 | 135,684.0 | $14.7bn |
| 2026/27 | 329.17 | 134,205.3 | $16.1bn |
| 2027/28 | 333.44 | 134,478.1 | $16.4bn |
| 2028/29 | 325.00 | 138,317.8 | $16.4bn |
Prices are held down only by a temporary cap and floor of $256.75 and $138.25 per MW-ICAP, which are $325.00 and $175.00 on an unforced capacity basis. PJM's own no-collar simulation says 2027/28 would otherwise have cleared at $529.80, about $9.9 billion higher. The last two auctions both cleared at a 14.4% installed reserve margin, well below the 20% target.
For a 100 MW data centre in 2027/28, applying the forecast pool requirement, that is roughly $11 million a year in capacity charges alone, against about $1 million three years earlier. PJM attributes 30 GW of 32 GW of forecast demand growth to 2030 to data centres.
PJM's Interim Resource Adequacy Service, filed with FERC on 13 August 2026 and pending, would require new large loads above 50 MW to bring their own generation, curtail them at the first emergency level ahead of residential customers, and from the 2029/2030 auction stop new large loads that bring no new supply from counting toward the capacity everyone else pays for.
This is the single best argument for siting in Canada, and the single best warning about what happens when a grid operator runs out of room.